Article
Publication date: 20 February 2024

Huy Minh Vo, Jyh-Bin Yang and Veerakumar Rangasamy

Construction projects commonly encounter complicated delay problems. Over the past few decades, numerous delay analysis methods (DAMs) have been developed. There is no consensus…

Abstract

Purpose

Construction projects commonly encounter complicated delay problems. Over the past few decades, numerous delay analysis methods (DAMs) have been developed. There is no consensus on whether existing DAMs effectively resolve delays, particularly in the case of complex concurrent delays. Thus, the primary objective of this study is to undertake a comprehensive and systematic literature review on concurrent delays, aiming to answer the following research question: Do existing delay analysis techniques deal with concurrent delays well?

Design/methodology/approach

This study conducts a comprehensive review of concurrent delays by both bibliometric and systematic analysis of research publications published between 1982 and 2022 in the Web of Science (WoS) and Scopus databases. For quantitative analysis, a bibliometric mapping tool, the VOSviewer, was employed to analyze 68 selected publications to explore the co-occurrence of keywords, co-authorship and direct citation. Additionally, we conducted a qualitative analysis to answer the targeted research question, identify academic knowledge gaps and explore potential research directions for solving the theoretical and practical problems of concurrent delays.

Findings

Concurrent delays are a critical aspect of delay claims. Despite DAMs developed by a limited number of research teams to tackle issues like concurrence, float consumption and the critical path in concurrent delay resolution, practitioners continue to face significant challenges. This study has successfully identified knowledge gaps in defining, identifying, analyzing and allocating liability for concurrent delays while offering promising directions for further research. These findings reveal the incompleteness of available DAMs for solving concurrent delays.

Practical implications

The outcomes of this study are highly beneficial for practitioners and researchers. For practitioners, the discussions on the resolution process of concurrent delays in terms of identification, analysis and apportionment enable them to proactively address concurrent delays and lay the groundwork for preventing and resolving such issues in their construction projects. For researchers, five research directions, including advanced DAMs capable of solving concurrent delays, are proposed for reference.

Originality/value

Existing research on DAMs lacks comprehensive coverage of concurrent delays. Through a scientometric review, it is evident that current DAMs do not deal with concurrent delays well. This review identifies critical knowledge gaps and offers insights into potential directions for future research.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 23 January 2023

Bruno Falcón Silveira and Dayana Bastos Costa

Several studies have addressed the use of four-dimensional (4D) building information modeling (BIM) for construction management. However, the automation of the processes for…

Abstract

Purpose

Several studies have addressed the use of four-dimensional (4D) building information modeling (BIM) for construction management. However, the automation of the processes for generating 4D models and their integrated use with Location-Based Planning and the Last Planner® System is not well discussed. Therefore, this paper aims to develop a method for automating the generation and use of 4D BIM models integrated with Location-Based Planning and Last Planner® System supporting project control cycles.

Design/methodology/approach

The research strategy adopted was Design Science Research. The automated method for using the 4D models was developed and refined in two residential building projects in Brazil, along with 31 meetings and involving 11 direct users. The assessment of the proposed method focuses on four constructs: the impact of process automation, the impact on the identification and assessment of site progress and the planning process, ease of adoption and utility of the proposed method.

Findings

The results of this paper indicated increased adherence between planned and executed through an automated method for using the 4D models. The established routines enabled automating the link between the planning levels and the three-dimensional (3D) model, providing a more agile and updated data source and achieving 92.8% of user satisfaction regarding the deadline and frequency of delivery of the 4D model reports. Moreover, this study identified the relationships between the processes of the method proposed and Digital Models.

Originality/value

The primary scientific value achieved in this study is creating a method for automating processes and simplifying steps for the generation and use of 4D BIM models in the production planning and control cycles during the construction phase.

Details

Construction Innovation , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 19 July 2023

Ruochen Zeng, Jonathan J.S. Shi, Chao Wang and Tao Lu

As laser scanning technology becomes readily available and affordable, there is an increasing demand of using point cloud data collected from a laser scanner to create as-built…

Abstract

Purpose

As laser scanning technology becomes readily available and affordable, there is an increasing demand of using point cloud data collected from a laser scanner to create as-built building information modeling (BIM) models for quality assessment, schedule control and energy performance within construction projects. To enhance the as-built modeling efficiency, this study explores an integrated system, called Auto-Scan-To-BIM (ASTB), with an aim to automatically generate a complete Industry Foundation Classes (IFC) model consisted of the 3D building elements for the given building based on its point cloud without requiring additional modeling tools.

Design/methodology/approach

ASTB has been developed with three function modules. Taking the scanned point data as input, Module 1 is built on the basis of the widely used region segmentation methodology and expanded with enhanced plane boundary line detection methods and corner recalibration algorithms. Then, Module 2 is developed with a domain knowledge-based heuristic method to analyze the features of the recognized planes, to associate them with corresponding building elements and to create BIM models. Based on the spatial relationships between these building elements, Module 3 generates a complete IFC model for the entire project compatible with any BIM software.

Findings

A case study validated the ASTB with an application with five common types of building elements (e.g. wall, floor, ceiling, window and door).

Originality/value

First, an integrated system, ASTB, is developed to generate a BIM model from scanned point cloud data without using additional modeling tools. Second, an enhanced plane boundary line detection method and a corner recalibration algorithm are developed in ASTB with high accuracy in obtaining the true surface planes. At last, the research contributes to develop a module, which can automatically convert the identified building elements into an IFC format based on the geometry and spatial relationships of each plan.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 6 March 2023

Ningshuang Zeng, Xuling Ye, Yan Liu and Markus König

The unstable labor productivity and periodic planning method cause barriers to improving construction logistics management. This paper aims to explore a demand-driven mechanism…

Abstract

Purpose

The unstable labor productivity and periodic planning method cause barriers to improving construction logistics management. This paper aims to explore a demand-driven mechanism for efficient construction logistics planning to record the material consumption, report the real-time demand and trigger material replenishment from off-site to on-site, which is aided by Building Information Modeling (BIM) and the Kanban technique.

Design/methodology/approach

This paper follows the design science research (DSR) principles to propose a system of designing and applying Kanban batch with 4D BIM for construction logistics planning and monitoring. Prototype development with comparative simulation experiments of a river remediation project is conducted to analyze the conventional and Kanban-triggered supply. Two-staged industrial interviews are conducted to guide and evaluate the system design.

Findings

The proposed BIM-enabled Kanban system enables construction managers and suppliers to better set integrated on- and off-site targets, report real-time demands and conduct collaborative planning and monitoring. The simulation results present significant site storage and schedule savings applying the BIM-enabled Kanban system. Feedback and constructive suggestions from practitioners are collected via interviews and analyzed for further development.

Originality/value

This paper brings to the limelight the benefits of implementing BIM-enabled demand-driven replenishment to remove waste from the material flow. This paper combines lean production theory with advanced information technology to solve construction logistics management problems.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 19 January 2024

Mohamed Marzouk and Mohamed Zaher

Facility management gained profound importance due to the increasing complexity of different systems and the cost of operation and maintenance. However, due to the increasing…

58

Abstract

Purpose

Facility management gained profound importance due to the increasing complexity of different systems and the cost of operation and maintenance. However, due to the increasing complexity of different systems, facility managers may suffer from a lack of information. The purpose of this paper is to propose a new facility management approach that links segmented assets to the vital data required for managing facilities.

Design/methodology/approach

Automatic point cloud segmentation is one of the most crucial processes required for modelling building facilities. In this research, laser scanning is used for point cloud acquisition. The research utilises region growing algorithm, colour-based region-growing algorithm and Euclidean cluster algorithm.

Findings

A case study is worked out to test the accuracy of the considered point cloud segmentation algorithms utilising metrics precision, recall and F-score. The results indicate that Euclidean cluster extraction and region growing algorithm revealed high accuracy for segmentation.

Originality/value

The research presents a comparative approach for selecting the most appropriate segmentation approach required for accurate modelling. As such, the segmented assets can be linked easily with the data required for facility management.

Details

International Journal of Building Pathology and Adaptation, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 2398-4708

Keywords

Article
Publication date: 5 January 2024

Caroline Silva Araújo, Emerson de Andrade Marques Ferreira and Dayana Bastos Costa

Tracking physical resources at the construction site can generate information to support effective decision-making and building production control. However, the methods for…

Abstract

Purpose

Tracking physical resources at the construction site can generate information to support effective decision-making and building production control. However, the methods for conventional tracking usually offer low reliability. This study aims to propose the integrated Smart Twins 4.0 to track and manage metallic formworks used in cast-in-place concrete wall systems using internet of things (IoT) (operationalized by radio frequency identification [RFID]) and building information modeling (BIM), focusing on increasing quality and productivity.

Design/methodology/approach

Design science research is the research approach, including an exploratory study to map the constructive system, the integrated system development, an on-site pilot implementation in a residential project and a performance evaluation based on acquired data and the perception of the project’s production team.

Findings

In all rounds of requests, Smart Twins 4.0 registered and presented the status from the formworks and the work progress of buildings in complete correspondence with the physical progress providing information to support decision-making during operation. Moreover, analyses of the system infrastructure and implementation details can drive researchers regarding future IoT and BIM implementation in real construction sites.

Originality/value

The primary contribution is the system proposal, centralized into a mobile app that contains a Web-based virtual model to receive data in real time during construction phases and solve a real problem. The paper describes Smart Twins 4.0 development and its requirements for tracking physical resources considering theoretical and practical previous research regarding RFID, IoT and BIM.

Details

Construction Innovation , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 31 March 2023

Zul-Atfi Ismail

Green building (GB) maintenance is increasingly accepted in the construction industry, so it can now be interpreted as an industry best practice for maintenance planning. However…

Abstract

Purpose

Green building (GB) maintenance is increasingly accepted in the construction industry, so it can now be interpreted as an industry best practice for maintenance planning. However, the performance competency and design knowledge of the practice's building control instrument process can be affected by its evaluation and the information management of building information modelling (BIM)–based model checking (BMC). These maintenance-planning problems have not yet been investigated in instances such as the Grenfell Tower fire (14 June 2017, approximately 80 fatalities) in North Kensington, West London.

Design/methodology/approach

This study proposes a theoretical framework for analysing the existing conceptualisation of BIM tools and techniques based on a critical review of GB maintenance environments. These are currently employed on GB maintenance ecosystems embedded in project teams that can affect BMC practices in the automation system process. In order to better understand how BMC is implemented in GB ecosystem projects, a quantitative case study is conducted in the Malaysian public works department (Jabatan Kerja Raya (JKR)).

Findings

GB ecosystem projects were not as effective as planned due to safety awareness, design planning, inadequate track insulation, environmental (in) compatibility and inadequate building access management. Descriptive statistics and an ANOVA were applied to analyse the data. The study is reinforced by a process flow, which is transformed into a theoretical framework.

Originality/value

Industry practitioners can use the developed framework to diagnose BMC application issues and leverage the staff competency inherent in an ecosystem to plan GB maintenance environments successfully.

Details

Journal of Enterprise Information Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1741-0398

Keywords

Article
Publication date: 27 January 2023

S.M.A.H. Senanayake, Pamal Akila Manamperi Gunawardana, B.A.K.S. Perera and Dilakshan Rajaratnam

Construction cost management is one of the important processes that should be achieved effectively and accurately for successful project delivery. Modern-day construction cost…

Abstract

Purpose

Construction cost management is one of the important processes that should be achieved effectively and accurately for successful project delivery. Modern-day construction cost management demands a high level of spatial skills. Augmented reality (AR) can potentially increase the stakeholders’ spatial skills as a supportive technology to traditional cost management tools and techniques. AR is a breakthrough technology that could considerably ease execution in various industries, but AR applicability in cost management has not been studied extensively. Thus, this study aims to explore the use of AR in construction cost management tools and techniques.

Design/methodology/approach

Data were collected using a qualitative approach consisting of two rounds of the Delphi technique. A total of 22 experts in the construction and information technology fields were interviewed using a purposive sampling technique. The manual content analysis helped analyse data.

Findings

The study identified AR features with the potential to increase the usage of cost management tools and techniques. AR can enable spatial skills (abilities, thinking and tasks) in most cost management tools and techniques. However, technical, cultural and technical and cultural barriers obstruct the use of AR in the construction industry.

Originality/value

The usage of AR in construction cost management tools and techniques has not been examined in detail until now. Thus, the study was developed to meet the industry needs and fill the literature gap to investigate the potential use of AR in construction cost management tools and techniques.

Details

Journal of Engineering, Design and Technology , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1726-0531

Keywords

Article
Publication date: 16 November 2022

Hesam Khorrami Shad, Kenneth Tak Wing Yiu, Ruggiero Lovreglio and Zhenan Feng

This paper aims to explore augmented reality (AR) applications in construction safety academic literature and propose possible improvements for future scholarly works. The paper…

Abstract

Purpose

This paper aims to explore augmented reality (AR) applications in construction safety academic literature and propose possible improvements for future scholarly works. The paper explicitly focuses on AR integration with Construction 4.0 technologies as an effective solution to safety concerns in the construction industry.

Design/methodology/approach

This study applied a systematic review approach. In total, 387 potentially relevant articles from databases were identified. Once filtering criteria were applied, 29 eligible papers where selected. The inclusion criteria were being directly associated with construction safety focused on an AR application and AR interactions associated with the Construction 4.0 technologies.

Findings

This study investigated the structure of AR applications in construction safety. To this end, the authors studied the safety purposes of AR applications in construction safety: pre-event (intelligent operation, training, safety inspection and hazard alerting), during-event (pinpointing hazard) and post-event (safety estimation) applications. Then, the integration of AR with Construction 4.0 technologies was elaborated. The systematic review also revealed that the AR integration has contributed to developing several technical aspects of AR technology: display, tracking and human–computer interaction. The study results indicate that AR integration with construction is effective in mitigating safety concerns; however, further research studies are required to support this statement.

Originality/value

This study contributes to exploring applications and integrations of AR into construction safety in order to facilitate the leverage of this technology. This review can help encourage practitioners and researchers to conduct further academic investigations into AR application in construction safety.

Details

Smart and Sustainable Built Environment, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 2046-6099

Keywords

Article
Publication date: 23 January 2024

Dilan Weerasooriya, K.A.T.O Ranadewa and B.A.K.S Perera

Cyber-physical systems (CPS) enable the synergistic integration of virtual models with the physical environment. This integration is gaining recognition for its potential to…

Abstract

Purpose

Cyber-physical systems (CPS) enable the synergistic integration of virtual models with the physical environment. This integration is gaining recognition for its potential to enhance construction project information management, thereby contributing to improved cost management in construction. Similarly, quantity surveyor (QS) plays a key role in construction projects by estimating and monitoring construction costs. Consequently, this research aims to explore redefining the role of QSs by integrating CPS.

Design/methodology/approach

The research adopted an interpretivism stance to collect and analyse data. Two rounds of 21 and 19 semi-structured interviews were conducted, with experts selected through heterogeneous purposive sampling. Code-based content analysis was used to analyse the data using NVivo12. MS Visio data visualisation tool was used to present the findings.

Findings

It is empirically proven the potential of CPS to facilitate nine key roles of QSs in all stages of the RIBA plan of work through the identification of 15 CPS applications and technologies. Nine key roles of QSs that CPS can facilitate were identified as preliminary estimation, measurement and quantification, contract administration, preparation of BOQ, interim valuation and payments, tender and contract documentation, cost planning, cost control and procurement advice. The study explored how adopting CPS technologies can transform traditional quantity surveying practices and enhance their value within the construction industry.

Originality/value

The findings add to the body of knowledge by redefining the role of QS through the integration of CPS for the first time and then by highlighting the usages of CPS in the construction industry rather than limiting it to a specific sector of the construction industry, as previous studies have done. This research uncovers several other research arenas on CPS as being the very first research to evaluate CPS to facilitate key roles of QSs. The findings can enhance the awareness and the practical implementation of CPS by intervening to form more partnerships among application developers and industry leaders.

Details

Journal of Engineering, Design and Technology , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1726-0531

Keywords

1 – 10 of 20