1 – 10 of over 2000Abdulmohsen S. Almohsen, Naif M. Alsanabani, Abdullah M. Alsugair and Khalid S. Al-Gahtani
The variance between the winning bid and the owner's estimated cost (OEC) is one of the construction management risks in the pre-tendering phase. The study aims to enhance the…
Abstract
Purpose
The variance between the winning bid and the owner's estimated cost (OEC) is one of the construction management risks in the pre-tendering phase. The study aims to enhance the quality of the owner's estimation for predicting precisely the contract cost at the pre-tendering phase and avoiding future issues that arise through the construction phase.
Design/methodology/approach
This paper integrated artificial neural networks (ANN), deep neural networks (DNN) and time series (TS) techniques to estimate the ratio of a low bid to the OEC (R) for different size contracts and three types of contracts (building, electric and mechanic) accurately based on 94 contracts from King Saud University. The ANN and DNN models were evaluated using mean absolute percentage error (MAPE), mean sum square error (MSSE) and root mean sums square error (RMSSE).
Findings
The main finding is that the ANN provides high accuracy with MAPE, MSSE and RMSSE a 2.94%, 0.0015 and 0.039, respectively. The DNN's precision was high, with an RMSSE of 0.15 on average.
Practical implications
The owner and consultant are expected to use the study's findings to create more accuracy of the owner's estimate and decrease the difference between the owner's estimate and the lowest submitted offer for better decision-making.
Originality/value
This study fills the knowledge gap by developing an ANN model to handle missing TS data and forecasting the difference between a low bid and an OEC at the pre-tendering phase.
Rick Forster, Andrew Lyons, Nigel Caldwell, Jennifer Davies and Hossein Sharifi
The study sets out to demonstrate how a lifecycle perspective on complex, public-sector procurement projects can be used for making qualitative assessments of procurement policy…
Abstract
Purpose
The study sets out to demonstrate how a lifecycle perspective on complex, public-sector procurement projects can be used for making qualitative assessments of procurement policy and practice and reveal those procurement capabilities that are most impactful for operating effectively.
Design/methodology/approach
Agency theory, institutional theory and the lifecycle analysis technique are combined to abductively develop a framework to identify, analyse and compare complex procurement policies and practices in public sector organisations. Defence is the focal case and is compared with cases in the Nuclear, Local Government and Health sectors.
Findings
The study provides a framework for undertaking a lifecycle analysis to understand the challenges and capabilities of complex, public-sector buyers. Eighteen hierarchically-arranged themes are identified and used in conjunction with agency theory and institutional theory to explain complex procurement policy and practice variation in some of the UK’s highest-profile public buyers. The study findings provide a classification of complex buyers and offer valuable guidance for practitioners and researchers navigating complex procurement contexts.
Originality/value
The lifecycle approach proposed is a new research tool providing a bespoke application of theory by considering each lifecycle phase as an individual but related element that is governed by unique institutional pressures and principal-agent relationships.
Details
Keywords
Tennakoon Mudiyanselage Maheshi Pabasara Tennakoon, Nicholas Chileshe, Raufdeen Rameezdeen, J. Jorge Ochoa and Aparna Samaraweera
Offsite construction (OC) is an efficient method to reduce waste in the construction industry from a circular economy perspective. Yet, its uptake is subdued by the ambiguities…
Abstract
Purpose
Offsite construction (OC) is an efficient method to reduce waste in the construction industry from a circular economy perspective. Yet, its uptake is subdued by the ambiguities around its supply chain. Hence, the purpose of this study is twofold: to identify the OC project delivery models, the limitations in their procurement approach to facilitate the resilience of the supply chain and interventions to promote supply chain resilience (SCR) and to identify the gaps in the existing procurement process and propose further research areas that implement strategies to improve SCR.
Design/methodology/approach
The study was conducted as a systematic literature review. In total, 41 peer-reviewed research papers published between 2013 and 2023 were shortlisted through the preferred reporting items for systematic reviews and meta-analysis guidelines. A descriptive analysis was conducted, followed by a thematic analysis.
Findings
The descriptive analysis reveals that the emphasis on digitising OC has shifted to transforming the business model, procurement and supply chain with a human-centric view. In thematic analysis, the predictability of the SC partners and the probabilities of evaluating the prospects are revealed as arbitrary characteristics in the current procurement strategies. Rewarding collaborative relationships among SC partners and incorporating provisions to postpone the module delivery are some interventions to promote flexibility. Drafting comprehensive and effective contracts that address transparency issues and facilitating the need for continuous development of capabilities through procurement are among the further research avenues proposed.
Originality/value
This study is a precursor demonstrating the potential of the procurement process to implement the decrees of SCR for better goal congruence of the OC supply chain.
Details
Keywords
Abstract
Purpose
Competency frameworks can support public procurement capacity development and performance. However, literature on connecting professionalisation with national procurement contexts is limited. This paper aims to explain and conceptualise recent Romanian experience with developing bespoke competency frameworks at national level for public procurement that reflect the features of the Romanian public procurement system. The approach used could guide in broad-brush, mutatis mutandis, other (national) public procurement systems with comparable features, mainly those seeking a shift from a rather administrative function of public procurement towards a strategic function.
Design/methodology/approach
This case study reflects on the methodology used for analysing the Romanian public procurement environment in EU context to develop bespoke professionalisation instruments, and on ways to integrate competency management approaches in Romanian public procurement culture. That methodological mix has been mainly qualitative and constructionist, within an applied research approach. It combined desk research with empirical research and included legal research in this context.
Findings
A principled, methodological and pragmatic approach tailored to the procurement environment in question is essential for developing competency frameworks capable to resonate to and address the specific practical needs of that procurement system.
Social implications
Competency frameworks can uphold societal objectives through public procurement.
Originality/value
Using valuable insights into the development of the Romanian public procurement competency frameworks, the paper provides a conceptual framework for instilling competency management approaches to public procurement professional development where the latter is governed by a rather distinct, public administration, paradigm. This conceptual framework can guide other public procurement systems and stimulate further research.
Details
Keywords
Babar Ali, Ajibade A. Aibinu and Vidal Paton-Cole
Delay and disruption claims involve a complex process that often result in disputes, unnecessary expenses and time loss on construction projects. This study aims to review and…
Abstract
Purpose
Delay and disruption claims involve a complex process that often result in disputes, unnecessary expenses and time loss on construction projects. This study aims to review and synthesize the contributions of previous research undertaken in this area and propose future directions for improving the process of delay and disruption claims.
Design/methodology/approach
This study adopted a holistic systematic review of literature following Preferred Reporting Items for Systematic Reviews and Meta-Analysis guidelines. A total of 230 articles were shortlisted related to delay and disruption claims in construction using Scopus and Web of Science databases.
Findings
Six research themes were identified and critically reviewed including delay analysis, disruption analysis, claim management, contract administration, dispute resolution and delay and disruption information and records. The systematic review showed that there is a dearth of research on managing the wide-ranging information required for delay and disruption claims, ensuring the transparency and uniformity in delay and disruption claims’ information and adopting an end-user’s centred research approach for resolving the problems in the process of delay and disruption claims.
Practical implications
Complexities in delay and disruption claims are real-world problems faced by industry practitioners. The findings will help the research community and industry practitioners to prioritize their energies toward information management of delay and disruption claims.
Originality/value
This study contributes to the body of knowledge in delay and disruption claims by identifying the need for conducting more research on its information requirements and management. Subsequently, it provides an insight on the use of modern technologies such as drones, building information modeling, radio frequency identifiers, blockchain, Bigdata and machine learning, as tools for more structured and efficient attainment of required information in a transparent and consistent manner. It also recommends greater use of design science research approach for delay and disruption claims. This will help to ensure delay and disruption claims are the least complex and less dispute-prone process.
Details
Keywords
Na Zhang, Bon-Gang Hwang, Xiaopeng Deng and Fiona Tay
The Singapore construction sector is promoting performance improvement by implementing collaborative contracting (CC). For CC's successful implementation, there is a need to sieve…
Abstract
Purpose
The Singapore construction sector is promoting performance improvement by implementing collaborative contracting (CC). For CC's successful implementation, there is a need to sieve out the critical success factors (CSFs). Hence, this paper aims to explore factors influencing the adoption of CC and investigate the potential performance improvement by implementing CC.
Design/methodology/approach
Based on the literature review, 23 CSFs were identified and packaged to a questionnaire to evaluate the CSF's priority as well as CC's potential impact on the project performance. After prior validation, 165 potential respondents were drawn from survey list by using simple random sampling. Finally, 31 valid responses were received.
Findings
The survey result showed that the top five CSFs are mutual trust, all parties to commit fully, openness between parties, commitment to a win–win attitude and resource availability. The majority of respondents hold that CC implementation would improve overall project performance, decision effectiveness, cost, time, quality and risk performance.
Research limitations/implications
Directors, project managers, contractor managers and site engineers have different perceptions of CSFs. Also rather than meeting the same requirements in the implementation of CC, there are differences among projects with different values.
Originality/value
This study provides an in-depth understanding of the CSFs for industry practitioners adopting CC and CC's potential impact on project performance. This study is also helpful for authorities to formulate effective policies to push the implementation of CC.
Details
Keywords
Emmanuel Dele Omopariola, Abimbola Olukemi Windapo, David John Edwards, Clinton Ohis Aigbavboa, Sunday Ukwe-Nya Yakubu and Onimisi Obari
Previous studies have postulated that an advance payment system (APS) positively impacts the contractor's working capital and is paramount to ensuring an efficient and effective…
Abstract
Purpose
Previous studies have postulated that an advance payment system (APS) positively impacts the contractor's working capital and is paramount to ensuring an efficient and effective project cash flow process. However, scant research has been undertaken to empirically establish the cash flow performance and domino effect of APS on project and organisational performance.
Design/methodology/approach
The epistemological design adopted a positivist philosophical stance augmented by deductive reasoning to explore the phenomena under investigation. Primary quantitative data were collected from 504 Construction Industry Development Board (CIDB) registered contractors (within the grade bandings 1–9) in South Africa. A five-point Likert scale was utilised, and subsequent data accrued were analysed using structural equation modelling (SEM).
Findings
Emergent findings reveal that the mandatory use of an APS does not guarantee a positive project cash flow, an improvement in organisational performance or an improvement in project performance.
Practical implications
The ensuing discussion reveals the contributory influence of APS on positive cash flow and organisational performance, although APS implementation alone will not achieve these objectives. Practically, the research accentuates the need for various measures to be concurrently adopted (including APS) towards ensuring a positive project cash flow and improved organisational and project performance.
Originality/value
There is limited empirical research on cash flow performance and the domino effect of APS on project and organisational performance in South Africa, nor indeed, the wider geographical location of Africa as a continent. This study addresses this gap in the prevailing body of knowledge.
Details
Keywords
Sayed Muhammad Fawad Sharif, Yang Naiding and Sayed Kifayat Shah
Collaborative projects require overlapping skills and capabilities to facilitate knowledge transfer. However, not all kinds of learning are virtuous and some may lead to leakage…
Abstract
Purpose
Collaborative projects require overlapping skills and capabilities to facilitate knowledge transfer. However, not all kinds of learning are virtuous and some may lead to leakage of commercially valuable knowledge. The purpose of this paper is to explain and restrain leakage of organizational competitive knowledge in collaborative projects.
Design/methodology/approach
A total of 398 survey questionnaires are collected from project-based firms in Pakistan. We gathered data from horizontal and vertical collaborations. Analysis is conducted with transaction cost economics lens through Process Macro 3.0.
Findings
Findings suggest that partner’s learning intent (PLI) and distrust positively affect knowledge leakage, whereas human resource management (HRM) practices have negative effect on knowledge leakage. Furthermore, HRM practices negatively moderate the relationship between PLI and knowledge leakage and distrust positively mediates it.
Research limitations/implications
This study integrates HRM with knowledge management to restrain knowledge leakage and contributes to knowledge management and strategic management. This study examines knowledge leakage in the presence of passive opportunism.
Originality/value
This study explains how passive opportunism translates into opportunistic behavior. Besides, effectiveness of HRM practices are least surveyed to restrain passive and active opportunisms.
Details
Keywords
Elina Karttunen, Aki Jääskeläinen, Iryna Malacina, Katrina Lintukangas, Anni-Kaisa Kähkönen and Frederik G.S. Vos
This study aims to build on the dynamic capability view by examining dynamic capabilities associated with public value in public procurement.
Abstract
Purpose
This study aims to build on the dynamic capability view by examining dynamic capabilities associated with public value in public procurement.
Design/methodology/approach
A qualitative case study approach is used in this study. The interview and secondary data consist of eight cases of value-creating procurement from four public organizations.
Findings
The findings connect dynamic capabilities and public value in terms of innovation generation and promotion, well-functioning supplier markets, public procurement process effectiveness, environmental and social sustainability and quality and availability of products or services.
Social implications
Dynamic capabilities in public procurement are necessary to improve public procurement.
Originality/value
This study extends understanding of how sensing, seizing and transforming capabilities contribute to public value creation in both innovative and less innovative (i.e. ordinary) procurement scenarios.
Details
Keywords
John Aliu, Ayodeji Emmanuel Oke, Isaac I. Akinwumi, Rislan Abdulazeez Kanya and Lydia Uyi Ehiosun
This study aimed to investigate and analyze the level of awareness and adoption of distributed ledger technologies (DLTs) within the Nigerian construction industry. The focus was…
Abstract
Purpose
This study aimed to investigate and analyze the level of awareness and adoption of distributed ledger technologies (DLTs) within the Nigerian construction industry. The focus was on addressing the current state of DLT utilization, identifying challenges and opportunities and proposing strategies to enhance the integration of DLTs into the construction processes and practices of Nigerian professionals and organizations.
Design/methodology/approach
The research was underpinned by a robust theoretical and conceptual framework, drawing from established theories of technology adoption. A comprehensive literature review guided the identification of various DLT types. This informed the development of a well-structured questionnaire, which was then distributed to Nigerian construction professionals. The collected data underwent analysis using percentages, frequencies, mean scores, the Kruskal–Wallis H-test and the Shapiro–Wilk test.
Findings
A significant finding of this study reveals a generally low awareness and implementation of DLT among construction professionals in Nigeria. These findings emphasize the urgent need for comprehensive strategies to bridge the gap between awareness and adoption of DLT within the Nigerian construction industry.
Practical implications
Industry associations, regulatory bodies and educational institutions can collaborate to develop specialized programs aimed at familiarizing professionals with the benefits and applications of DLTs. Additionally, technology providers and policymakers can leverage these findings to design user-friendly interfaces and guidelines for seamless DLT integration into construction processes.
Originality/value
This study contributes to the existing body of knowledge by providing a comprehensive assessment of the awareness and adoption of DLTs specifically within the Nigerian construction industry. While the global recognition of DLT’s potential in construction is acknowledged, this research delves into a regional context, shedding light on the specific opportunities within Nigeria. Furthermore, the study’s identification of a gap between awareness and implementation highlights a critical area for future exploration and development in the field of construction technology adoption.