Search results

1 – 10 of 309
Article
Publication date: 18 November 2019

Tianqi Wang, Moatassem Abdallah, Caroline Clevenger and Shahryar Monghasemi

Achieving project objectives in constructionprojects such as time, cost and quality is a challenging task. Minimizing project cost often results in additional project duration and…

2232

Abstract

Purpose

Achieving project objectives in constructionprojects such as time, cost and quality is a challenging task. Minimizing project cost often results in additional project duration and might jeopardize quality, and minimizing project duration often results in additional cost and might jeopardize quality. Also, increasing construction quality often results in additional cost and time. The purpose of this paper is to identify and analyze trade-offs among the project objectives of time, cost and quality.

Design/methodology/approach

The optimization model adopted a quantitative research method and is developed in two main steps formulation step that focuses on identifying model decision variables and formulating objective functions, and implementation step that executes the model computations using multi-objective optimization of Non-Dominated Sorting Genetic Algorithms to identify the aforementioned trade-offs, and codes the model using python. The model performance is verified and tested using a case study of construction project consisting of 20 activities.

Findings

The model was able to show practical and needed value for construction managers by identifying various trade-off solutions between the project objectives of time, cost and quality. For example, the model was able to identify the shortest project duration at 84 days while keeping cost under $440,000 and quality higher than 85 percent. However, with an additional budget of $20,000 (4.5 percent increase), the quality can be increased to 0.935 (8.5 percent improvement).

Research limitations/implications

The present research work is limited to project objectives of time, cost and quality. Future expansion of the model will focus on additional project objectives such as safety and sustainability. Furthermore, new optimization models can be developed for construction projects with repetitive nature such as roads, tunnels and high rise buildings.

Practical implications

The present model advances existing research in planning construction projects efficiently and achieving important project objectives. On the practical side, the optimization model will support the construction industry by allowing construction managers to identify the highest quality to deliver a construction project within specified budget and duration, lowest cost for specified duration and quality or shortest duration for specified budget and quality.

Originality/value

The present model introduces new and innovative method of increasing working hours per day and number of working days per shift while analyzing labor working efficiency and overtime rate to identify optimal trade-offs among important project objectives of time, cost and quality.

Details

Engineering, Construction and Architectural Management, vol. 28 no. 1
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 1 February 2022

Chijoo Lee

Work crew productivity and the application of limited resources are necessary elements in construction duration delay analysis. This study thus proposes a method to analyze…

Abstract

Purpose

Work crew productivity and the application of limited resources are necessary elements in construction duration delay analysis. This study thus proposes a method to analyze construction delays and resource reallocation based on work crew productivity and resource constraints. The study also presents an economic feasibility analysis that maximizes economic effect by reducing construction duration, the cost of resource reallocation, delay liquidated damages (DLDs) and incentives for reducing contractual duration.

Design/methodology/approach

The proposed method involved three steps. First, work crew characteristics such as productivity, unit price and workload helped analyze delay information, including delay duration, reducible duration and daily reduced cost. Next, a goal programming method assessed resource reallocation based on the priority (as determined by decision-makers) of each constraint condition, such as the available number of workers, cost, goal workload and statutory working hours. Lastly, the level of reallocation was analyzed based on the results of the economic feasibility analysis and decision-makers’ delay attitudes.

Findings

A case study was performed to test the proposed method's applicability. Its involved sensitivity analysis indicated proposing to decision-makers a scenario based on the prioritization of economic feasibility. The proposed method's applicability proved high for decision-makers, as they can determine whether to reduce construction duration per the proposed data.

Originality/value

The proposed method's main contribution is the reallocation of resources to reduce construction duration based on work crew productivity and the prioritization of limited resources. The proposed method can analyze the differences in productivity between the plan and actual progress, as well as calculate the necessary number of workers. Decision-makers can then reduce the appropriate level of contractual duration based on their own delay attitude, constraint condition prioritization and results from daily economic feasibility analyses.

Details

Engineering, Construction and Architectural Management, vol. 30 no. 4
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 2 January 2024

Xin Zou and Zhuang Rong

In repetitive projects, repetition offers more possibilities for activity scheduling at the sub-activity level. However, existing resource-constrained repetitive scheduling…

Abstract

Purpose

In repetitive projects, repetition offers more possibilities for activity scheduling at the sub-activity level. However, existing resource-constrained repetitive scheduling problem (RCRSP) models assume that there is only one sequence in performing the sub-activities of each activity, resulting in an inefficient resource allocation. This paper proposes a novel repetitive scheduling model for solving RCRSP with soft logic.

Design/methodology/approach

In this paper, a constraint programming model is developed to solve the RCRSP using soft logic, aiming at the possible relationship between parallel execution, orderly execution or partial parallel and partial orderly execution of different sub activities of the same activity in repetitive projects. The proposed model integrated crew assignment strategies and allowed continuous or fragmented execution.

Findings

When solving RCRSP, it is necessary to take soft logic into account. If managers only consider the fixed logic between sub-activities, they are likely to develop a delayed schedule. The practicality and effectiveness of the model were verified by a housing project based on eight different scenarios. The results showed that the constraint programming model outperformed its equivalent mathematical model in terms of solving speed and solution quality.

Originality/value

Available studies assume a fixed logic between sub-activities of the same activity in repetitive projects. However, there is no fixed construction sequence between sub-activities for some projects, e.g. hotel renovation projects. Therefore, this paper considers the soft logic relationship between sub-activities and investigates how to make the objective optimal without violating the resource availability constraint.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 12 September 2008

Avninder Gill

This paper endeavors to critically examine the trade‐offs among project objectives and their underlying assumptions.

1835

Abstract

Purpose

This paper endeavors to critically examine the trade‐offs among project objectives and their underlying assumptions.

Design/methodology/approach

Effect‐cause‐effect (ECE) methodology of theory of constraints (TOC) has been applied to examine the assumptions behind successfully managing business projects.

Findings

The essence of discussion in this paper leads towards the realization that a possibility exists for time, cost and quality objectives to be pursued collectively in a project management environment.

Research limitations/implications

This paper evaluates to what extent trade‐offs among project objectives actually exist and explores the possibility of their co‐existence in a project management environment. This realization can significantly impact the project trade‐off models in existing literature.

Originality/value

Time, cost and quality have been recognized to be important objectives to successfully complete a project and several studies have acknowledged the necessity to address their trade‐offs. However, most of these studies have taken the trade‐offs for granted without critically examining the assumptions behind such trade‐offs. The present paper fills that gap by applying ECE approach of TOC to examine project management trade‐off assumptions. There‐in lies the value of the current paper.

Details

International Journal of Managing Projects in Business, vol. 1 no. 4
Type: Research Article
ISSN: 1753-8378

Keywords

Article
Publication date: 17 July 2019

Magdalini Titirla and Georgios Aretoulis

This paper aims to examine selected similar Greek highway projects to create artificial neural network-based models to predict their actual construction duration based on data…

Abstract

Purpose

This paper aims to examine selected similar Greek highway projects to create artificial neural network-based models to predict their actual construction duration based on data available at the bidding stage.

Design/methodology/approach

Relevant literature review is presented that highlights similar research approaches. Thirty-seven highway projects, constructed in Greece, with similar type of available data, were examined. Considering each project’s characteristics and the actual construction duration, correlation analysis is implemented, with the aid of SPSS. Correlation analysis identified the most significant project variables toward predicting actual duration. Furthermore, the WEKA application, through its attribute selection function, highlighted the most important subset of variables. The selected variables through correlation analysis and/or WEKA and appropriate combinations of these are used as input neurons for a neural network. Fast Artificial Neural Network (FANN) Tool is used to construct neural network models in an effort to predict projects’ actual duration.

Findings

Variables that significantly correlate with actual time at completion include initial cost, initial duration, length, lanes, technical projects, bridges, tunnels, geotechnical projects, embankment, landfill, land requirement (expropriation) and tender offer. Neural networks’ models succeeded in predicting actual completion time with significant accuracy. The optimum neural network model produced a mean squared error with a value of 6.96E-06 and was based on initial cost, initial duration, length, lanes, technical projects, tender offer, embankment, existence of bridges, geotechnical projects and landfills.

Research limitations/implications

The sample size is limited to 37 projects. These are extensive highway projects with similar work packages, constructed in Greece.

Practical implications

The proposed models could early in the planning stage predict the actual project duration.

Originality/value

The originality of the current study focuses both on the methodology applied (combination of Correlation Analysis, WEKA, FannTool) and on the resulting models and their potential application for future projects.

Details

Journal of Engineering, Design and Technology , vol. 17 no. 6
Type: Research Article
ISSN: 1726-0531

Keywords

Article
Publication date: 11 February 2019

S.M. Reza Alavipour and David Arditi

Planning for increased contractor profits should start at the time the contract is signed because low profits and lack of profitability are the primary causes of contractor…

Abstract

Purpose

Planning for increased contractor profits should start at the time the contract is signed because low profits and lack of profitability are the primary causes of contractor failure. The purpose of this paper is to propose an integrated profit maximization model (IPMM) that aims for maximum expected profit by using time-cost tradeoff analysis, adjusted start times of activities, minimized financing cost and minimized extension of work schedule beyond the contract duration. This kind of integrated approach was never researched in the past.

Design/methodology/approach

IPMM is programmed into an automated system using MATLAB 2016a. It generates an optimal work schedule that leads to maximum profit by means of time-cost tradeoff analysis considering different activity acceleration/deceleration methods and adjusting the start/finish times of activities. While doing so, IPMM minimizes the contractor’s financing cost by considering combinations of different financing alternatives such as short-term loans, long-term loans and lines of credit. IPMM also considers the impact of extending the project duration on project profit.

Findings

IPMM is tested for different project durations, for the optimality of the solutions, differing activity start/finish times and project financing alternatives. In all cases, contractors can achieve maximum profit by using IPMM.

Research limitations/implications

IPMM considers a deterministic project schedule, whereas stochastic time-cost tradeoff analysis can improve its performance. Resource allocation and resource leveling are not considered in IPMM, but can be incorporated into the model in future research. Finally, the long computational time is a challenge that needs to be overcome in future research.

Practical implications

IPMM is likely to increase profits and improve the chances of contractors to survive and grow compared to their competitors. The practical value of IPMM is that any contractor can and should use IPMM since all the data required to run IPMM is available to the contractor at the time the contract is signed. The contractor who provides information about network logic, schedule data, cost data, contractual terms, and available financing alternatives and their APRs can use an automated IPMM that adjusts activity start times and durations, minimizes financing cost, eliminates or minimizes time extensions, minimizes total cost and maximizes expected profit.

Originality/value

Unlike any prior study that looks into contractors’ profits by considering the impact of only one or two factors at a time, this study presents an IPMM that considers all major factors that affect profits, namely, time-cost tradeoff analysis, adjusted start times of activities, minimized financing cost and minimized extension of work schedule beyond the contract duration.

Details

Engineering, Construction and Architectural Management, vol. 26 no. 1
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 17 April 2020

Duc Hoc Tran

Project managers work to ensure successful project completion within the shortest period and at the lowest cost. One of the main tasks of a project manager in the planning phase…

Abstract

Purpose

Project managers work to ensure successful project completion within the shortest period and at the lowest cost. One of the main tasks of a project manager in the planning phase is to generate the project time–cost curve, and furthermore, to determine the most appropriate schedule for the construction process. Numerous existing time–cost tradeoff analysis models have focused on solving a simple project representation without regarding for typical activity and project characteristics. This study aims to present a novel approach called “multiple-objective social group optimization” (MOSGO) for optimizing time–cost decisions in generalized construction projects.

Design/methodology/approach

In this paper, a novel MOGSO to mimic the time–cost tradeoff problem in generalized construction projects is proposed. The MOSGO has slightly modified the mechanism operation from the original algorithm to be a free-parameter algorithm and to enhance the exploring and exploiting balance in an optimization algorithm. The evidential reasoning technique is used to rank the global optimal obtained non-dominated solutions to help decision makers reach a single compromise solution.

Findings

Two case studies of real construction projects were investigated and the performance of MOSGO was compared to those of widely considered multiple-objective evolutionary algorithms. The comparison results indicated that the MOSGO approach is a powerful, efficient and effective tool in finding the time–cost curve. In addition, the multi-criteria decision-making approaches were applied to identify the best schedule for project implementation.

Research limitations/implications

Accordingly, the first major practical contribution of the present research is that it provides a tool for handling real-world construction projects by considering all types of construction project. The second important implication of this study derives from research finding on the hybridization multiple-objective and multi-criteria techniques to help project managers in facilitating the time–cost tradeoff (TCT) problems easily. The third implication stems from the wide-range application of the proposed model TCT.

Practical implications

The model can be used in early stages of the construction process to help project managers in selecting an appropriate plan for whole project lifecycle.

Social implications

The proposal model can be applied to multi-objective contexts in diversified fields. Moreover, the model is also a useful reference for future research.

Originality/value

This paper makes contributions to extant literature by: introducing a method for making TCT models applicable to actual projects by considering general activity precedence relations; developing a novel MOSGO algorithm to solving TCT problems in multi-objective context by a single simulation; and facilitating the TCT problems to project managers by using multi-criteria decision-making approaches.

Details

Engineering, Construction and Architectural Management, vol. 27 no. 9
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 20 March 2020

Amin Mahmoudi and Saad Ahmed Javed

The study aims to introduce two new models of project scheduling by incorporating potential quality loss cost (PQLC) in time–cost tradeoff problems by overcoming the drawbacks of…

Abstract

Purpose

The study aims to introduce two new models of project scheduling by incorporating potential quality loss cost (PQLC) in time–cost tradeoff problems by overcoming the drawbacks of the existing Kim, Khang and Hwang (KKH) model. The proposed methods are named the Revised KKH-I (RKKH-I) and Revised KKH-II (RKKH-II) models for project scheduling.

Design/methodology/approach

The performance of the existing KKH model has been tested using a numerical example followed by the identification of the main shortcomings of the KKH method. Later, a concrete effort has been made to address its shortcomings while improving its performance significantly. The comparative analysis of the Revised KKH models with the original model has also been presented along with sensitivity analyses.

Findings

The study recognizes that the construct on which the original KKH method was built is important; however, certain drawbacks make it unable to consider PQLC in projects, thus making its practical use questionable. The comparative analysis of the proposed methodology with the original method demonstrated that the new models (RKHH-I and II) are more comprehensive and intelligent than the existing KKH model.

Originality/value

The comparative analysis of the original KKH model and its improved version reveals that the revised model is far more suitable for project scheduling. The study is important for project managers who recognize project scheduling being one of the key parameters associated with project management process, crucial to control every day during the management of projects.

Details

Journal of Modelling in Management, vol. 15 no. 3
Type: Research Article
ISSN: 1746-5664

Keywords

Article
Publication date: 21 February 2020

Farhad Hosseinzadeh, Behzad Paryzad, Nasser Shahsavari Pour and Esmaeil Najafi

The optimization and tradeoff of cost-time-quality-risk in one dimension and this four-dimensional problem in ambiguous mode and risk can be neither predicted nor estimated. This…

Abstract

Purpose

The optimization and tradeoff of cost-time-quality-risk in one dimension and this four-dimensional problem in ambiguous mode and risk can be neither predicted nor estimated. This study aims to solve this problem and rank fuzzy numbers using an innovative algorithm “STHD” and a special technique “radius of gyration” (ROG) for fuzzy answers, respectively.

Design/methodology/approach

First, it is the optimization of a fully fuzzy four-dimensional problem which has never been dealt with in regard to risk in ambiguous mode and complexities. Therefore, the risk is a parameter which has been examined neither in probability and estimableness mode nor in the ambiguous mode so far. Second, it is a fully fuzzy tradeoff which, based on the principle of incompatibility “Zadeh, 1973”, proposes that when the complexity of a system surpasses the limited point, it becomes impossible to define the performance of that system accurately, precisely and meaningfully. The authors believe that this principle is the source of fuzzy logic. Third, for calculating and ranking fuzzy numbers of answers, a special technique for fuzzy numbers has been used. Fourth, For the sake of ease, precision and efficiency, an innovative algorithm called the technique of hunting dolphins “STHD” has been used. Finally, the problem is very close to reality. By applying risk in ambiguous mode, the problem has been realistically looked at.

Findings

The results showed that the algorithm was highly robust, with its performance depending very little on the regulation of the parameters. Ranking fuzzy numbers using the ROG indicated the flexibility of fuzzy logic, and it was also determined that the most appropriate regulations were to ensure low time, risk and cost but maximum quality in calculations, which were produced non-uniformly based on the levels of Pareto answers.

Originality/value

The ROG and Chanas Fuzzy Critical Path Method as developed by other researchers have been used. Despite the increase in limitations, parameters can develop. The originality of this study with regard to evaluating the results of tradeoff combinatorial optimization is upon decision-making which has a special and highly strategic role in the fate of the project, with the research been conducted with a special approach and different tools in a fully fuzzy environment.

Article
Publication date: 16 March 2021

Xin Zou, Lihui Zhang and Qian Zhang

The purpose of this research is to develop a time-cost optimization model to schedule repetitive projects while considering limited resource availability.

Abstract

Purpose

The purpose of this research is to develop a time-cost optimization model to schedule repetitive projects while considering limited resource availability.

Design/methodology/approach

The model is based on the constraint programming (CP) framework; it integrates multiple scheduling characteristics of repetitive activities such as continuous or fragmented execution, atypical activities and coexistence of different modes in an activity. To improve project performance while avoiding inefficient hiring and firing conditions, the strategy of bidirectional acceleration is presented and implemented, which requires keeping regular changes in the execution modes between successive subactivities in the same activity.

Findings

Two case studies involving a real residential building construction project and a hotel refurbishing project are used to demonstrate the application of the proposed model based on four different scenarios. The results show that (1) the CP model has great advantages in terms of solving speed and solution quality than its equivalent mathematical model, (2) higher project performance can be obtained compared to using previously developed models and (3) the model can be easily replicated or even modified to enable multicrew implementation.

Originality/value

The original contribution of this research is presenting a novel CP-based repetitive scheduling optimization model to solve the multimode resource-constrained time-cost tradeoff problem of repetitive projects. The model has the capability of minimizing the project total cost that is composed of direct costs, indirect costs, early completion incentives and late completion penalties.

Details

Engineering, Construction and Architectural Management, vol. 29 no. 2
Type: Research Article
ISSN: 0969-9988

Keywords

1 – 10 of 309