Search results

1 – 10 of over 13000
Article
Publication date: 21 May 2020

Osman Hürol Türkakın, Ekrem Manisalı and David Arditi

In smaller projects with limited resources, schedule updates are often not performed. In these situations, traditional delay analysis methods cannot be used as they all require…

Abstract

Purpose

In smaller projects with limited resources, schedule updates are often not performed. In these situations, traditional delay analysis methods cannot be used as they all require updated schedules. The objective of this study is to develop a model that performs delay analysis by using only an as-planned schedule and the expense records kept on site.

Design/methodology/approach

This study starts out by developing an approach that estimates activity duration ranges in a network schedule by using as-planned and as-built s-curves. Monte Carlo simulation is performed to generate candidate as-built schedules using these activity duration ranges. If necessary, the duration ranges are refined by a follow-up procedure that systematically relaxes the ranges and develops new as-built schedules. The candidate schedule that has the closest s-curve to the actual s-curve is considered to be the most realistic as-built schedule. Finally, the as-planned vs. as-built delay analysis method is performed to determine which activity(ies) caused project delay. This process is automated using Matlab. A test case is used to demonstrate that the proposed automated method can work well.

Findings

The automated process developed in this study has the capability to develop activity duration ranges, perform Monte Carlo simulation, generate a large number of candidate as-built schedules, build s-curves for each of the candidate schedules and identify the most realistic one that has an s-curve that is closest to the actual as-built s-curve. The test case confirmed that the proposed automated system works well as it resulted in an as-built schedule that has an s-curve that is identical to the actual as-built s-curve. To develop an as-built schedule using this method is a reasonable way to make a case in or out of a court of law.

Research limitations/implications

Practitioners specifying activity ranges to perform Monte Carlo simulation can be characterized as subjective and perhaps arbitrary. To minimize the effects of this limitation, this study proposes a method that determines duration ranges by comparing as-built and as-planned cash-flows, and then by systematically modifying the search space. Another limitation is the assumption that the precedence logic in the as-planned network remains the same throughout construction. Since updated schedules are not available in the scenario considered in this study, and since in small projects the logic relationships are fairly stable over the short project duration, the assumption of a stable logic throughout construction may be reasonable, but this issue needs to be explored further in future research.

Practical implications

Delays are common in construction projects regardless of the size of the project. The critical path method (CPM) schedules of many smaller projects, especially in developing countries, are not updated during construction. In case updated schedules are not available, the method presented in this paper represents an automated, practical and easy-to-use tool that allows parties to a contract to perform delay analysis with only an as-planned schedule and the expense logs kept on site.

Originality/value

Since an as-built schedule cannot be built without updated schedules, and since the absence of an as-built schedule precludes the use of any delay analysis method that is acceptable in courts of law, using the method presented in this paper may very well be the only solution to the problem.

Details

Engineering, Construction and Architectural Management, vol. 27 no. 10
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 17 July 2019

Magdalini Titirla and Georgios Aretoulis

This paper aims to examine selected similar Greek highway projects to create artificial neural network-based models to predict their actual construction duration based on data…

Abstract

Purpose

This paper aims to examine selected similar Greek highway projects to create artificial neural network-based models to predict their actual construction duration based on data available at the bidding stage.

Design/methodology/approach

Relevant literature review is presented that highlights similar research approaches. Thirty-seven highway projects, constructed in Greece, with similar type of available data, were examined. Considering each project’s characteristics and the actual construction duration, correlation analysis is implemented, with the aid of SPSS. Correlation analysis identified the most significant project variables toward predicting actual duration. Furthermore, the WEKA application, through its attribute selection function, highlighted the most important subset of variables. The selected variables through correlation analysis and/or WEKA and appropriate combinations of these are used as input neurons for a neural network. Fast Artificial Neural Network (FANN) Tool is used to construct neural network models in an effort to predict projectsactual duration.

Findings

Variables that significantly correlate with actual time at completion include initial cost, initial duration, length, lanes, technical projects, bridges, tunnels, geotechnical projects, embankment, landfill, land requirement (expropriation) and tender offer. Neural networks’ models succeeded in predicting actual completion time with significant accuracy. The optimum neural network model produced a mean squared error with a value of 6.96E-06 and was based on initial cost, initial duration, length, lanes, technical projects, tender offer, embankment, existence of bridges, geotechnical projects and landfills.

Research limitations/implications

The sample size is limited to 37 projects. These are extensive highway projects with similar work packages, constructed in Greece.

Practical implications

The proposed models could early in the planning stage predict the actual project duration.

Originality/value

The originality of the current study focuses both on the methodology applied (combination of Correlation Analysis, WEKA, FannTool) and on the resulting models and their potential application for future projects.

Details

Journal of Engineering, Design and Technology , vol. 17 no. 6
Type: Research Article
ISSN: 1726-0531

Keywords

Article
Publication date: 20 March 2023

Haruna Sa'idu Lawal, Hassan Adaviriku Ahmadu, Muhammad Abdullahi, Muhammad Aliyu Yamusa and Mustapha Abdulrazaq

This study aims to develop a building renovation duration prediction model incorporating both scope and non-scope factors.

Abstract

Purpose

This study aims to develop a building renovation duration prediction model incorporating both scope and non-scope factors.

Design/methodology/approach

The study used a questionnaire to obtain basic information relating to identified project scope factors as well as information relating to the impact of the non-scope factors on the duration of building renovation projects. The study retrieved 121 completed questionnaires from construction firms on tertiary education trust fund (TETFund) building renovation projects. Artificial neural network was then used to develop the model using 90% of the data, while mean absolute percentage error was used to validate the model using the remaining 10% of the data.

Findings

Two artificial neural network models were developed – a multilayer perceptron (MLP) and a radial basis function (RBF) model. The accuracy of the models was 86% and 80%, respectively. The developed models’ predictions were not statistically different from those of actual duration estimates with less than 20% error margin. Also, the study found that MLP models are more accurate than RBF models.

Research limitations/implications

The developed models are only applicable to projects that suit the characteristics and nature of the data used to develop the models. Hence, models can only predict the duration of building renovation projects.

Practical implications

The developed models are expected to serve as a tool for realistic estimation of the duration of building renovation projects and thus, help construction project managers to effectively plan and manage it.

Social implications

The developed models are expected to serve as a tool for realistic estimation of the duration of building renovation projects and thus, help construction project managers to effectively plan and manage it; it also helps clients to effectively benchmark projects duration and contractors to accurately estimate duration at tendering stage.

Originality/value

The study presents models that combine both scope and non-scope factors in predicting the duration of building renovation projects so as to ensure more realistic predictions.

Details

Journal of Financial Management of Property and Construction , vol. 28 no. 3
Type: Research Article
ISSN: 1366-4387

Keywords

Article
Publication date: 26 December 2023

Farshad Peiman, Mohammad Khalilzadeh, Nasser Shahsavari-Pour and Mehdi Ravanshadnia

Earned value management (EVM)–based models for estimating project actual duration (AD) and cost at completion using various methods are continuously developed to improve the…

Abstract

Purpose

Earned value management (EVM)–based models for estimating project actual duration (AD) and cost at completion using various methods are continuously developed to improve the accuracy and actualization of predicted values. This study primarily aimed to examine natural gradient boosting (NGBoost-2020) with the classification and regression trees (CART) base model (base learner). To the best of the authors' knowledge, this concept has never been applied to EVM AD forecasting problem. Consequently, the authors compared this method to the single K-nearest neighbor (KNN) method, the ensemble method of extreme gradient boosting (XGBoost-2016) with the CART base model and the optimal equation of EVM, the earned schedule (ES) equation with the performance factor equal to 1 (ES1). The paper also sought to determine the extent to which the World Bank's two legal factors affect countries and how the two legal causes of delay (related to institutional flaws) influence AD prediction models.

Design/methodology/approach

In this paper, data from 30 construction projects of various building types in Iran, Pakistan, India, Turkey, Malaysia and Nigeria (due to the high number of delayed projects and the detrimental effects of these delays in these countries) were used to develop three models. The target variable of the models was a dimensionless output, the ratio of estimated duration to completion (ETC(t)) to planned duration (PD). Furthermore, 426 tracking periods were used to build the three models, with 353 samples and 23 projects in the training set, 73 patterns (17% of the total) and six projects (21% of the total) in the testing set. Furthermore, 17 dimensionless input variables were used, including ten variables based on the main variables and performance indices of EVM and several other variables detailed in the study. The three models were subsequently created using Python and several GitHub-hosted codes.

Findings

For the testing set of the optimal model (NGBoost), the better percentage mean (better%) of the prediction error (based on projects with a lower error percentage) of the NGBoost compared to two KNN and ES1 single models, as well as the total mean absolute percentage error (MAPE) and mean lags (MeLa) (indicating model stability) were 100, 83.33, 5.62 and 3.17%, respectively. Notably, the total MAPE and MeLa for the NGBoost model testing set, which had ten EVM-based input variables, were 6.74 and 5.20%, respectively. The ensemble artificial intelligence (AI) models exhibited a much lower MAPE than ES1. Additionally, ES1 was less stable in prediction than NGBoost. The possibility of excessive and unusual MAPE and MeLa values occurred only in the two single models. However, on some data sets, ES1 outperformed AI models. NGBoost also outperformed other models, especially single models for most developing countries, and was more accurate than previously presented optimized models. In addition, sensitivity analysis was conducted on the NGBoost predicted outputs of 30 projects using the SHapley Additive exPlanations (SHAP) method. All variables demonstrated an effect on ETC(t)/PD. The results revealed that the most influential input variables in order of importance were actual time (AT) to PD, regulatory quality (RQ), earned duration (ED) to PD, schedule cost index (SCI), planned complete percentage, rule of law (RL), actual complete percentage (ACP) and ETC(t) of the ES optimal equation to PD. The probabilistic hybrid model was selected based on the outputs predicted by the NGBoost and XGBoost models and the MAPE values from three AI models. The 95% prediction interval of the NGBoost–XGBoost model revealed that 96.10 and 98.60% of the actual output values of the testing and training sets are within this interval, respectively.

Research limitations/implications

Due to the use of projects performed in different countries, it was not possible to distribute the questionnaire to the managers and stakeholders of 30 projects in six developing countries. Due to the low number of EVM-based projects in various references, it was unfeasible to utilize other types of projects. Future prospects include evaluating the accuracy and stability of NGBoost for timely and non-fluctuating projects (mostly in developed countries), considering a greater number of legal/institutional variables as input, using legal/institutional/internal/inflation inputs for complex projects with extremely high uncertainty (such as bridge and road construction) and integrating these inputs and NGBoost with new technologies (such as blockchain, radio frequency identification (RFID) systems, building information modeling (BIM) and Internet of things (IoT)).

Practical implications

The legal/intuitive recommendations made to governments are strict control of prices, adequate supervision, removal of additional rules, removal of unfair regulations, clarification of the future trend of a law change, strict monitoring of property rights, simplification of the processes for obtaining permits and elimination of unnecessary changes particularly in developing countries and at the onset of irregular projects with limited information and numerous uncertainties. Furthermore, the managers and stakeholders of this group of projects were informed of the significance of seven construction variables (institutional/legal external risks, internal factors and inflation) at an early stage, using time series (dynamic) models to predict AD, accurate calculation of progress percentage variables, the effectiveness of building type in non-residential projects, regular updating inflation during implementation, effectiveness of employer type in the early stage of public projects in addition to the late stage of private projects, and allocating reserve duration (buffer) in order to respond to institutional/legal risks.

Originality/value

Ensemble methods were optimized in 70% of references. To the authors' knowledge, NGBoost from the set of ensemble methods was not used to estimate construction project duration and delays. NGBoost is an effective method for considering uncertainties in irregular projects and is often implemented in developing countries. Furthermore, AD estimation models do fail to incorporate RQ and RL from the World Bank's worldwide governance indicators (WGI) as risk-based inputs. In addition, the various WGI, EVM and inflation variables are not combined with substantial degrees of delay institutional risks as inputs. Consequently, due to the existence of critical and complex risks in different countries, it is vital to consider legal and institutional factors. This is especially recommended if an in-depth, accurate and reality-based method like SHAP is used for analysis.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 19 September 2016

Isaac Mensah, Theophilus Adjei-Kumi and Gabriel Nani

Determining the duration for road construction projects represents a problem for construction professionals in Ghana. The purpose of this paper is to develop an artificial neural…

Abstract

Purpose

Determining the duration for road construction projects represents a problem for construction professionals in Ghana. The purpose of this paper is to develop an artificial neural network (ANN) model for determining the duration for rural bituminous surfaced road projects.

Design/methodology/approach

Data for 22 completed bituminous surfaced road projects from the Department of Feeder Roads (rural road agency) were collected and analyzed using the principal component analysis (PCA) and ANN techniques. The data collected were final payment certificates which contained payment bill of quantities (BOQ) of work items executed for the selected completed road projects. The executed quantities in the BOQ were the total quantities of work items for site clearance, earthworks, in-situ concrete, reinforcement, formwork, gravel sub-base/base, bitumen, road line markings and furniture, length of road and actual durations for each of the completed projects. The PCA was first employed to reduce the data in order to identify a smaller number of variables (or significant quantities) that constitute 81.58 percent of the total variance of the collected data. The ANN was then used to develop the network using the identified significant quantities as input variables and the actual durations as output variables.

Findings

The coefficient of correlation (R) and determination (R2) as well as the mean absolute percentage error (MAPE) obtained show that construction professionals can use the developed ANN model for determining duration. The study shows that the best neural network is the multi-layer perceptron with a structure 3-38-1 based on a back propagation feed forward algorithm. The developed network produces good results with an MAPE of 17.56 percent or an average accuracy of 82.44 percent.

Research limitations/implications

Apart from the fact that the sample size was small, the developed model does not incorporate the implications of other likely factors that may affect contract duration.

Practical implications

The outcome of this study is to help construction professionals to fix realistic contract duration for road construction projects before signing a contract. Such realistic contract duration would help reduce time overruns as well as the payment of liquidated and ascertained damages by contractors for late completion.

Originality/value

This paper proposes an alternative way of determining the duration for road construction projects using the total quantities of work items in a final payment BOQ. The approach is based on the PCA and ANN model of quantities of work items of completed road projects.

Details

Engineering, Construction and Architectural Management, vol. 23 no. 5
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 2 June 2021

Shambel Kifle Alemu

The aim of the study was to develop a practical construction time model for public building projects in Addis Ababa, Ethiopia.

Abstract

Purpose

The aim of the study was to develop a practical construction time model for public building projects in Addis Ababa, Ethiopia.

Design/methodology/approach

This research work used regression analysis and also exploratory scatter and residual plot techniques. Simple and multiple regressions were used for the investigation of the best fit time model. The analyses were carried out using IBM SPSS statistical software, version 20.

Findings

The result revealed that the Bromilow time-cost principle was moderately applicable. However, the cubic regression model (CUB) was found a better time-cost relationship. On the contrary, the study has shown a poor relationship between actual time and gross floor area. Furthermore, multiple linear regression analysis (MLR) consists of three statistically significant variables were found a better fit time model.

Research limitations/implications

The study is limited to only six project scope factors. Further research is recommended to include more building projects of similar type and implications of other factors to improve the reliability of the models.

Practical implications

The developed model was not intended as a replacement for detailed construction scheduling techniques. The resulting model is applicable for front-end predictions of construction duration.

Originality/value

The main parties involved in the building projects should apply the model for benchmarking a precise construction time during the early planning phase.

Details

Engineering, Construction and Architectural Management, vol. 29 no. 5
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 27 April 2020

Hassan Adaviriku Ahmadu, Ahmed Doko Ibrahim, Yahaya Makarfi Ibrahim and Kulomri Jipato Adogbo

This study aims to develop a model which incorporates the impact of both aleatory and epistemic uncertainties into construction duration predictions, in a manner that is…

Abstract

Purpose

This study aims to develop a model which incorporates the impact of both aleatory and epistemic uncertainties into construction duration predictions, in a manner that is consistent with the nature/quality of information available about various factors which bring about uncertainties.

Design/methodology/approach

Data relating to 178 completed Tertiary Education Trust Fund (TETfund) building construction projects were obtained from construction firms via questionnaire survey. Using 90% of the data, the model was developed in the form of a hybrid-based algorithm implemented through a suitable user-friendly graphical user interface (GUI) using MATLAB programming language. Bayesian model averaging, Monte Carlo simulation and fuzzy logic were the statistical methods used for the algorithm development, prior to its GUI implementation in MATLAB. Using the remaining 10% data, the model's predictive accuracy was assessed via the independent samples t-test and the mean absolute percentage error (MAPE).

Findings

The developed model's predictions were found not statistically different from those of actual duration estimates in the 10% test data, with a MAPE of just 2%. This suggests that the model's ability to incorporate both aleatory and epistemic uncertainties improves accuracy of duration predictions made using it.

Research limitations/implications

The model was developed using a particular type of building projects (TETfund building construction projects), and so its use is limited to projects with characteristics similar to those used for its development.

Practical implications

The developed model's predictions are expected to serve as a useful basis for consultancy firms and contractor organisations to make more realistic schedules and benchmark measures of construction period, thereby facilitating effective planning and successful execution of construction projects.

Originality/value

The study presented a model which permits combined manipulation of aleatory and epistemic uncertainties, hence ensuring a more realistic incorporation of uncertainty into construction duration predictions.

Details

Engineering, Construction and Architectural Management, vol. 27 no. 9
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 16 June 2023

Jyh-Bin Yang and Tzu-Hua Lai

This study aims to review earned value management (EVM)-relative methods, including the original EVM, earned schedule method (ESM) and earned duration management (EDM(t)). This…

Abstract

Purpose

This study aims to review earned value management (EVM)-relative methods, including the original EVM, earned schedule method (ESM) and earned duration management (EDM(t)). This study then proposes a general implementation procedure and some basic principles for the selection of EVM-relative methods.

Design/methodology/approach

After completing an intensive literature review, this study conducts a case study to examine the forecasting performance of project duration using the EVM, ESM and EDM(t) methods.

Findings

When the project is expected to finish on time, ESM with a performance factor equal to 1 is the recommended method. EDM(t) would be the most reliable method during a project's entire lifetime if EDM(t) is expected to be delayed based on past experience.

Research limitations/implications

As this research conducts a case study with only one building construction project, the results might not hold true for all types of construction projects.

Practical implications

EVM, ESM and EDM(t) are simple and data-accessible methods. With the help of a general implementation procedure, applying all three methods would be better. The power of the three methods is definitely larger than that of choosing only one for complex construction projects.

Originality/value

Previous studies have discussed the advantages and disadvantages of EVM, ESM and EDM(t). This study amends the available outcomes. Thus, for schedulers or researchers interested in implementing EVM, ESM and EDM(t), this study can provide more constructive instructions.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 30 April 2021

Alexis Barrientos-Orellana, Pablo Ballesteros-Pérez, Daniel Mora-Melia, Maria Carmen González-Cruz and Mario Vanhoucke

Earned Value Management (EVM) is a project monitoring and control technique that enables the forecasting of a project's duration. Many EVM metrics and project duration forecasting…

Abstract

Purpose

Earned Value Management (EVM) is a project monitoring and control technique that enables the forecasting of a project's duration. Many EVM metrics and project duration forecasting methods have been proposed. However, very few studies have compared their accuracy and stability.

Design/methodology/approach

This paper presents an exhaustive stability and accuracy analysis of 27 deterministic EVM project duration forecasting methods. Stability is measured via Pearson's, Spearman's and Kendall's correlation coefficients while accuracy is measured by Mean Squared and Mean Absolute Percentage Errors. These parameters are determined at ten percentile intervals to track a given project's progress across 4,100 artificial project networks with varied topologies.

Findings

Findings support that stability and accuracy are inversely correlated for most forecasting methods, and also suggest that both significantly worsen as project networks become increasingly parallel. However, the AT + PD-ESmin forecasting method stands out as being the most accurate and reliable.

Practical implications

Implications of this study will allow construction project managers to resort to the simplest, most accurate and most stable EVM metrics when forecasting project duration. They will also be able to anticipate how the project topology (i.e., the network of activity predecessors) and the stage of project progress can condition their accuracy and stability.

Originality/value

Unlike previous research comparing EVM forecasting methods, this one includes all deterministic methods (classical and recent alike) and measures their performance in accordance with several parameters. Activity durations and costs are also modelled akin to those of construction projects.

Details

Engineering, Construction and Architectural Management, vol. 29 no. 3
Type: Research Article
ISSN: 0969-9988

Keywords

Book part
Publication date: 27 October 2014

Laura Fink

This article examines the effect of the customer focus (CF) group of competencies, which includes communication and negotiation skills, on project performance as measured by…

Abstract

Purpose

This article examines the effect of the customer focus (CF) group of competencies, which includes communication and negotiation skills, on project performance as measured by reaching the internal and the overall budget, the quality, and the deadline goals.

Methodology/approach

The multiple regression model was based on a dataset from Trimo, an engineering and production company of prefabricated buildings.

Findings

The inverted U-shaped relationship of the CF group has been proven to exist with all project goals.

Research implications

The present study provides a starting-point for further empirical research on the international construction sector, projects, teams, and competence research.

Details

A Focused Issue on Building New Competences in Dynamic Environments
Type: Book
ISBN: 978-1-78441-274-6

Keywords

1 – 10 of over 13000