1 – 10 of 128Andrew Ebekozien, Clinton Ohis Aigbavboa, Wellington Didibhuku Thwala, Mohamed Ahmed Hafez and Mohamad Shaharudin Samsurijan
Despite advancements in construction digitalisation and alternative building technologies, cost overrun is still a challenge in the construction industry. The inflation rate is…
Abstract
Purpose
Despite advancements in construction digitalisation and alternative building technologies, cost overrun is still a challenge in the construction industry. The inflation rate is increasing, especially in developing countries, and is critical in cost overrun matters. It can deviate construction built-up rate components. This may thwart improving construction-related Sustainable Development Goals (SDGs). Studies concerning the impact of the inflation rate on construction-related SDGs are scarce in developing countries, including Nigeria. The study investigated the impact of inflation on Nigeria’s construction projects and their outcome on SDGs and suggested possible ways to improve achievement of construction-related SDGs and their targets.
Design/methodology/approach
The researchers employed a qualitative research design. This is because of the study’s unexplored dimension. The researchers engaged 35 participants across major cities in Nigeria via semi-structured virtual and face-to-face interviews. The research utilised a thematic method for collated data and accomplished saturation.
Findings
Findings reveal that the impact of inflation on construction projects, if not checked, could hinder achieving construction-related SDGs in Nigeria. This is because of the past three years of hyperinflation that cut across major construction components. It shows that the upward inflation rate threatens achieving construction-related SDGs and proffered measures to mitigate inflation and, by extension, enhance achieving construction-related SDGs. This includes a downward review of the Monetary Policy Rate, control of exchange rate volatility and addressing insecurity to restore FDIs and FPIs confidence.
Originality/value
Besides suggesting possible solutions to mitigate hyperinflation on construction components to improve achieving construction-related SDGs, findings will stipulate government policymakers put measures in place through favourable fiscal and monetary policy implementation and encourage moving from a consumption to a production nation.
Details
Keywords
Aravindh Devandran, Felicita J. Davis and Michael Sammanasu Joseph
This study aims to determine and investigate the main causes of construction project delays. Construction projects are more intricate and associated with significant levels of…
Abstract
Purpose
This study aims to determine and investigate the main causes of construction project delays. Construction projects are more intricate and associated with significant levels of risk owing to cost overruns. These overruns frequently lead to delays, incomplete work or other related challenges. Building delays are a prevalent problem in the building sector of developing nations. These delays prolong the duration of projects and result in increased costs and conflicts among stakeholders. A conceptual model consisting of the factors causing the delays in heating, ventilation and air conditioning (HVAC) projects was developed and tested in this study.
Design/methodology/approach
A comprehensive data collection process was undertaken. A meticulously designed survey was distributed to a diverse cohort of 294 participants, including contractors and sub-contractors from Chennai, Tamil Nadu. The data was collected using stratified sampling, ensuring a representative sample. The data was then analysed using ordinary least squares multiple regression.
Findings
The findings of this study have significant implications for the construction industry. They indicate that factors related to sales, clients, design, procurement, finance and labour all contribute to delays in HVAC projects. Understanding these factors can help stakeholders in the industry to better manage and mitigate project delays.
Originality/value
This study is unique because it is a perceptual study of stakeholders. It provides valuable information for analysing and assessing project performance by identifying the primary causes of HVAC project delays. To the best of the authors’ knowledge, the study conducted on HVAC projects is the first of its kind and hence makes a pivotal contribution to the literature on construction projects. Additionally, the study will assist policymakers and consultants in taking necessary steps to minimize delays.
Details
Keywords
Inimbom Walter Isang and David Ojimaojo Ebiloma
Covid-19 pandemic have raised serious health concerns, work disruptions and job loss. Thus, Nigeria’s Covid-19 challenges can hinder project performance in the construction…
Abstract
Purpose
Covid-19 pandemic have raised serious health concerns, work disruptions and job loss. Thus, Nigeria’s Covid-19 challenges can hinder project performance in the construction sector. By integrating the principle of sustainable construction, it can minimise the environmental and socio-economic impact of Covid-19. This research therefore aims at developing strategies to achieve sustainable project performance in the post-Covid era in Nigeria.
Design/methodology/approach
A qualitative research method was used. Data was collected from 13 stakeholders in the built environment. Percentages and thematic analysis were used to analyse data from the interviews.
Findings
The study reveals that stakeholders are encountering operational and financial challenges: Increased price of materials, labour and material shortage and project delays were key operational challenges. The financial challenges were related to increased construction cost, reduced profit and payment delays. To address these challenges, the study developed managerial, contractual and governmental strategies: Market survey and bulk purchase, remote working and adherence to Covid-19 protocols were among the key managerial strategies. For the contractual strategies: contracts reviews, smart contracts, working overtime and night shift were developed, while governmental strategies included provision of funds, loans and incentives for workers.
Originality/value
The study deduced that while environmental sustainability was employed to address the Covid-19 challenges, the economic and social aspects were found to be under-utilized. Therefore, the study concluded that a holistic application of environmental, economic and social sustainability themes while incorporating managerial, contractual and governmental strategies is significant for achieving sustainable project performance in the post-Covid era in Nigeria.
Details
Keywords
This research aims to offers a new method for assessing geoeconomic risks in bilateral relations and evaluate the level of such risks from Vietnam’s economic dependency on China.
Abstract
Purpose
This research aims to offers a new method for assessing geoeconomic risks in bilateral relations and evaluate the level of such risks from Vietnam’s economic dependency on China.
Design/methodology/approach
I apply descriptive analysis to identify asymmetrical dependency in Vietnam–China economic relations and propose a geoeconomic risk assessment framework to evaluate risk levels in bilateral economic linkages.
Findings
The proposed geoeconomic risk framework assesses risk levels, which are positively influenced by the degree of asymmetrical relations (vulnerabilities), the net impacts on the receiving economy (impacts) and the sending state’s ability to control economic tools (threats). In contrast, risk levels are negatively affected by the effectiveness of existing mitigation efforts. The framework employs ordinal likelihood scales to rank various risk levels. In the context of Vietnam–China relations, market access for agricultural products and control of the Mekong water emerge as the most risky areas for economic coercion, followed by Chinese official development finance in infrastructure and critical input imports. On the other hand, debt dependency and foreign direct investment in the energy sector are considered more secure areas—less likely targets for economic coercion. Hence, risk mitigation strategies should prioritize reducing asymmetry in vulnerable dependence areas while maintaining current practices in more secure areas.
Originality/value
Methodologically, it introduces a new approach for assessing bilateral geoeconomic risk. Empirically, it provides Vietnam’s policymakers with a comprehensive evaluation of the implications of economic interdependence with China.
Details
Keywords
Christophe Gaie, Bertrand Florat and Steven Morvan
In the present article, the authors tackle the problem of IT documentation, which plays an important role in information technology (IT) project management.
Abstract
Purpose
In the present article, the authors tackle the problem of IT documentation, which plays an important role in information technology (IT) project management.
Design/methodology/approach
They provide a simple tool based on five complementary views, which should be detailed by the project team using a classic source code management platform.
Findings
The proposed tool is open source and may be reused by any IT team in various project contexts and heterogeneous development methods.
Originality/value
This research provides an operational framework, which facilitates IT project management and documentation. The framework is open source and may be easily downloaded by any other IT team.
Details
Keywords
Yaser Gamil and Ismail Abd Rahman
The purpose of this paper is to develop a structural relationship model to study the relationship between causes and effects of poor communication and information exchange in…
Abstract
Purpose
The purpose of this paper is to develop a structural relationship model to study the relationship between causes and effects of poor communication and information exchange in construction projects using Smart-PLS.
Design/methodology/approach
The first method of this research is to identify the causes and effects factors of poor communication in construction projects from the extant of literature. The data used to develop the model was collected using a questionnaire survey, which targeted construction practitioners in the Malaysian construction industry. A five-point Likert type scale was used to rate the significance of the factors. The factors were classified under their relevant construct/group using exploratory factor analysis. A hypothetical model was developed and then transformed into Smart-PLS in which the hypothetical model suggested that each group of the cause factors has a direct impact on the effect groups. The hypothesis was tested using t-values and p-values. The model was assessed for its inner and outer components and achieved the threshold criterion. Further, the model was verified by engaging 14 construction experts to verify its applicability in the construction project setting.
Findings
The study developed a structural equation model to clarify the relationships between causes and effects of poor communication in construction projects. The model explained the degree of relationships among causes and effects of poor communication in construction projects.
Originality/value
The published academic and non-academic literature introduced many studies on the issue of communication including the definitions, importance, barriers to effective communication and means of poor communication. However, these studies ended up only on the general issue of communication lacking an in-depth investigation of the causes and effects of poor communication in the construction industry. The study implemented advanced structural modeling to study the causes and effects. The questionnaire, the data and concluding results fill the identified research gap of this study. The addressed issue is also of interest because communication is considered one of the main knowledge areas in construction management.
Details
Keywords
Gro Holst Volden and Bjorn Andersen
The purpose of this paper is to study public project governance frameworks in various ministries and agencies in Norway, following the introduction of such a framework on the…
Abstract
Purpose
The purpose of this paper is to study public project governance frameworks in various ministries and agencies in Norway, following the introduction of such a framework on the topmost level (i.e. the cabinet) which applies to the very largest projects.
Design/methodology/approach
The study is methodologically designed as a qualitative assessment of project governance frameworks that apply to state-funded investment projects in selected sectors, based on data gathered through document reviews and interviews.
Findings
The study finds that all of the agencies have introduced their own project governance frameworks, which are basically consistent with the recommendations from the project management literature and with the cabinet’s overall requirements in Norway. By contrast, only one ministry has taken a formalized role as a project owner. Governance tasks thus seem to be extensively delegated to the subordinate agencies. This even includes strategic tasks such as project selection and portfolio management, and implies there is a risk that public project governance has a narrow and internal focus.
Originality/value
The paper is a first step toward a better understanding of public project governance as a hierarchical system and the relationship between project owners on three levels, the cabinet, the sectoral ministry, and the government agency.
Details
Keywords
Atupakisye Mwakolo, Meshack Siwandeti, Leticia Mahuwi and Baraka Israel
The study aims to explore the role of procurement of good governance (PGG) on value for money (VfM) achievement in public construction projects. By investigating various…
Abstract
Purpose
The study aims to explore the role of procurement of good governance (PGG) on value for money (VfM) achievement in public construction projects. By investigating various dimensions of PGG, including transparency, accountability, competition and integrity, this study provides insights into how these factors contribute to the successful achievement of VfM outcomes in public construction projects.
Design/methodology/approach
The data were sourced from 203 construction project practitioners from 24 selected procuring entities in Tanzania using a census approach and a cross-sectional questionnaire survey. Confirmatory factor analysis (CFA) and structural equation modelling (SEM) were used for data analysis.
Findings
The findings of the study revealed a positive and significant impact of various dimensions of PGG on VfM. Specifically, transparency, accountability, competition and integrity were positively and significantly related to VfM, with p-values <0.001. Based on the study findings, we conclude that PGG is an important predictor of VfM achievement in public construction projects.
Practical implications
The study offers policy implications for streamlined PGG and VfM achievement in public construction projects. It is suggested that procuring entities can enhance VfM by enforcing compliance with the principles of PGG throughout the entirety of construction projects. In this case, streamlined legislative frameworks and control mechanisms are crucial components that could enhance PGG and the achievement of VfM.
Originality/value
This study contributes to the academic literature on the strategic role of PGG in enhancing VfM achievement. This is one of the research domains, which has not been adequately researched, particularly in Tanzania’s context. In addition, the study provides valuable insights to policymakers, practitioners and stakeholders involved in public construction projects to improve project outcomes and resource allocation.
Details
Keywords
The purpose of this paper is to explore the adverse incentives at the front end of government-funded projects with concentrated benefits and no liabilities for the privileged…
Abstract
Purpose
The purpose of this paper is to explore the adverse incentives at the front end of government-funded projects with concentrated benefits and no liabilities for the privileged groups. In particular, the author discusses the risk of perverse incentives of the types typically found in the development aid sector that results in counterproductive outcomes.
Design/methodology/approach
The paper uses a simple conceptual framework based on agency theory. A qualitative, case-based approach with purposive sampling was chosen for the empirical part of the study. Eight Norwegian projects were selected because incentive problems were to be expected, and one development aid project served as a reference case.
Findings
The paper finds that low strategic project success corresponded well with the terms of financing. There were clear indications of agency problems, in three cases to the extent that the incentives turned perverse. The paper concludes with a discussion of relevant measures to prevent the emergence of perverse incentives.
Originality/value
The paper contributes to an improved understanding of the incentives related to public project initiation and selection, which is an under-researched topic and generally not included in formal project governance schemes. The research should therefore be useful to scholars as well as practitioners within the field of project governance.
Details
Keywords
Salman Ashkanani and Robert Franzoi
There is a large amount of published literature on project management. However, there exists a gap between the existing literature and current…
Abstract
Purpose
There is a large amount of published literature on project management. However, there exists a gap between the existing literature and current practices in the industry for the development and execution of megaprojects. Existing literature generally focuses on individual elements applicable to project management in general. This article aims to provide an overview of the project management system components used in industrial megaprojects and identify the gaps between theory and practice, which can be used as input for further research on the topic.
Design/methodology/approach
The topic of megaproject management is reviewed based on available literature sources on megaproject management systems to identify the main gaps in the literature between theory and practice. Based on the findings, an analysis is provided to discuss the improvements required in distinct project management areas and phases.
Findings
There are multiple gaps associated with issues, failures, successes and challenges in industrial megaprojects. Improvements are needed in distinct management areas and over the entire project lifetime. Further guidelines are required for achieving improved megaproject management systems. Such concepts could benefit researchers and practitioners in streamlining their research toward the most relevant and critical areas of improvement of megaproject management systems.
Originality/value
This study addresses the literature gaps between theory and practices on megaproject management systems with an overview that provides helpful guidance for industrial applications and future research. A holistic analysis identifies gaps and critical drives in the body of knowledge, revealing avenues for future research focused on quality as the central pillar that affects the entire megaproject management system.