Article
Publication date: 28 September 2020

Simon Adamtey

The purpose of this paper is to investigate and determine the time and cost performance of progressive design-build (PDB) projects compared with that of design-build (DB…

Abstract

Purpose

The purpose of this paper is to investigate and determine the time and cost performance of progressive design-build (PDB) projects compared with that of design-build (DB) projects. The objective is to provide empirical evidence on the performance of PDB delivery method.

Design/methodology/approach

A quantitative research approach was used by analyzing time and cost data collected on 75 PDB and 92 DB projects from the database of Design-Build Institute of America. One-way analysis of variance was used to determine statistical difference in time and cost performance between PDB and DB.

Findings

PDB projects have a comparatively better time performance than cost performance. When compared with DB projects, there was a statistically significant difference in time overrun with PDB performing better than DB (0.41 vs 8.0%). Additionally, about 80% of PDB projects had shorter or as scheduled duration compared to 74% for DB. There was no statistically significant difference of cost performance between PDB and DB.

Research limitations/implications

The main limitation is the sample size of 72 PDB projects. It is recommended that further research should be conducted using a larger sample size to confirm the findings of this study.

Practical implications

PDB will be more beneficial for projects with sensitive deadlines. For an owner deciding between PDB and DB, the advantage of using PDB is in its time performance, which may lead to the project being completed on or ahead of time. As such, PDB can serve as another “tool in the toolbox” for owners to help in reducing construction delays.

Originality/value

This paper is the first attempt to provide an empirical evidence of the cost and time performance of PDB based on analyzing multiple projects. Owners will be better informed when selecting PDB for their projects.

Details

Journal of Engineering, Design and Technology , vol. 19 no. 3
Type: Research Article
ISSN: 1726-0531

Keywords

Article
Publication date: 18 June 2021

Pramen P. Shrestha and Jacimaria R. Batista

The purpose of this study is to determine the barriers and constraints executive decision-makers have to face during the delivery method selection stage of water and wastewater…

Abstract

Purpose

The purpose of this study is to determine the barriers and constraints executive decision-makers have to face during the delivery method selection stage of water and wastewater projects using alternative project delivery (APD) methods, e.g. design-build (DB), design-build-operate (DBO) and construction management-at-risk (CMAR).

Design/methodology/approach

Structured interviews were conducted with 18 executive decision-makers from public agencies to identify the reasons for transitioning to APD from the design-bid-build (DBB) method. Respondents were also asked about the major obstacles they faced during the decision-making process, as well as key positive and negative factors in using APD methods. The executive decision-makers were also asked about their lessons learned during this process. In addition, this study collected key steps in making APD water and wastewater projects successful. All of the findings from the interview phase were validated by seven public agency executive decision-makers of water and wastewater industries.

Findings

One major study finding was that executive decision-makers chose the APD method because it provided cost and schedule benefits and the owner could also choose the designer or builder based on qualifications. The study also found that the main obstacles executive decision-makers faced were: (1) difficulty in implementing APD methods because they do not follow the low-bid process, (2) reluctance to use DB/CMAR because of the status quo and (3) unfamiliarity of city councils/elected commissions with the DB/CMAR process. The validation survey found that most findings from the initial phase of interviews were confirmed by the executives who took part in validation phase.

Research limitations/implications

The major limitation of this research is the small sample size. As the executive decision-makers are very hard to reach for interviews, the authors failed to get interviews from a large number of them, despite repeated efforts made by the authors. Another limitation of this study is that the authors contacted most of the executive decision-makers listed in the WDBC list. These executive decision-makers worked for public agencies and, therefore, the views from private agencies could not be included in this research. The authors understand that the validation of the study findings is very important. However, due to the scope and limited time available for the research, the authors could not validate the findings of this study with other public agencies.

Practical implications

Selecting APD methods instead of DBB methods in water and wastewater projects for public agencies is a crucial issue during the project planning phase. Agencies' executive decision-makers need to understand the advantages and disadvantages of APD methods, along with the transition process in order to smoothly deliver projects. The findings of this study will assist public agency executive decision-makers to mitigate risks, overcome obstacles and become more educated about the APD method process, so that these projects can be successfully delivered within budget and on time.

Originality/value

This paper contributes to the existing body of knowledge by identifying lessons learned related to various APD method issues, which can be utilized by municipal executive decision-makers to successfully complete future APD projects.

Details

Engineering, Construction and Architectural Management, vol. 29 no. 7
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 20 September 2022

Vassiliki Demetracopoulou, William J. O'Brien, Nabeel Khwaja, Jeffrey Feghaly and Mounir El Asmar

Over the last three decades, construction projects have increasingly been delivered through alternative delivery methods. As a result, many owners have a range of delivery methods…

Abstract

Purpose

Over the last three decades, construction projects have increasingly been delivered through alternative delivery methods. As a result, many owners have a range of delivery methods to choose from and aim to use the right one for each of their projects. Researchers have developed several tools and decision-support processes to facilitate this selection procedure. The purpose of this study is to review and discuss differences and common themes across selection tools developed by academic researchers and project owners.

Design/methodology/approach

The study reviews prominent selection processes and tools used for infrastructure projects by conducting an in-depth literature review and using the content analysis method to elicit findings on the methodologies and criteria presented in the literature.

Findings

This study presents three principal findings. First, findings show three common themes emerge within the selection criteria—characteristics, goals and risks. Second, while academic studies most commonly suggest employing multi-attribute analysis, this study reveals that, in practice, selection tools most frequently employ a staged or gated evaluation based on the type of criteria and their importance to the decision. Finally, this review further highlights the importance of institutional context in decision-making.

Originality/value

This work contributes to the body of knowledge by providing guidance to practitioners and opening new directions for researchers around the way selection criteria are categorized in the relevant literature and the institutional context considerations when structuring or evaluating a selection process or tool.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 1
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 4 March 2021

Zheng Ping Lee, Rahimi A. Rahman and Shu Ing Doh

The success rate of design-build (D-B) implementation in Malaysia’s private construction projects is low compared to the nation’s public projects. Thus, the purpose of this paper…

Abstract

Purpose

The success rate of design-build (D-B) implementation in Malaysia’s private construction projects is low compared to the nation’s public projects. Thus, the purpose of this paper is to investigate the critical success factors (CSFs) for D-B implementation in Malaysian public construction projects.

Design/methodology/approach

To achieve the research objectives, 111 questionnaire survey responses from construction-related professionals were collected and analysed using multivariate analysis, including t-test, analysis of variance (ANOVA) and factor analysis.

Findings

The results indicate that while the client’s briefing effectiveness remained the top CSF among many nations, the other top CSFs in Malaysia D-B construction projects vastly differed compared to those countries. Moreover, the underlying components for successful D-B projects in Malaysia include the project management team, leader competency and “stakeholder” management.

Originality/value

This is one of the first studies that identify the CSFs for D-B implementation in the Malaysian construction industry. The outcomes provide a valuable reference and resource for academic scholars and construction practitioners to increase D-B implementation in the Malaysian private sector.

Details

Journal of Engineering, Design and Technology , vol. 20 no. 5
Type: Research Article
ISSN: 1726-0531

Keywords

Article
Publication date: 24 November 2021

Asif R. Khan and N. Lakshmi Thilagam

The unparalleled crisis due to the COVID-19 pandemic has displaced the existing normal in every field of higher education. Especially architecture education with high dependence…

Abstract

Purpose

The unparalleled crisis due to the COVID-19 pandemic has displaced the existing normal in every field of higher education. Especially architecture education with high dependence on institutional studio based pedagogical participation has been affected. Consequently, there is a critical necessity to reinvigorate pedagogical approaches in order to ensure continuity of pedagogical pursuits.

Design/methodology/approach

A systematic approach is used to conduct an interdisciplinary study. The research mainly attempts to externalize the basics of virtual design studio composition. In concurrence role of instructional design in providing an underlying framework for enabling virtual discourse is also explored. Primarily, the process commenced by identifying objectives and queries which needed to be addressed. In order to deal with the concerns rationally, the research used exploratory approach. The primary data were based on focus group interactions. The secondary data were based on relevant subject-oriented literature reviews; explicit information based. Explanatory mode of analysis is used to interpret the outcome.

Findings

A pedagogical design; an instructional design process model for effectively structuring the virtual design studio has evolved as part of the research. In addition detailed insights have been derived about the key integrals that make up the constituent phases of the virtual design studio.

Research limitations/implications

The research provides insights into the methodological structure of virtual design studio. The inferences would provide the pedagogues a comprehensive and rational overview to envision and conduct architecture studio discourse virtually.

Originality/value

The study presents a unique contribution to the limited literature available on virtual design studio pedagogy and instructional design in virtual mode.

Article
Publication date: 26 April 2024

Brett Rolfe

This paper explores the context within which experimental, pedagogically progressive schools were established in Australia during the first decades of the 20th century.

Abstract

Purpose

This paper explores the context within which experimental, pedagogically progressive schools were established in Australia during the first decades of the 20th century.

Design/methodology/approach

The paper presents a case study of the establishment of Rosbercon Girls’ Grammar School. It draws on educator accounts, archival documents and contemporary literature to provide a brief narrative of the events leading to the opening of the school; to sketch the family of educators who were pivotal in making it a reality; and to identify key aspects of the social and legislative context that made such an initiative possible.

Findings

Rosbercon was established at a time when a modest school could be established relatively easily by a small group of educators with a shared vision. The early 20th century was a moment of national optimism in Australia, where an appetite for new educational ideas created a climate in which innovative educators found fertile soil for their pedagogical experiments and adaptation of emerging ideas from around the world. Their efforts were facilitated by an emerging global network of personal interactions, professional learning, professional associations and educational literature.

Originality/value

This paper addresses the relative lack of scholarly examination of the origins of Rosbercon Girls’ Grammar School, an institution that previous authors have identified as Australia’s oldest experimental school. The case study also contributes to a broader appreciation of the trajectory of progressive education during the early 20th century.

Details

History of Education Review, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0819-8691

Keywords

Article
Publication date: 18 August 2021

Ibrahim Yahaya Wuni, Geoffrey Qiping Shen and Amos Darko

Industrialized construction (IC) leverages manufacturing principles and innovative processes to improve the performance of construction projects. Though IC is gaining popularity…

Abstract

Purpose

Industrialized construction (IC) leverages manufacturing principles and innovative processes to improve the performance of construction projects. Though IC is gaining popularity in the global construction industry, studies that establish the best practices for implementing IC projects are scarce. This study aims to benchmark practical lifecycle-based best practices for implementing IC projects.

Design/methodology/approach

The study used a qualitative research design where nine IC cases from Australia, Singapore and Hong Kong were analysed to identify best practices. The methodological framework of the study followed well-established case study research cycle and guidelines, including planning, data collection, data analysis and reflection on findings.

Findings

The study identified and allocated key considerations, relevant stakeholders, best practices, typical deliverables and best indicators to the different construction lifecycle phases of IC projects. It also developed a lifecycle-based framework of the best practices for IC projects.

Practical implications

The study provides practitioners with practical insight into how best to effectively implement, manage and evaluate the performance of the IC project lifecycle phases. The proposed framework can serve as a practical diagnostic tool that enables project partners to evaluate the performance upfront progressively and objectively in each project lifecycle phase, which may inform timely corrective actions.

Originality/value

The study’s novelty lies in developing a framework that identifies and demonstrates the dynamic linkages among different sets of best practices, typical outputs and best practice indicators across the IC project lifecycle phases.

Details

Construction Innovation , vol. 22 no. 4
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 1 September 2006

Jeffrey Haase

This paper describes a studio model that attempts to bridge the gap between conventional design studio settings and professional practice, by adopting design-build principles that…

Abstract

This paper describes a studio model that attempts to bridge the gap between conventional design studio settings and professional practice, by adopting design-build principles that incorporate experiential learning theory, derived from the early research of Dewey, Lewin, and Piaget. Part of the dichotomy of the profession is the dynamic difference in the established representational tools of the trade and the result of the built environment. This disconnect exists because the tools of the trade utilize two dimensional explanations about a three dimensional place, typically comprised of drawings in the form of plans, elevations, and perspectives. Additionally, there is a dynamic difference in scale that exists between these tools and the environments they represent. Thus, design educators tend to teach representational techniques without teaching a clear understanding of what they represent. This gap in education creates a gap in the profession. The described case studies outline an alternative studio model that is intended to introduce some of the “realities” often missing in a conventional studio approach. Each of the case studies involved second year Interior Design students, who were given the parameters of an existing space with specific user needs. The students had to design and then physically construct that interior environment all within a ten week time period (one academic quarter). By creating a more “hands-on” learning environment, it is the hope that students retain that knowledge in a more meaningful and lasting way, with the ability to transfer that experience over to similar situations in other studio settings and within the professional practice.

Details

Open House International, vol. 31 no. 3
Type: Research Article
ISSN: 0168-2601

Keywords

Article
Publication date: 1 January 1997

Oshani Perera

To develop more sustainable tourism, the Cleaner Production approach in sitting, designing, building and managing tourism facilities and hotels appears essential.

Abstract

To develop more sustainable tourism, the Cleaner Production approach in sitting, designing, building and managing tourism facilities and hotels appears essential.

Details

The Tourist Review, vol. 52 no. 1
Type: Research Article
ISSN: 0251-3102

Open Access
Article
Publication date: 6 June 2022

Natalia Garcia Cervantes and Karen Hinojosa Hinojosa

The purpose of this article is the discussion of a service-learning experience in architecture pedagogy, based on two core courses at a private university in Mexico. The aim is to…

1427

Abstract

Purpose

The purpose of this article is the discussion of a service-learning experience in architecture pedagogy, based on two core courses at a private university in Mexico. The aim is to identify learning opportunities, challenges and implications arising from engaging with inhabitants of an informal urban settlement with limited digital resources in La Campana-Altamira in Monterrey, Mexico.

Design/methodology/approach

The methodology selected is a case study approach, chosen for its effectiveness in architectural pedagogy to create knowledge through exposure to a particular phenomenon, as well as highlight positive teaching practices to facilitate replicability. Case-study methodology was also beneficial in this case because its openness and flexibility allowed for research of a variety of phenomena simultaneously, in this case, both the effects in the informal settlement community and in the academic one.

Findings

Findings revealed that opportunities outweigh challenges, and meaningful service and learning are possible in an online context, even when the service aspects take longer than the course length if there are long-term relationships between communities and institutions.

Originality/value

The value of the article lies in the need for flexible and sensitive approaches that put communities in the center, a critical path to identifying and understanding their needs and improving their contexts. This holds especially true given the rapid pace of worldwide urbanization and the ubiquity of informal urban settlements. Implementing service-learning approaches in informal settings using online tools, while sanitary restrictions are in place shows that meaningful experiences can be achieved, even when courses are short and resources are limited.

Details

Archnet-IJAR: International Journal of Architectural Research, vol. 17 no. 2
Type: Research Article
ISSN: 2631-6862

Keywords

1 – 10 of 225