1 – 10 of 19Richard Kadan, Temitope Seun Omotayo, Prince Boateng, Gabriel Nani and Mark Wilson
This study aimed to address a gap in subcontractor management by focusing on previously unexplored complexities surrounding subcontractor management in developing countries. While…
Abstract
Purpose
This study aimed to address a gap in subcontractor management by focusing on previously unexplored complexities surrounding subcontractor management in developing countries. While past studies concentrated on selection and relationships, this study delved into how effective subcontractor management impacts project success.
Design/methodology/approach
This study used the Bayesian Network analysis approach, through a meticulously developed questionnaire survey refined through a piloting stage involving experienced industry professionals. The survey was ultimately distributed among participants based in Accra, Ghana, resulting in a response rate of approximately 63%.
Findings
The research identified diverse components contributing to subcontractor disruptions, highlighted the necessity of a clear regulatory framework, emphasized the impact of financial and leadership assessments on performance, and underscored the crucial role of main contractors in Integrated Project and Labour Cost Management with Subcontractor Oversight and Coordination.
Originality/value
Previous studies have not considered the challenges subcontractors face in projects. This investigation bridges this gap from multiple perspectives, using Bayesian network analysis to enhance subcontractor management, thereby contributing to the successful completion of construction projects.
Details
Keywords
Sarfo Mensah, Gabriel Nani and Joshua Ayarkwa
There is low adoption rate of existing environmentally sustainable construction frameworks. Contractors have dwindled capability to adapt to environmentally sustainable…
Abstract
Purpose
There is low adoption rate of existing environmentally sustainable construction frameworks. Contractors have dwindled capability to adapt to environmentally sustainable construction (ESC) towards achievement of SDGs. The aim of this paper is to develop a framework that leverages both theoretical and practical aspects of sustainable construction to enable contractors' adaptation to ESC at the micro level.
Design/methodology/approach
Due to the social constructivism orientation of the objectives of this research, abductive approach and qualitative research strategy were adopted. Data were obtained through interviews and validation focus group discussion. Content analysis and thematic template analyses techniques were employed to conduct qualitative data analyses.
Findings
There are peculiar ESC barriers that need to be overcome by contractors in the study area. Legislative and financing efforts of stakeholders are key contractors' ESC adaptation drivers. Contractors in less affluent societies, such as Ghana, require high resilience, dense and centralized social network structures and isomorphic and coercive drivers to be able to adapt to ESC.
Research limitations/implications
The scope of this research is limited to the data gathered from large construction firms in Ghana, a developing country in the sub-Saharan region.
Originality/value
This is one of the first papers that provide guidelines on developing capability of contractors in a developing country to adapt to ESC. The paper addresses the challenge in the ecological modernization theory by adducing empirical evidence to prescribe guidelines on how contractors can increase rate of efficiency through collaborative strategies that engender ESC.
Details
Keywords
Safowaa Osei-Tutu, Joshua Ayarkwa, Gabriel Nani, Dickson Osei-Asibey and Ivy Maame Adwoa Abu
This study aims to identify in literature the role of construction stakeholders in the implementation of circular economy (CE) in the construction industry (CI). This study also…
Abstract
Purpose
This study aims to identify in literature the role of construction stakeholders in the implementation of circular economy (CE) in the construction industry (CI). This study also sought to identify the status quo and research trend, “hot themes”, areas requiring more research and future research direction of stakeholders’ role in CE implementation in the CI.
Design/methodology/approach
A literature search was conducted using the Scopus search engine, augmented by Google Scholar to produce 50 relevant articles for the identification of stakeholders’ roles using content analysis. The scientometric study was undertaken using VOSviewer on 42 articles obtained from Scopus search to identify the status quo, “hot themes”, knowledge gaps and future research direction of the role of stakeholders in CE implementation.
Findings
Through content analysis, the identified roles of government as a stakeholder are to develop efficient policy instruments, legislation support and financial investment in research and development activities that will promote the smooth implementation of CE. The role of academia/research is to engage in research aimed at investigating both the short-term behaviour and the durability of recycled materials and products. In addition, the roles of professionals in the consultant/design/procurement team are to design with life cycle assessment and reused materials, design for deconstruction and disassembly, etc. The role of the user/consumer is to ensure knowledge diffusion and awareness exchange that recognize the available opportunities for long-term material usage (including repair, reuse, refurbishment and recycling). The research status quo identified from the scientometric analysis include how stakeholders can come up with innovative ways in demolition that will ensure that more of the materials can be reused. Stakeholders should focus on enacting policies and laws that can promote the use of recycled materials in buildings, etc. Research that focuses on how to engage the various construction stakeholders to come up with specific public policy that will promote CE implementation, identifying the specific roles to be played by stakeholders during policy enactment as well as managing the environment, laws and legislations towards CE implementation. The role of stakeholders in the extension of the life span of projects, the use of strategies to minimize waste generation and standardization of building materials, components and connectors with the purpose of simplifying disassembly are the research gaps and areas for future research studies. Some of the research “hot themes” include “circular business models in the CI”, “environmental sustainability policy implementation”, “environmental, economic and social sustainability”, “policy, laws and legislations on waste management” and “environmental and industrial economics” towards CE implementation.
Practical implications
The findings from this study serve as a valuable reference for construction stakeholders to assess their specific roles as stakeholders and to identify the status quo and research trend, “hot themes”, areas requiring more research and future research directions on stakeholders’ roles in CE implementation in the CI.
Originality/value
Identifying the role of stakeholders for CE implementation is one bold step towards the achievement of CE implementation in the CI.
Details
Keywords
Safowaa Osei-Tutu, Joshua Ayarkwa, Dickson Osei-Asibey, Gabriel Nani and Aba Essanowa Afful
This study aimed to identify barriers impeding circular economy (CE) uptake in the construction industry in literature, categorize them for the development of a framework and to…
Abstract
Purpose
This study aimed to identify barriers impeding circular economy (CE) uptake in the construction industry in literature, categorize them for the development of a framework and to seek the interrelationships among the categorized barriers. This allowed for identifying integrated solutions to holistically address the barriers. The study also sought to identify the “hot” themes, the knowledge gaps and future research directions on barriers impeding CE.
Design/methodology/approach
Forty-eight relevant articles were desk reviewed from different construction peer-reviewed journals and published conference papers. A scientometric analysis allowed for co-occurrence of keywords relating to CE. A content analysis enabled the identification of 79 barriers impeding the uptake of CE in the construction industry which were further categorized into six distinct categories for the development of a framework showing the interrelationships among the categorized barriers.
Findings
The identified barriers include construction sector inertia, lack of design standards, lack of knowledge, awareness and understanding, design cost, and perception of second-hand materials as substandard among others. The study categorized the identified barriers for better understanding into six different groups: cultural barriers, social barriers, environmental barriers, economic barriers, technical barriers and technological barriers. Strategies to address the barriers were also proposed. The interrelationships among the various barriers were also shown in a proposed framework to educate professionals on the interconnectivity of the barriers.
Practical implications
Categorization of the various barriers impeding CE uptake contributes to the body of knowledge. Also, the interrelationships among the various categorized barriers in the framework will enable construction professionals make informed decisions regarding the successful integration of CE in the industry, better appreciate the barriers that impede CE uptake and apply strategies to holistically address the barriers. This will expand current knowledge outside the narrow scope of isolated barriers.
Social implications
To the global construction industry, the review presents a list of barriers and their interrelationships that could provide implementation strategies for the uptake of CE in the industry.
Originality/value
The geographical scope of this study is not limited, and therefore encourages wide applicability of the findings to the global construction industry.
Details
Keywords
Sitsofe Kwame Yevu, Ann Tit Wan Yu, Amos Darko, Gabriel Nani and David J. Edwards
This study aims to investigate the dynamic influences of clustered barriers that hinder electronic procurement technology (EPT) implementation in construction procurement, using…
Abstract
Purpose
This study aims to investigate the dynamic influences of clustered barriers that hinder electronic procurement technology (EPT) implementation in construction procurement, using the neuro-fuzzy system.
Design/methodology/approach
A comprehensive literature review was conducted and 21 barriers to EPT implementation within construction projects were identified. Based on an expert survey, 121 datasets were gathered for this study. Using mean and normalization analysis for the datasets, 15 out of the 21 barriers were deemed to have critical influences in EPT barriers phenomenon. Subsequently, the critical barriers were classified into five groups: human-related; technological risk-related; government-related; industry growth-related; and financial-related. The relationships and influence patterns between the groups of barriers to EPT implementation were analyzed using the neuro-fuzzy system. Furthermore, sensitivity analysis was performed to examine the dynamic influence levels of the barriers within the hindrance level composition.
Findings
The results reveal that addressing one barrier group does not reduce the high levels of hindrances experienced in EPT implementation. However, addressing at least two barrier groups mostly tends to reduce the hindrance levels for EPT implementation. Further, this study revealed that addressing some barrier group pairings, such as technological risk-related and government-related barriers, while other barrier groups remained at a high level, still resulted in high levels of hindrances to EPT implementation in construction procurement.
Research limitations/implications
This study provides insights for researchers to help them contribute to the development of theory with contemporary approaches based on the influence patterns of barrier interrelationships.
Practical implications
This study provides a model that would help practitioners and decision makers in construction procurement to understand and effectively determine the complex and dynamic influences of barrier groups to EPT uptake, for the development of suitable mitigation strategies.
Originality/value
This study provides novel insights into the complex influence patterns among grouped barriers concerning EPT adoption in the construction industry. Researchers and practitioners are equipped with knowledge on the influence patterns of barriers. This knowledge aids the development of effective strategies that mitigate the combined groups of barriers, and promote the wider implementation of EPT in the construction industry.
Details
Keywords
Isaac Mensah, Theophilus Adjei-Kumi and Gabriel Nani
Determining the duration for road construction projects represents a problem for construction professionals in Ghana. The purpose of this paper is to develop an artificial neural…
Abstract
Purpose
Determining the duration for road construction projects represents a problem for construction professionals in Ghana. The purpose of this paper is to develop an artificial neural network (ANN) model for determining the duration for rural bituminous surfaced road projects.
Design/methodology/approach
Data for 22 completed bituminous surfaced road projects from the Department of Feeder Roads (rural road agency) were collected and analyzed using the principal component analysis (PCA) and ANN techniques. The data collected were final payment certificates which contained payment bill of quantities (BOQ) of work items executed for the selected completed road projects. The executed quantities in the BOQ were the total quantities of work items for site clearance, earthworks, in-situ concrete, reinforcement, formwork, gravel sub-base/base, bitumen, road line markings and furniture, length of road and actual durations for each of the completed projects. The PCA was first employed to reduce the data in order to identify a smaller number of variables (or significant quantities) that constitute 81.58 percent of the total variance of the collected data. The ANN was then used to develop the network using the identified significant quantities as input variables and the actual durations as output variables.
Findings
The coefficient of correlation (R) and determination (R2) as well as the mean absolute percentage error (MAPE) obtained show that construction professionals can use the developed ANN model for determining duration. The study shows that the best neural network is the multi-layer perceptron with a structure 3-38-1 based on a back propagation feed forward algorithm. The developed network produces good results with an MAPE of 17.56 percent or an average accuracy of 82.44 percent.
Research limitations/implications
Apart from the fact that the sample size was small, the developed model does not incorporate the implications of other likely factors that may affect contract duration.
Practical implications
The outcome of this study is to help construction professionals to fix realistic contract duration for road construction projects before signing a contract. Such realistic contract duration would help reduce time overruns as well as the payment of liquidated and ascertained damages by contractors for late completion.
Originality/value
This paper proposes an alternative way of determining the duration for road construction projects using the total quantities of work items in a final payment BOQ. The approach is based on the PCA and ANN model of quantities of work items of completed road projects.
Details
Keywords
Mershack Opoku Tetteh, Albert P.C. Chan, Gabriel Nani, Amos Darko and Goodenough D. Oppong
While previous studies have focused on identifying management control (MC) mechanisms in international construction joint ventures (ICJVs), the impacts of such MC mechanisms on…
Abstract
Purpose
While previous studies have focused on identifying management control (MC) mechanisms in international construction joint ventures (ICJVs), the impacts of such MC mechanisms on the performance of ICJVs remain largely unknown. This study aims to investigate the impacts of MC mechanisms on the performance of ICJVs hosted in the developing country of Ghana.
Design/methodology/approach
Through a comprehensive review of the literature, a theoretical model was developed, and data were collected through a questionnaire survey with 190 project managers composed of Ghanaians/locals and their foreign partners of ICJVs. The data were analyzed using partial least squares structural equation modeling.
Findings
Results showed that both personnel and support and training control mechanisms have a positive and significant impact on project and company/partner performance. Surprisingly, insignificant and negative impacts exist between both mechanisms and socioenvironmental and company/partner performance from the local partners' view, respectively; the reverse is rather true from the foreign partners' perspective.
Practical implications
This study contributes to the ICJV body of knowledge by analyzing the impacts of MC mechanisms on the ICJVs’ performance, enabling ICJVs frontliners (i.e. top managers) and project managers to better enhance their control structures and the ICJVs’ performance.
Originality/value
This is arguably the first study to take the bipartite perspective rather than the unilateral view of studying the impacts of MC mechanisms on the performance of ICJVs.
Details
Keywords
Richard Ohene Asiedu, Nana Kena Frempong and Gabriel Nani
Time overruns are commonplace within the construction industry. These result in deception because project managers critically assess the economic and financial viability of a…
Abstract
Purpose
Time overruns are commonplace within the construction industry. These result in deception because project managers critically assess the economic and financial viability of a project before implementation. Forecasting the likelihood of time overruns will not only lead to a reconsideration on the decision to build but also help put in place the necessary control measures – exactly what this research achieved.
Design/methodology/approach
The paper argues that rather than depending on the critical failure factors that are unknown at the pre-contract stage to forecast the likelihood of occurrence, it will be more useful to rely on project attributes that are known before contract signing. A multiple linear regression analysis is used for the model development based on ten independent variables.
Findings
About 86.6 per cent of all the projects experienced time overruns. The mean time overrun is 106.5 per cent. Initial contract sum, initial duration, gross floor area, contractor class D2K2, competitive tendering, sole sourcing and single-storey buildings explained about 44.7 per cent of the variations within time overruns, with a mean absolute percentage error of 60.7 per cent.
Research limitations/implications
The predictive accuracy of the model can, in practice, be tested after the completion of a project by comparing the actual project schedule with the planned schedule. Any disparity in the expected outputs should result in a reassessment of the significant independent variables to improve the forecasting abilities of the model.
Practical implications
The model is expected to be very useful at the pre-contract stage when detailed designs are unavailable. As a decision support system, it will help the practitioners and decision-makers make informed decisions while minimizing the time and resources spent to arrive at these decisions.
Originality/value
This research presents a unique opportunity to forecast the likelihood of time overruns within the building sector based on project attributes that are known before the contract-signing phase.
Details
Keywords
Jemima Antwiwaa Ottou, Bernard Kofi Baiden and Gabriel Nani
Project management tools and techniques have been widely adopted in the construction industry; however, its combination with Six Sigma and application in construction procurement…
Abstract
Purpose
Project management tools and techniques have been widely adopted in the construction industry; however, its combination with Six Sigma and application in construction procurement has not been widely researched. This paper explores the use of Six Sigma Project Procurement (SSPP) and its potential applications in public sector construction procurement.
Design/methodology/approach
The role of Six Sigma and project management in construction is critically evaluated using three case studies to demonstrate their application in public procurement.
Findings
The use of SSPP by public sector organisations creates efficient and effective construction procurement processes by addressing delays. The proposed timelines for competitive tendering in the Ghanaian Public Procurement Manual are not realistic.
Research limitations/implications
This paper contributes to and broadens the limited body of evidence and knowledge of applying SSPP to public procurement processes and identifies areas for further research.
Practical implications
Project management will continue to expand in the global construction industry. However, what will eventually determine if SSPP is embraced by public sector construction depends on the leadership and success of its execution. The application of SSPP to public construction procurement will address delays and lead to significant time reduction of the process. This will eliminate the major issue (delay) accounting for deficiencies in the process.
Originality/value
The paper yields immense value to construction project management researchers and practitioners, especially in the public sector. It recommends the inclusion of Six Sigma to promote focus on actual instead of perceived problems and advocates for decisions-making based on facts which will ensure continuous improvement.
Details
Keywords
Gabriel Nani, Isaac Mensah and Theophilus Adjei-Kumi
A major concern for construction professionals at the rural road agency in Ghana is the problem of fixing contract duration for bridge construction projects in rural areas. The…
Abstract
Purpose
A major concern for construction professionals at the rural road agency in Ghana is the problem of fixing contract duration for bridge construction projects in rural areas. The purpose of the study was to develop a tool for construction professionals to forecast duration for bridge projects.
Design/methodology/approach
In all, 100 questionnaires were distributed to professionals at the Department of Feeder Roads to ascertain their views on the work items in a bill of quantities (BOQ) that impact significantly on the duration of bridge construction projects. Historical data for 30 completed bridge projects were also collected from the same Department. The data collected were executed work items in BOQ and actual durations used in completing the works. The qualitative data were analysed using the relative importance index and the quantitative data, processed and analysed using both the stepwise regression method and artificial neural network (ANN) technique.
Findings
The identified predictors, namely, in-situ concrete, weight of prefabricated steel components, gravel sub-base and haulage of aggregates, used as independent variables resulted in the development of a regression model with a mean absolute percentage error (MAPE) of 25 per cent and an ANN model with a feed forward back propagation algorithm with an MAPE of 26 per cent at the validation stage. The study has shown that both regression and ANN models are appropriate for predicting the duration of a new bridge construction project.
Research limitations/implications
The predictors used in the developed models are limited to work items in BOQs only of completed bridge construction projects as well as the small sample size.
Practical implications
The study has developed a working tool for practitioners at the agency to forecast contract duration for bridge projects prior to its commencement.
Originality value
The study has quantified the relationship between the work items in BOQs and the duration of bridge construction projects using the stepwise regression method and the ANN techniques.