Duration estimation model for bridge construction projects in Ghana

Gabriel Nani (Department of Building Technology, College of Art and Built Environment, Kwame Nkrumah University of Science and Technology, Kumasi, Ghana)
Isaac Mensah (Department of Feeder Roads, Ministry of Roads and Highways, Ghana and Department of Building Technology, College of Art and Built Environment, Kwame Nkrumah University of Science and Technology, Kumasi, Ghana)
Theophilus Adjei-Kumi (Department of Building Technology, College of Art and Built Environment, Kwame Nkrumah University of Science and Technology, Kumasi, Ghana)

Journal of Engineering, Design and Technology

ISSN: 1726-0531

Article publication date: 4 December 2017

390

Abstract

Purpose

A major concern for construction professionals at the rural road agency in Ghana is the problem of fixing contract duration for bridge construction projects in rural areas. The purpose of the study was to develop a tool for construction professionals to forecast duration for bridge projects.

Design/methodology/approach

In all, 100 questionnaires were distributed to professionals at the Department of Feeder Roads to ascertain their views on the work items in a bill of quantities (BOQ) that impact significantly on the duration of bridge construction projects. Historical data for 30 completed bridge projects were also collected from the same Department. The data collected were executed work items in BOQ and actual durations used in completing the works. The qualitative data were analysed using the relative importance index and the quantitative data, processed and analysed using both the stepwise regression method and artificial neural network (ANN) technique.

Findings

The identified predictors, namely, in-situ concrete, weight of prefabricated steel components, gravel sub-base and haulage of aggregates, used as independent variables resulted in the development of a regression model with a mean absolute percentage error (MAPE) of 25 per cent and an ANN model with a feed forward back propagation algorithm with an MAPE of 26 per cent at the validation stage. The study has shown that both regression and ANN models are appropriate for predicting the duration of a new bridge construction project.

Research limitations/implications

The predictors used in the developed models are limited to work items in BOQs only of completed bridge construction projects as well as the small sample size.

Practical implications

The study has developed a working tool for practitioners at the agency to forecast contract duration for bridge projects prior to its commencement.

Originality value

The study has quantified the relationship between the work items in BOQs and the duration of bridge construction projects using the stepwise regression method and the ANN techniques.

Keywords

Citation

Nani, G., Mensah, I. and Adjei-Kumi, T. (2017), "Duration estimation model for bridge construction projects in Ghana", Journal of Engineering, Design and Technology, Vol. 15 No. 6, pp. 754-777. https://doi.org/10.1108/JEDT-04-2017-0029