To read this content please select one of the options below:

Duration determination for rural roads using the principal component analysis and artificial neural network

Isaac Mensah (Department of Building Technology, Kwame Nkrumah University of Science and Technology, Kumasi, Ghana)
Theophilus Adjei-Kumi (Department of Building Technology, Kwame Nkrumah University of Science and Technology, Kumasi, Ghana)
Gabriel Nani (Department of Building Technology, Kwame Nkrumah University of Science and Technology, Kumasi, Ghana)

Engineering, Construction and Architectural Management

ISSN: 0969-9988

Article publication date: 19 September 2016

507

Abstract

Purpose

Determining the duration for road construction projects represents a problem for construction professionals in Ghana. The purpose of this paper is to develop an artificial neural network (ANN) model for determining the duration for rural bituminous surfaced road projects.

Design/methodology/approach

Data for 22 completed bituminous surfaced road projects from the Department of Feeder Roads (rural road agency) were collected and analyzed using the principal component analysis (PCA) and ANN techniques. The data collected were final payment certificates which contained payment bill of quantities (BOQ) of work items executed for the selected completed road projects. The executed quantities in the BOQ were the total quantities of work items for site clearance, earthworks, in-situ concrete, reinforcement, formwork, gravel sub-base/base, bitumen, road line markings and furniture, length of road and actual durations for each of the completed projects. The PCA was first employed to reduce the data in order to identify a smaller number of variables (or significant quantities) that constitute 81.58 percent of the total variance of the collected data. The ANN was then used to develop the network using the identified significant quantities as input variables and the actual durations as output variables.

Findings

The coefficient of correlation (R) and determination (R2) as well as the mean absolute percentage error (MAPE) obtained show that construction professionals can use the developed ANN model for determining duration. The study shows that the best neural network is the multi-layer perceptron with a structure 3-38-1 based on a back propagation feed forward algorithm. The developed network produces good results with an MAPE of 17.56 percent or an average accuracy of 82.44 percent.

Research limitations/implications

Apart from the fact that the sample size was small, the developed model does not incorporate the implications of other likely factors that may affect contract duration.

Practical implications

The outcome of this study is to help construction professionals to fix realistic contract duration for road construction projects before signing a contract. Such realistic contract duration would help reduce time overruns as well as the payment of liquidated and ascertained damages by contractors for late completion.

Originality/value

This paper proposes an alternative way of determining the duration for road construction projects using the total quantities of work items in a final payment BOQ. The approach is based on the PCA and ANN model of quantities of work items of completed road projects.

Keywords

Citation

Mensah, I., Adjei-Kumi, T. and Nani, G. (2016), "Duration determination for rural roads using the principal component analysis and artificial neural network", Engineering, Construction and Architectural Management, Vol. 23 No. 5, pp. 638-656. https://doi.org/10.1108/ECAM-09-2015-0148

Publisher

:

Emerald Group Publishing Limited

Copyright © 2016, Emerald Group Publishing Limited

Related articles