Nuno Miguel de Matos Torre and Andrei Bonamigo

Maintenance represents an indispensable role in the productive sector of the steel industry. The increasing use of operating with a high level of precision makes hydraulic systems…

Abstract

Purpose

Maintenance represents an indispensable role in the productive sector of the steel industry. The increasing use of operating with a high level of precision makes hydraulic systems one of the issues that require a high level of attention. This study aims to explore an empirical investigation for decreasing the occurrences of corrective maintenance of hydraulic systems in the context of Lean 4.0.

Design/methodology/approach

The maintenance model is developed based on action-research methodology through an empirical investigation, with nine stages. This approach aims to build a scenario to analyze and interpret the occurrences, seeking to implement and evaluate the actions to be performed. The undertaken initiatives demonstrate that this approach can be applied to optimize the maintenance of an organization.

Findings

The main contribution of this paper is to demonstrate that the applied method allows the overviewing results, with a qualitative approach concerning the maintenance actions and management processes to be considered, allowing a holistic understanding and contributing to the current literature. The results also indicated that Lean 4.0 has direct and mediating effects on maintenance performance.

Originality/value

This research intends to propose an evaluation framework with an interdimensional linkage between action research methodology and Lean 4.0, to explore an empirical investigation and contributing to understanding the actions to reduce the occurrences of hydraulic systems corrective maintenance in a production line in the steel industry.

Details

Journal of Quality in Maintenance Engineering, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1355-2511

Keywords

Article
Publication date: 19 December 2023

Zul-Atfi Ismail

Operation and maintenance (O&M) processes projects such as identification, assessment, planning and execution, embody a variety of standards such as technical (method of…

Abstract

Purpose

Operation and maintenance (O&M) processes projects such as identification, assessment, planning and execution, embody a variety of standards such as technical (method of statement), environmental, economic (campus development) and social (health and wellbeing). Because these standards have proven to be challenging to integrate, local governments are increasingly experimenting with social innovation (SI) as a bottom-up form of standard integration. This study aims to apply the concept of SI to the O&M processes of facilities management at polytechnics in Malaysia to identify problems with conventional working practices in this area and to recommend potential solutions.

Design/methodology/approach

The paper reviews evidence that conventional working methods generate significant problems related to paper-based forms, improper database management and flawed decision-making processes. Because of the lack knowledge about different ways of how standard integration is achieved, the comparison of three polytechnic institutions which are Rensselaer Polytechnic Institute (RPI) and Southern Polytechnic College of Engineering and Engineering Technology (SPCEET) in USA as well as Seberang Perai Polytechnic, Pulau Pinang (PSP) in Malaysia shares the ambition to realise standard integration of O&M through SI.

Findings

The findings reveal that SI leads to four ways of standard integration: computerised maintenance management system, online customer complaint, electronic form and relational database. Application of the concept of SI reveals the need for more sophisticated management solutions in the O&M processes of facilities management.

Originality/value

These standard integration arrangements unfortunately seem to mainly contribute to greater alignment between standard rather than true standard integration. The concept of SI will guide future improvements and developments in maintenance management systems to fulfil requirements in this area.

Details

Journal of Global Responsibility, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 2041-2568

Keywords

Article
Publication date: 26 April 2024

Mawloud Titah and Mohammed Abdelghani Bouchaala

This paper aims to establish an efficient maintenance management system tailored for healthcare facilities, recognizing the crucial role of medical equipment in providing timely…

Abstract

Purpose

This paper aims to establish an efficient maintenance management system tailored for healthcare facilities, recognizing the crucial role of medical equipment in providing timely and precise patient care.

Design/methodology/approach

The system is designed to function both as an information portal and a decision-support system. A knowledge-based approach is adopted centered on Semantic Web Technologies (SWTs), leveraging a customized ontology model for healthcare facilities’ knowledge capitalization. Semantic Web Rule Language (SWRL) is integrated to address decision-support aspects, including equipment criticality assessment, maintenance strategies selection and contracting policies assignment. Additionally, Semantic Query-enhanced Web Rule Language (SQWRL) is incorporated to streamline the retrieval of decision-support outcomes and other useful information from the system’s knowledge base. A real-life case study conducted at the University Hospital Center of Oran (Algeria) illustrates the applicability and effectiveness of the proposed approach.

Findings

Case study results reveal that 40% of processed equipment is highly critical, 40% is of medium criticality, and 20% is of negligible criticality. The system demonstrates significant efficacy in determining optimal maintenance strategies and contracting policies for the equipment, leveraging combined knowledge and data-driven inference. Overall, SWTs showcases substantial potential in addressing maintenance management challenges within healthcare facilities.

Originality/value

An innovative model for healthcare equipment maintenance management is introduced, incorporating ontology, SWRL and SQWRL, and providing efficient data integration, coordinated workflows and data-driven context-aware decisions, while maintaining optimal flexibility and cross-departmental interoperability, which gives it substantial potential for further development.

Details

Journal of Quality in Maintenance Engineering, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1355-2511

Keywords

Article
Publication date: 13 November 2023

Thisara Manupriya Sathkumara, Anuradha Samarajeewa Waidyasekara and Hasith Chathuranga Victar

The use of renewable energy has become necessary because of the harmful effects of current energy sources on the environment, limited availability and financial crisis…

Abstract

Purpose

The use of renewable energy has become necessary because of the harmful effects of current energy sources on the environment, limited availability and financial crisis. Transparent solar panels have emerged as a promising technology for integrating renewable energy generation into building structures. Therefore, this paper aims to explore the feasibility of transparent solar panels for high-rise building façades in Sri Lanka.

Design/methodology/approach

The research apprehended a qualitative approach, including two expert interview rounds adhering to the Delphi technique with 17 and 15 experts each per round. Manual content analysis was incorporated to analyse the collected data.

Findings

Regarding operation and maintenance, the study emphasizes the importance of regular inspection, cleaning and repair of transparent solar panels to ensure optimal performance and longevity. These activities contribute to maximizing energy generation and maintaining the aesthetic appeal of the building. The benefits of implementing transparent solar panels on building façades are manifold. They include renewable energy generation, reduced greenhouse gas emissions, improved energy efficiency and enhanced architectural aesthetics. Furthermore, the research findings underscore the potential of transparent solar panels to contribute to Sri Lanka’s sustainable development goals and address the country’s increasing energy demand. However, the study also identifies challenges that need to be addressed for successful implementation.

Originality/value

This study contributes to understanding the feasibility of transparent solar panels for high-rise building façades in Sri Lanka. The research findings offer valuable insights into the operation and maintenance aspects, benefits, challenges and strategies for implementing transparent solar panels effectively. This knowledge can guide policymakers, architects and developers in making informed decisions regarding the integration of transparent solar panels, thereby promoting sustainable and energy-efficient building practices in Sri Lanka.

Details

Construction Innovation , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 9 February 2024

Runze Yu and Li Ma

The paper covers mega infrastructure construction supply chain (MICSC) in Engineering-Procurement-Construction (EPC) projects, where the frequent occurrence of risk incidents has…

138

Abstract

Purpose

The paper covers mega infrastructure construction supply chain (MICSC) in Engineering-Procurement-Construction (EPC) projects, where the frequent occurrence of risk incidents has greatly affected human life. The research aims to establish a risk evaluation index system for MICSC in EPC projects, exploring what risk factors lead to risk incidents and measure the importance and causality of all these risk factors.

Design/methodology/approach

The research applies a combination of quantitative and qualitative analysis methodology to process data sequentially. In the first place, risk factors for MICSC in EPC projects are extracted and identified from literature survey and expert interviews. In the second place, an integration model fuzzy Analytic Hierarchy Process (f-AHP) and fuzzy Decision-making Trial and Evaluation Laboratory (f-DEMATEL) is constructed to comprehensively analyze all these risk factors.

Findings

12 primary risk factors and 36 secondary risk factors comprise the risk evaluation index system for MICSC in EPC projects from 178 literature and 5 professionals. The results indicate that Political Situation (F1), Social Security (F2) and Management Mode (F8) are critical risk factors, where F1 and F2 are cause factors and F8 is an effect factor.

Originality/value

There are three main contributions of this paper. First and foremost, from the perspective of the research content, no other study has been able to assess risk factors for MICSC in EPC projects, while embedding nine phases of the whole project life cycle and six subjects of stakeholders into a risk evaluation index system. Additionally, from the perspective of research method, a combined model incorporating f-AHP and f-DEMATEL is constructed to avoid the one-sidedness of a single model. Last but not least, from the perspective of practical significance, focusing on the critical risk factors, a series of effective measures are formulated to make appropriate management decisions for nodal enterprises of MICSC, which can improve their risk management capabilities.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 1 May 2024

Fatemeh Shaker, Arash Shahin and Saeed Jahanyan

This paper aims to simulate vital corrective actions (CAs) affecting system availability through a system dynamics approach based on the results obtained by analyzing the causal…

Abstract

Purpose

This paper aims to simulate vital corrective actions (CAs) affecting system availability through a system dynamics approach based on the results obtained by analyzing the causal relationships among failure modes and effects analysis elements.

Design/methodology/approach

A stock and flow diagram has been developed to simulate system behaviors during a timeframe. Some improvement scenarios regarding the most necessary CAs according to their strategic priority and the possibility of eliminating root causes of critical failure modes in a roller-transmission system have been simulated and analyzed to choose the most effective one(s) for the system availability. The proposed approach has been examined in a steel-manufacturing company.

Findings

Results indicated the most effective CAs to remove or diminish critical failure causes that led to the less reliability of the system. It illustrated the impacts of the selected CAs on eliminating or decreasing root causes of the critical failure modes, lessening the system’s failure rate and increasing the system availability more effectively.

Research limitations/implications

Results allow managers and decision-makers to consider different maintenance scenarios without wasting time and more cost, choosing the most appropriate option according to system conditions.

Originality/value

This study innovation would be the dynamic analysis of interactions among failure modes, effects and causes over time to predict the system behavior and improve availability by choosing the most effective CAs through improvement scenario simulation via VENSIM software.

Details

Journal of Modelling in Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1746-5664

Keywords

Article
Publication date: 17 April 2024

Zul-Atfi Ismail

This paper aims to identify the different system approach using Building Information Modelling (BIM) technology that is equipped with decision making processes. Maintenance…

Abstract

Purpose

This paper aims to identify the different system approach using Building Information Modelling (BIM) technology that is equipped with decision making processes. Maintenance planning and management are integral components of the construction sector, serving the broader purpose of post-construction activities and processes. However, as Precast Concrete (PC) construction projects increase in scale and complexity, the interconnections among these activities and processes become apparent, leading to planning and performance management challenges. These challenges specifically affect the monitoring of façade components for corrective and preventive maintenance actions.

Design/methodology/approach

The concept of maintenance planning for façades, along with the main features of information and communication technology tools and techniques using building information modeling technology, is grounded in the analysis of numerous literature reviews in PC building scenarios.

Findings

This research focuses on an integrated system designed to analyze information and support decision-making in maintenance planning for PC buildings. It is based on robust data collection regarding concrete façades' failures and causes. The system aims to provide appropriate planning decisions and minimize the risk of façade failures throughout the building's lifetime.

Originality/value

The study concludes that implementing a research framework to develop such a system can significantly enhance the effectiveness of maintenance planning for façade design, construction and maintenance operations.

Details

Facilities , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0263-2772

Keywords

Open Access
Article
Publication date: 14 December 2023

Marta Tkaczyk, Anna Salina, Jouni Lyly-Yrjänäinen and Teemu Laine

New service businesses carry opportunities for industrial companies. The different cost management and management control implications of those service businesses deserve…

Abstract

Purpose

New service businesses carry opportunities for industrial companies. The different cost management and management control implications of those service businesses deserve attention, which is a widely under-researched area in management accounting and control literature. Digital twins could hold potential in unveiling and supporting those new service business opportunities, as a unique approach of this paper. Thus, the purpose of this paper is to examine the possibility and potential for creating a digital twin of a service, especially to unveil the management accounting and control implications of the digital twin in developing new service businesses.

Design/methodology/approach

This paper investigates the potential of a digital twin in unveiling cost and control implications of new service businesses by examining the characteristics of a digital twin in the service business development context. The paper use an in-depth interventionist case study, where the designed animations illustrate the possibilities of a digital twin of a service. The animations showing the service process characteristics were first used as a communication tool and eventually those animations were actively used in customer cases for different purposes. This motivated the idea for examining the implications of such animations representing a digital twin of a service.

Findings

The paper provides empirical insights regarding the potential for developing and using a digital twin of a service for different cost management and management control purposes. The digital twin of a service may include all main details of a new service offering, simulating the functionality of a service, hence making the performance and the implications of the new service concept clear for all the stakeholders. The digital twin of the service enables defining the processes, setting targets and helps communication about the value generation. Thus, they represent a significant toolkit for the management accounting and control function of the manufacturers.

Originality/value

This paper is among the first attempts to understand the digital twin of the service. The paper is unique in providing financial and control implications of digital twins also in the context of service business development. The in-depth interventionist approach enabled an exceptional exploration process on the subject. The article paves the way toward further research on managing the digital twins of services in the future.

Details

Qualitative Research in Accounting & Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1176-6093

Keywords

Article
Publication date: 15 March 2024

Phebe Hassana Obaka, Seyi Julian Adelegan and Leonard Shaibu

The level of deterioration of educational facilities, such as leaking classroom roofs, inadequate good seats, obsolete offices, broken shutters and doors, outdated school…

Abstract

Purpose

The level of deterioration of educational facilities, such as leaking classroom roofs, inadequate good seats, obsolete offices, broken shutters and doors, outdated school buildings, power plants and office equipment like ICT media, laboratories, offices and workshops, despite the involvement of Alumni association in the maintenance of educational facilities for the effective actualization of school objectives was a worrisome nightmare in Kogi state. This, therefore, prompted the researchers to explore the Alumni’s participation in plant maintenance for effective implementation of the universal basic education (UBE) programme in public junior secondary schools in Kogi state. The purpose of this study was guided by the research question which stated that to what extent does the Alumni Association participate in plant maintenance for effective implementation of the UBE programme in public junior secondary schools in Kogi state?

Design/methodology/approach

A quantitative research approach using a descriptive survey was adopted for the study. The sample was drawn using a proportionate stratified sampling technique comprising 387 participants which consisted of 191 (49%) urban junior secondary school principals and 196 (51%) rural principals in selected UBE junior secondary schools. Alumni’s Participation in Plant Maintenance Questionnaire was used as an instrument for data collection. The data were analysed with the aid of mean and standard deviation for the research question and z-test statistics at 0.05 level of significance and the value of z-crit. of 1.96 was used to determine the rejection or otherwise of the hypotheses.

Findings

The descriptive analysis revealed that the average mean set of 2.64 pointed to the fact that the respondents averagely agreed that there was a high extent to which Alumni participate in plant maintenance in urban than rural areas for effective implementation of the UBE programme in public junior secondary schools in Kogi state. This indicates that Alumni contribute to the management of UBE schools in Kogi state, especially in the areas of funding, infrastructural facilities, discipline, politics and quality control. This finding also shows that the contributions of the alumni to educational institutions are still unclear if they have made contributions to education in some areas and none in other areas making their relevance to plant maintenance unclear.

Research limitations/implications

In terms of practical implications, the study has contributed to knowledge in that it is the first of this form of a study carried out in Kogi state, and as such the findings of the research will make contributions to the physique of information on plant maintenance for the profitable implementation of the UBE programme in Kogi state. Besides, the degree of plant preservation for the implementation of the UBE programme among applicable stakeholders in Kogi state is nevertheless at a low extent.

Originality/value

Researchers have conducted studies that show how non-state Alumni members contribute to the administration of education across different states. Some of these studies revealed that Alumni members have assisted schools in the provision of teaching and learning materials at the senior secondary or tertiary education level. There are no sufficient studies to show how these Alumni members have contributed to the implementation of the free education programme, especially in public junior secondary schools in Kogi state and this is the gap this study intends to fill.

Details

Facilities , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0263-2772

Keywords

Article
Publication date: 9 January 2024

Fadoua Benhamza Hlihel, Youness Chater and Abderrazak Boumane

Competencies are significant predictors of employee outcome. Nowadays, new technologies are changing maintenance processes and workflow. The role of employees and their…

Abstract

Purpose

Competencies are significant predictors of employee outcome. Nowadays, new technologies are changing maintenance processes and workflow. The role of employees and their competencies will therefore undergo decisive changes in the future. Therefore, a well-designed competency model for maintenance departments is important. The purpose of this paper is to develop a maintenance 4.0 competency model applicable to all industrial sectors by adapting it to the specificities of each sector.

Design/methodology/approach

The research methods consist of a comprehensive literature review on the main characteristics of the competency model and the individual competencies needed for the maintenance 4.0 employees. Interviews were conducted in order to validate and prioritize the required competencies for maintenance 4.0 employees identified in the literature.

Findings

The maintenance 4.0 competency model combines the required competencies in maintenance 4.0 and crosses the three hierarchical levels: managers, engineers and technicians. These competencies are organized in terms of four categories: technical, personal, social and methodological. In addition, a degree of importance for each competency is assigned as very important, moderately important and slightly important. As a result, this study identified the essential competencies for maintenance 4.0 stakeholders, where 12 competencies are considered very important for maintenance 4.0 technicians, 19 for engineers and 18 for managers.

Research limitations/implications

This work has some limitations. First, although the articles related to competencies and their classification were selected very carefully, it is difficult to eliminate the probability of overlooking publications. Second, the limitation of the study is based on the difficulty of implementing the model in a case study, given that a minority of industrial companies have implemented maintenance 4.0 technologies in Morocco.

Practical implications

This work has practical implications for both individuals and institutions (companies and academies) to cope with new competency requirements in maintenance 4.0. Organizations can use the model in the recruitment process and for the identification of training needs. The results of the research will also contribute to identifying the scope of competencies of the maintenance 4.0 actors (engineer, manager and technician), which, in practice, contributes to the creation of requirements for the candidates applying for a job in the maintenance department. Additionally, educational institutions should make the necessary changes to their curricula to suitably prepare students for the required maintenance 4.0 competencies.

Social implications

The social implications of the article result from the contribution to the development of maintenance competencies. Individuals can use this model for their own personal development. Furthermore, companies can use this model to define job profiles for vacancies in M4.0. Therefore, using the model for training program implementation has a positive effect on employee job satisfaction and employees ’morale.

Originality/value

This research develops a novel maintenance 4.0 competency model by categorizing the maintenance workforce into three hierarchical levels: managers, engineers and technicians. In addition, the competency requirement is prioritized to three degrees: very important, moderately important and slightly important. According to the previous studies conducted on maintenance 4.0 and employees' competencies, this study revealed that no research has developed a competency model for maintenance 4.0. Hence, this model is unique, generic and integrative since it presents the most relevant competencies for the three hierarchical levels. Moreover, this work combines the results of the literature review and the experts' returns. This model can be useful in the recruitment of new maintenance employees, the evaluation of their performance and the identification of training needs to cope with new changes in maintenance competencies.

Details

International Journal of Quality & Reliability Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0265-671X

Keywords

Access

Year

Last 6 months (83)

Content type

Earlycite article (83)
1 – 10 of 83