Article
Publication date: 28 June 2021

Dan Wang, Xueqing Wang, Lu Wang, Henry J. Liu and Xiajie Jia

The purpose of this study is for examining the evolution of stakeholder influence and the trans-period effect (TPE) of process performance of public–private partnerships (PPPs)…

Abstract

Purpose

The purpose of this study is for examining the evolution of stakeholder influence and the trans-period effect (TPE) of process performance of public–private partnerships (PPPs). TPE refers to the ripple effect of project performance across different phases of a PPP.

Design/methodology/approach

Social network analysis is used to analyze each stakeholder’s influence on PPP performance. For examining the TPE, partial least squares structural equation modelling is conducted.

Findings

The performance in the five phases (e.g. initiation and planning, procurement, construction, operation and transition) of PPPs exhibits significant TPE. The stakeholder network varies in different phases. The most influential stakeholder is a public authority, followed by a public initiator and a private consortium.

Research limitations/implications

The project type of PPPs is not considered in the stakeholder network analysis. Future work should focus on developing a multidimensional stakeholder network by considering the typology of the project. Moreover, the TPE cannot reflect the relationships between the KPIs in the different phases, and thus, further study is required.

Practical implications

This research provides a useful tool for measuring the life cycle outputs and outcomes of PPPs through enhanced process-oriented performance measurement. The developed PMS enable practitioners to have a better understanding of the process performance of the projects and then ensure informed decision-making about actions to be required and taken to improve future performance.

Originality/value

This study contributes to knowledge of performance management by simultaneously addressing the process and stakeholder management theories within the context of PPPs. The proposed PMS provides an insight into managing stakeholders’ influences to enhance the life cycle performance of PPPs.

Details

International Journal of Productivity and Performance Management, vol. 72 no. 1
Type: Research Article
ISSN: 1741-0401

Keywords

Article
Publication date: 9 September 2022

Siavash Ghorbany, Saied Yousefi and Esmatullah Noorzai

Being an efficient mechanism for the value of money, public–private partnership (PPP) is one of the most prominent approaches for infrastructure construction. Hence, many…

413

Abstract

Purpose

Being an efficient mechanism for the value of money, public–private partnership (PPP) is one of the most prominent approaches for infrastructure construction. Hence, many controversies about the performance effectiveness of these delivery systems have been debated. This research aims to develop a novel performance management perspective by revealing the causal effect of key performance indicators (KPIs) on PPP infrastructures.

Design/methodology/approach

The literature review was used in this study to extract the PPPs KPIs. Experts’ judgment and interviews, as well as questionnaires, were designed to obtain data. Copula Bayesian network (CBN) has been selected to achieve the research purpose. CBN is one of the most potent tools in statistics for analyzing the causal relationship of different elements and considering their quantitive impact on each other. By utilizing this technique and using Python as one of the best programming languages, this research used machine learning methods, SHAP and XGBoost, to optimize the network.

Findings

The sensitivity analysis of the KPIs verified the causation importance in PPPs performance management. This study determined the causal structure of KPIs in PPP projects, assessed each indicator’s priority to performance, and found 7 of them as a critical cluster to optimize the network. These KPIs include innovation for financing, feasibility study, macro-environment impact, appropriate financing option, risk identification, allocation, sharing, and transfer, finance infrastructure, and compliance with the legal and regulatory framework.

Practical implications

Identifying the most scenic indicators helps the private sector to allocate the limited resources more rationally and concentrate on the most influential parts of the project. It also provides the KPIs’ critical cluster that should be controlled and monitored closely by PPP project managers. Additionally, the public sector can evaluate the performance of the private sector more accurately. Finally, this research provides a comprehensive causal insight into the PPPs’ performance management that can be used to develop management systems in future research.

Originality/value

For the first time, this research proposes a model to determine the causal structure of KPIs in PPPs and indicate the importance of this insight. The developed innovative model identifies the KPIs’ behavior and takes a non-linear approach based on CBN and machine learning methods while providing valuable information for construction and performance managers to allocate resources more efficiently.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 1
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 25 August 2023

Yunfeng Liu, Xueqing Wang, Jingxiao Zhang and Sijia Guo

Early termination of public–private partnerships (PPPs) in China is caused by various risk factors, resulting in significant losses. This study aimed to clarify the key factors…

Abstract

Purpose

Early termination of public–private partnerships (PPPs) in China is caused by various risk factors, resulting in significant losses. This study aimed to clarify the key factors and identify the causal relationships among these factors.

Design/methodology/approach

Social network analysis (SNA) was used to analyze 37 risk factors that were summarized from 97 early terminated PPP cases and to identify the relationships among these key risk factors. Interpretive structural modeling (ISM) was conducted to explore the causal relationships. Data were collected from case documents, questionnaires and interviews.

Findings

A total of 17 key risk factors were identified and distributed in a hierarchical structure with six tiers. Among these key risk factors, the root causes affecting the early termination of PPP projects were government oversight in decision-making, local government transition, policy and law changes and force majeure. The direct cause was insufficient returns. Furthermore, local government and private sector defaults were essential mediating factors. Local government transition and the low willingness of the private sector were highlighted as potential key risks.

Research limitations/implications

The cases and experts were all from China, and outcomes in other countries or cultures may differ from those of this study. Therefore, further studies are required.

Practical implications

This research provides knowledge regarding the key risk factors leading to the early termination of PPP projects and guidance on avoiding these factors and blocking the factors' transmission in the project lifecycle.

Originality/value

This study contributes to the knowledge of risk management by emphasizing the importance of local government transition, the low willingness of the private sector and project cooperation and operation, whose significance is ignored in the existing literature. The proposed ISM clarifies the role of risk factors in causing early termination and explains their transmission patterns.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 29 November 2021

Louisi Francis Moura, Edson Pinheiro de Lima, Fernando Deschamps, Dror Etzion and Sergio E. Gouvea da Costa

This conceptual paper presents a proposal for improving a performance measurement (PM) system implementation process based on enterprise engineering (EE) guidelines, which gives…

Abstract

Purpose

This conceptual paper presents a proposal for improving a performance measurement (PM) system implementation process based on enterprise engineering (EE) guidelines, which gives the process a sense of completeness.

Design/methodology/approach

This paper analyzes a well-known process for PM systems implementation organized in two phases: identifying, designing and implementing the top-level performance measures; and cascading the top-level measures and identify appropriate lower-level performance measures. The proposed improvements to the studied process derive from the EE guidelines, which establish a basis for the structure of an organizational management system, the formalization and synchronization of processes, performance expectations, exception handling and change management.

Findings

The study reveals that not all EE guidelines are covered by the analyzed process, with four of them having no evidence of being adopted: involvement of people in process design and implementation; ensuring interoperability between different systems in the information structure; addressing of all possible exceptions; coherence and consistency of semantics across all processes.

Originality/value

By the lens of EE guidelines, this paper advances a how-to-guide. This paper can support managers and researchers on PM system design and implementation, given the importance and relevance of EE recommendations having a consistent and well-structured procedure.

Details

International Journal of Productivity and Performance Management, vol. 72 no. 5
Type: Research Article
ISSN: 1741-0401

Keywords

Open Access
Article
Publication date: 13 February 2020

John A. Kearby, Ryan D. Winz, Thom J. Hodgson, Michael G. Kay, Russell E. King and Brandon M. McConnell

The purpose of this paper is to investigate US noncombatant evacuation operations (NEO) in South Korea and devise planning and management procedures that improve the efficiency of…

3359

Abstract

Purpose

The purpose of this paper is to investigate US noncombatant evacuation operations (NEO) in South Korea and devise planning and management procedures that improve the efficiency of those missions.

Design/methodology/approach

It formulates a time-staged network model of the South Korean noncombatant evacuation system as a mixed integer linear program to determine an optimal flow configuration that minimizes the time required to complete an evacuation. This solution considers the capacity and resource constraints of multiple transportation modes and effectively allocates the limited assets across a time-staged network to create a feasible evacuation plan. That solution is post-processed and a vehicle routing procedure then produces a high resolution schedule for each individual asset throughout the entire duration of the NEO.

Findings

This work makes a clear improvement in the decision-making and resource allocation methodology currently used in a NEO on the Korea peninsula. It immediately provides previously unidentifiable information regarding the scope and requirements of a particular evacuation scenario and then produces an executable schedule for assets to facilitate mission accomplishment.

Originality/value

The significance of this work is not relegated only to evacuation operations on the Korean peninsula; there are numerous other NEO and natural disaster related scenarios that can benefit from this approach.

Details

Journal of Defense Analytics and Logistics, vol. 4 no. 1
Type: Research Article
ISSN: 2399-6439