Article
Publication date: 27 October 2023

Muhammad Saiful Islam, Madhav Nepal and Martin Skitmore

Power plant projects are very complex and encounter serious cost overruns worldwide. Their cost overrun risks are not independent but interrelated in many cases, having structural…

Abstract

Purpose

Power plant projects are very complex and encounter serious cost overruns worldwide. Their cost overrun risks are not independent but interrelated in many cases, having structural relationships among each other. The purpose of this study is, therefore, to establish the complex structural relationships of risks involved.

Design/methodology/approach

In total, 76 published articles from the previous literature are reviewed using the content analysis method. Three risk networks in different phases of power plant projects are depicted based on literature review and case studies. The possible methods of solving these risk networks are also discussed.

Findings

The study finds critical cost overrun risks and develops risk networks for the procurement, civil and mechanical works of power plant projects. It identifies potential models to assess cost overrun risks based on the developed risk networks. The literature review also revealed some research gaps in the cost overrun risk management of power plants and similar infrastructure projects.

Practical implications

This study will assist project risk managers to understand the potential risks and their relationships to prevent and mitigate cost overruns for future power plant projects. It will also facilitate decision-makers developing a risk management framework and controlling projects’ cost overruns.

Originality/value

The study presents conceptual risk networks in different phases of power plant projects for comprehending the root causes of cost overruns. A comparative discussion of the relevant models available in the literature is presented, where their potential applications, limitations and further improvement areas are discussed to solve the developed risk networks for modeling cost overrun risks.

Details

Construction Innovation , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 15 March 2024

Phebe Hassana Obaka, Seyi Julian Adelegan and Leonard Shaibu

The level of deterioration of educational facilities, such as leaking classroom roofs, inadequate good seats, obsolete offices, broken shutters and doors, outdated school…

Abstract

Purpose

The level of deterioration of educational facilities, such as leaking classroom roofs, inadequate good seats, obsolete offices, broken shutters and doors, outdated school buildings, power plants and office equipment like ICT media, laboratories, offices and workshops, despite the involvement of Alumni association in the maintenance of educational facilities for the effective actualization of school objectives was a worrisome nightmare in Kogi state. This, therefore, prompted the researchers to explore the Alumni’s participation in plant maintenance for effective implementation of the universal basic education (UBE) programme in public junior secondary schools in Kogi state. The purpose of this study was guided by the research question which stated that to what extent does the Alumni Association participate in plant maintenance for effective implementation of the UBE programme in public junior secondary schools in Kogi state?

Design/methodology/approach

A quantitative research approach using a descriptive survey was adopted for the study. The sample was drawn using a proportionate stratified sampling technique comprising 387 participants which consisted of 191 (49%) urban junior secondary school principals and 196 (51%) rural principals in selected UBE junior secondary schools. Alumni’s Participation in Plant Maintenance Questionnaire was used as an instrument for data collection. The data were analysed with the aid of mean and standard deviation for the research question and z-test statistics at 0.05 level of significance and the value of z-crit. of 1.96 was used to determine the rejection or otherwise of the hypotheses.

Findings

The descriptive analysis revealed that the average mean set of 2.64 pointed to the fact that the respondents averagely agreed that there was a high extent to which Alumni participate in plant maintenance in urban than rural areas for effective implementation of the UBE programme in public junior secondary schools in Kogi state. This indicates that Alumni contribute to the management of UBE schools in Kogi state, especially in the areas of funding, infrastructural facilities, discipline, politics and quality control. This finding also shows that the contributions of the alumni to educational institutions are still unclear if they have made contributions to education in some areas and none in other areas making their relevance to plant maintenance unclear.

Research limitations/implications

In terms of practical implications, the study has contributed to knowledge in that it is the first of this form of a study carried out in Kogi state, and as such the findings of the research will make contributions to the physique of information on plant maintenance for the profitable implementation of the UBE programme in Kogi state. Besides, the degree of plant preservation for the implementation of the UBE programme among applicable stakeholders in Kogi state is nevertheless at a low extent.

Originality/value

Researchers have conducted studies that show how non-state Alumni members contribute to the administration of education across different states. Some of these studies revealed that Alumni members have assisted schools in the provision of teaching and learning materials at the senior secondary or tertiary education level. There are no sufficient studies to show how these Alumni members have contributed to the implementation of the free education programme, especially in public junior secondary schools in Kogi state and this is the gap this study intends to fill.

Details

Facilities , vol. 42 no. 7/8
Type: Research Article
ISSN: 0263-2772

Keywords

Open Access
Article
Publication date: 25 December 2023

Anna Trubetskaya, Alan Ryan, Daryl John Powell and Connor Moore

Output from the Irish Dairy Industry has grown rapidly since the abolition of quotas in 2015, with processors investing heavily in capacity expansion to deal with the extra milk…

1280

Abstract

Purpose

Output from the Irish Dairy Industry has grown rapidly since the abolition of quotas in 2015, with processors investing heavily in capacity expansion to deal with the extra milk volumes. Further capacity gains may be achieved by extending the processing season into the winter, a key enabler for which being the reduction of duration of the winter maintenance overhaul period. This paper aims to investigate if Lean Six Sigma tools and techniques can be used to enhance operational maintenance performance, thereby releasing additional processing capacity.

Design/methodology/approach

Combining the Six-Sigma Define, Measure, Analyse, Improve, Control (DMAIC) methodology and the structured approach of Turnaround Maintenance (TAM) widely used in process industries creates a novel hybrid model that promises substantial improvement in maintenance overhaul execution. This paper presents a case study applying the DMAIC/TAM model to Ireland’s largest dairy processing site to optimise the annual maintenance shutdown. The objective was to deliver a 30% reduction in the duration of the overhaul, enabling an extension of the processing season.

Findings

Application of the DMAIC/TAM hybrid resulted in process enhancements, employee engagement and a clear roadmap for the operations team. Project goals were delivered, and original objectives exceeded, resulting in €8.9m additional value to the business and a reduction of 36% in the duration of the overhaul.

Practical implications

The results demonstrate that the model provides a structure that promotes systematic working and a continuous improvement focus that can have substantial benefits for wider industry. Opportunities for further model refinement were identified and will enhance performance in subsequent overhauls.

Originality/value

To the best of the authors’ knowledge, this is the first time that the structure and tools of DMAIC and TAM have been combined into a hybrid methodology and applied in an Irish industrial setting.

Details

International Journal of Lean Six Sigma, vol. 15 no. 8
Type: Research Article
ISSN: 2040-4166

Keywords

Case study
Publication date: 1 November 2023

Goutam Dutta

Mr. Sajjan Jindal, MD of JVSL (nos JSW) wanted to bring the latest technology of iron making into India. His project went to several cost overrun and time overrun due to several…

Abstract

Mr. Sajjan Jindal, MD of JVSL (nos JSW) wanted to bring the latest technology of iron making into India. His project went to several cost overrun and time overrun due to several foreseen and unforessen circumstances. This case discusses the issues new technology introduction in iron making area, problem faced by inexperienced contractor. It shows the need for proper risk management is required. It also shows the criticality of the project does not mean time cost trade off, but many other factors like reliability of the equipment, process and reliability of the equipment and plants.

Details

Indian Institute of Management Ahmedabad, vol. no.
Type: Case Study
ISSN: 2633-3260
Published by: Indian Institute of Management Ahmedabad

Keywords

Book part
Publication date: 26 September 2024

Jakob B Sørensen

Clause 1 [General Provisions] contains the provisions that in many contracts are bundled together under the ‘miscellaneous’ or ‘other provisions’ heading and includes a list of…

Abstract

Clause 1 [General Provisions] contains the provisions that in many contracts are bundled together under the ‘miscellaneous’ or ‘other provisions’ heading and includes a list of definitions, some interpretation principles, rules on communication between the Parties, documents forming the Contract, assignment, confidentiality etc. But Clause 1 also contains other provisions, like the Employer's right to use documentation and other deliverables provided by the Contractor (in other contracts usually referred to as a license to use), and a substantive Sub-Clause on limitation of liability.

Details

FIDIC Yellow Book: A Companion to the 2017 Plant and Design-Build Contract, Revised Edition
Type: Book
ISBN: 978-1-83608-164-7

Keywords

Open Access
Article
Publication date: 20 June 2022

Norbey Amaya, César Augusto Bernal-Torres, Yoni W. Nicolás-Rojas and Tamara T. Pando-Ezcurra

This study aims to analyse the way the internal resources and their attributes contribute to the competitive advantages in an intensive organisation in knowledge of the…

6935

Abstract

Purpose

This study aims to analyse the way the internal resources and their attributes contribute to the competitive advantages in an intensive organisation in knowledge of the pharmaceutical industry in an emerging market.

Design/methodology/approach

This is a qualitative case study focused where the NVivo software was used for information analysis and thematic analysis.

Findings

The outcomes showed that from the VRIO framework (value, rarity, imitability and organisation), the plant and equipment and the technical knowledge of its workers are the resources that, due to their attributes, especially the rare, those that grant an advantage competitive position compared to other companies in its sector. Those findings highlight that the resource-based view (RBV) is a good approximation to explain the construction of competitive advantage (CA) and, in addition, the relevance of rare attribute in pharmaceutical companies was confirmed.

Practical implications

The study points out empirical evidence on the relevancy of RBV, from the VRIO framework and the competitive profile matrix (CPM) for the analysis of the management of organisations from the emerging market (economy) perspective. The study also provides competitive advantage analysis tools with which managers can identify strategic resources for their companies.

Originality/value

The VRIO framework and CPM were integrated in the study to analyse the role of internal resources and their attributes in achieving CAs. This integration is the first time that it has been carried out in companies in the context of an emerging market.

Details

VINE Journal of Information and Knowledge Management Systems, vol. 54 no. 5
Type: Research Article
ISSN: 2059-5891

Keywords

Article
Publication date: 29 November 2023

Premaratne Samaranayake, Krishnamurthy Ramanathan and Weerabahu Mudiyanselage Samanthi Kumari Weerabahu

The main purpose of this research is to (1) prioritise key determinants of Industry 4.0 (I4.0) readiness assessment and (2) evaluate causal relationships among those determinants…

Abstract

Purpose

The main purpose of this research is to (1) prioritise key determinants of Industry 4.0 (I4.0) readiness assessment and (2) evaluate causal relationships among those determinants and associated sub-criteria based on inputs from industry experts.

Design/methodology/approach

The methodology involved two phases: (1) an MCDM approach for determining causal relationships among determinants and (2) empirical validation of findings from the first phase using industry experts' inputs.

Findings

It was found that while the choice of I4.0 technologies is important, organisational factors are also critical, as evidenced by the ranking of the “Strategy and Organisation” determinant as the highest rank prominent determinant. Also, the ranking of the sub-criteria within each determinant shows the importance of several organisational influencing and resulting sub-criteria.

Research limitations/implications

This research extends the existing literature on I4.0 by demonstrating the prioritisation of determinants and delineating causal relationships among them and associated sub-criteria as a basis for developing I4.0 adoption guidelines. This research is limited to the specific scope of determinants selected/considered and experts' inputs from the Sri Lankan manufacturing sector. Future studies could consider extending this research into a broader global manufacturing context.

Practical implications

Prioritisation and causal relationships of I4.0 readiness assessment determinants, supported with inputs from functional managers and industry experts, could be used to guide practitioners in developing guidelines for I4.0 adoption in a phased manner.

Originality/value

This research provides a re-evaluation and validation of a selected I4.0 readiness assessment framework from the perspectives of interdependencies and casual relationships among its determinants and sub-criteria, based on inputs from industry experts as a basis for developing guidelines for I4.0 adoption.

Details

Journal of Manufacturing Technology Management, vol. 35 no. 1
Type: Research Article
ISSN: 1741-038X

Keywords

Article
Publication date: 25 July 2024

Steven Call

The aim of this study is to understand health-care facilities’ practice of deferring maintenance and to identify the relationship between deferred maintenance and hospital…

Abstract

Purpose

The aim of this study is to understand health-care facilities’ practice of deferring maintenance and to identify the relationship between deferred maintenance and hospital profitability.

Design/methodology/approach

Financial statements from hospitals in Washington State were analyzed. Differences in building and equipment values were compared to the capital renewal investment benchmark. Then, linear regression analysis was conducted to identify correlations between deferring or sustaining maintenance and a hospital’s profitability.

Findings

The majority of hospitals in Washington State practice deferred maintenance, investing less in annual facility capital renewal than benchmark amounts. Hospitals in deferred and sustained maintenance states do not significantly differ in terms of facility size and plant operating expenses but there is a statistically significant difference in profit margins. Furthermore, a linear relationship exists between the level of investment in facility renewal and overall hospital expenses, revenue and profit.

Practical implications

The findings of this research can be used to support fiscal policies related to maintaining aging health-care facility infrastructure. The findings can also be used to overcome barriers to securing capital budgets that are sufficient to optimize the safety and performance of the built environment.

Originality/value

Hospitals in a state of deferred maintenance return higher profits than do hospitals in a state of sustained maintenance. Nevertheless, hospital spending on deferred maintenance backlog reduction generates a positive return on investment. While hospitals may achieve higher returns, in the short term, by spending less on facility capital renewal and focusing instead on higher-revenue-generating opportunities, additional research in necessary to understand the long-term costs of deferring facility infrastructure repairs and replacement.

Details

Facilities , vol. 42 no. 11/12
Type: Research Article
ISSN: 0263-2772

Keywords

Case study
Publication date: 7 December 2023

Chitra Singla and Bulbul Singh

Madan Mohanka set up Tega Industries Ltd in 1976 to manufacture abrasion-resistant rubber mill lining products used in the mining and mineral processing industries. In 2006, as…

Abstract

Madan Mohanka set up Tega Industries Ltd in 1976 to manufacture abrasion-resistant rubber mill lining products used in the mining and mineral processing industries. In 2006, as part of its inorganic expansion strategy, Tega bought a mill-liner company in South Africa. Buoyed by this growth, two acquisitions were made in Australia and Chile in the year 2011. However, post-acquisition, several managerial, legal and commercial problems crept up in its manufacturing facilities in Chile, leading to financial downturn in Tega's fortunes in 2016 and compelling it to either plan a revival or divest its interest in its Chilean Plant.

Details

Indian Institute of Management Ahmedabad, vol. no.
Type: Case Study
ISSN: 2633-3260
Published by: Indian Institute of Management Ahmedabad

Keywords

Article
Publication date: 14 December 2022

Bryan Pieterse, Kofi Agyekum, Patrick Manu, Saeed Reza Mohandes, Clara Cheung and Akilu Yunusa-Kaltungo

Major maintenance projects are often regarded as maintenance activities regardless of the projects' complexity and scale. Consequently, very scarce research attention has hitherto…

Abstract

Purpose

Major maintenance projects are often regarded as maintenance activities regardless of the projects' complexity and scale. Consequently, very scarce research attention has hitherto been paid to the critical skills required when undertaking these projects. More specifically, the body of relevant knowledge is deprived of a study focusing on maintenance projects within the energy sector. In view of this shortcoming, this research aims to examine the critical project management (PM) skills required to deliver major maintenance projects within the energy sector.

Design/methodology/approach

Based on a quantitative research strategy, this study addressed the knowledge gap through a cross-sectional survey of professionals involved in the delivery of major maintenance projects in the United Kingdom's (UK) energy sector. Data obtained were analyzed via descriptive (e.g. frequencies, mean and standard deviation [SD]) and inferential statistical analyses (One sample t-test and exploratory factor analysis (EFA)).

Findings

Out of the 45 PM skills identified in the literature and examined by the respondents, the results obtained from the One sample t-test (based on p (1-tailed) = 0.05) showed that 37 were considered to be at least “important,” accounting for 80.4% of all the skills identified. EFA revealed a clustering of the PM skills items into seven components: “skills related to work scheduling and coordination”; “communication, risk, safety and stakeholder management skills”; “quality assurance skills”; “people management skills”; “skills related to forecasting scope and duration of outage”; “implementation of processes and time management skills” and “technical/engineering skills and experience pertaining to the outage and local site knowledge.”

Originality/value

This study has identified and contributed to the limited state-of-the-art skills project managers must possess to manage major maintenance projects in the energy sector successfully. The findings would be useful to organizations within the energy sector in ensuring that the organizations have suitable personnel in place to deliver major maintenance projects on the organizations' assets.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 4
Type: Research Article
ISSN: 0969-9988

Keywords

1 – 10 of over 2000