Search results

1 – 10 of 754
Case study
Publication date: 19 December 2022

Juan Ernesto Perez Perez

At the end of the case students will be able to:1. Relate risk as one of the 12 principles in project management contemplated in the international standards of the PMBOK Seventh…

Abstract

Learning outcomes

At the end of the case students will be able to:

1. Relate risk as one of the 12 principles in project management contemplated in the international standards of the PMBOK Seventh Edition guide.

2. Determine high-level risks by articulating the WBS and RBS of a construction project.

3. Perform a qualitative and quantitative analysis of the probability and impact of risks through the heat map tool and the Expected Monetary Value (EMV) technique.

4. Propose the different response strategies contemplated in the risk management through the formulation of a response and contingency plan.

Case overview/synopsis

MORESA S.A.S was a family company founded in 1994, whose value proposition focused on construction and permanent advice for the execution of innovative and contemporary projects with more than 27 years of experience in the city of San José de Cucuta, department of Norte de Santander, Colombia. The objective of the case is to Relate risk as one of the 12 principles in project management contemplated in the international standards of the PMBOK Seventh Edition guide; Determine high-level risks by articulating the WBS and RBS of a construction project; Perform a qualitative and quantitative analysis of the probability and impact of risks through the heat map tool and the Expected Monetary Value (EMV) technique and propose the different response strategies contemplated in the risk management through the formulation of a response and contingency plan. The teaching case is designed for academic programs in areas of knowledge of civil engineering, architecture and at postgraduate level such as: Master’s in civil engineering, Master’s in risk management, Master in project management or MBA. For this case, an expert judgment was developed with professionals belonging to different areas of knowledge. Likewise, secondary information was collected from the organization's strategic documents and the analogous estimation through the historical records of the project portfolio developed by the construction company. Finally, the case, classified in the Built Environment, a challenge that project managers must face in VUCA environment through risk management.

Complexity academic level

The teaching case is designed for academic programs in areas of knowledge of civil engineering, architecture and at postgraduate level such as: Master’s in civil engineering, Master’s in risk management, Master’s in project management or MBA. In the modules of risk management, project management, international standards, the case guides the applicability of methods and artifacts used in risk management considering the process identification, quantitative, qualitative analysis, and development of response strategies and contingency plans.

Supplementary materials

Teaching notes are available for educators only.

Subject code

CSS 2: Built Environment.

Details

Emerald Emerging Markets Case Studies, vol. 12 no. 4
Type: Case Study
ISSN:

Keywords

Abstract

Subject area

Human resource management.

Study level/applicability

The case can be used on courses related to human resources management (HRM), which are offered in management programmes like MBA/PGDBM. The case could also be used in management development programmes, seminars and workshops that have HRM as a component of the programme. The case can be used effectively for classroom discussions as well as in distance learning programmes.

Case overview

The case looks into the HRM practices at a leading Indian construction company – ABC Constructions. The case tries to explain the management perspectives behind the people practice initiatives undertaken by the company in order to recruit/retain and nurture talent. The case also explains the basic principles underlying its human resource policies. It tries to explain the initiatives taken by ABC Constructions to meet the challenges posed by the changing business environment, as the company moves beyond the borders of the country of its initial operations. The case provides an overview of unique challenges faced by a company in the Indian construction industry, where a significant number of people executing its projects are not its permanent employees.

Expected learning outcomes

The students would get a fairly good understanding of existing good practices in the field of human resource management, especially in the context of a multifaceted and labour intensive construction industry in the Indian corporate scenario. Anecdotes of actual experiences with respect to people management would facilitate greater understanding of the complexities involved at the grass root level of functioning and implementation. Theoretical inputs relating to training could be better understood through the customised programmes provided by the company for its diverse workforce. The HR challenges faced by the top management as a company grows and expands to new markets can better be understood.

Supplementary materials

Teaching notes are available for educators only. Please contact your library to gain login details or email support@emeraldinsight.com to request teaching notes.

Details

Emerald Emerging Markets Case Studies, vol. 3 no. 6
Type: Case Study
ISSN: 2045-0621

Keywords

Case study
Publication date: 4 January 2024

Marina Apaydin, Martin Johannes Løkse Sand, Rebecca A Hoogendoorn and Maha Eshak

The expected learning outcomes are to understand key frameworks and tools for global leaders through the application of widely used theoretical frameworks on a written business…

Abstract

Learning outcomes

The expected learning outcomes are to understand key frameworks and tools for global leaders through the application of widely used theoretical frameworks on a written business case, understand the role of the leader in a team, apply theories of change to situations to anticipate courses of events and evaluate and apply relevant theory to assess a leader’s character and personality.

Case overview/synopsis

Hassan Allam Holding (HAH) was a family-owned Egyptian engineering, construction and infrastructure company managed by co-Chief Executive Officers and brothers Amr and Hassan Allam. HAH experienced significant growth and success, but eventually, it reached a point where its family governance structure could no longer sustain further growth. Amr and Hassan realized this and started planning to transition toward a corporate governance structure. In 2016, they managed to get the International Finance Corporation on board as an equity partner, and this helped propel the governance transition, but they still needed to find a way to convince the family to step back. This case study can help students understand the issues that may occur during a change within an established organization of any size. The case study considers the implications the change may have on the leader, his personality and his character and how it shapes the leader in question as an outcome. This case study has been designed to be used in one or two sessions and can be offered in management or leadership courses at an undergraduate or graduate level.

Complexity academic level

This case study is intended for graduate and undergraduate students studying a leadership or management course. It can help students comprehend the challenges of a family-owned business and how change is associated with such businesses. The case also considers how leaders are shaped by effectively managing conflict. This case can be considered as Level 1 on a 1–3 scale, as the full description of the situation is given in the case and the task of the students is to analyze the leader and his decisions using various academic concepts and theories (Erskin et al., 2003).

Supplementary materials

Teaching notes are available for educators only.

Subject code

CSS 3: Entrepreneurship

Details

Emerald Emerging Markets Case Studies, vol. 14 no. 1
Type: Case Study
ISSN: 2045-0621

Keywords

Abstract

Subject area

Innovation, privatisation and property development.

Study level/applicability

Undergraduate and MA level property development courses; modules covering privatisation within undergraduate, MBA and MA level management programmes.

Case overview

This paper presents the genesis and motivating factors that stimulate a managing director of a housing development (D&B Private Limited Company) to introduce innovation as a strategic solution to the challenges which hinder his firm's growth. The recently launched Ten Malaysian Plan and the Sustainable Programme for Corporate Malaysia are identified as the two stimulating events that triggered the initiation and subsequent implementation of innovation into Design and Build Sdn Bhd. Innovation has been recognized as an endeavor that impacts positively and significantly the performance of the firm that innovates. There was a major focus on factors that enhance innovation of a firm: structure, culture, resources and how to address or react to external factors such as government regulation on innovation, environmental uncertainty and market competition. The quest to be an innovative firm has led to major changes in the structure, culture and review of the firm intangible resources. Coupled with some corporate responsibilities, Design and Build Sdn Bhd has been recognized for its unique performance resulting from the competitive advantage derived from this very idea of innovations.

Expected learning outcomes

Students are expected to be able: to present a basic understanding of the motivations and driving force behind the housing developer's keen interest to innovate, to present the multiple benefits of adopting innovation in the housing industry, to highlight the internal and external factors which positively influence innovation among housing developers?, to present how housing developers are able to manage challenges facing their companies through innovation.

Supplementary materials

Teaching notes.

Details

Emerald Emerging Markets Case Studies, vol. 1 no. 1
Type: Case Study
ISSN: 2045-0621

Keywords

Abstract

Subject area

Operations and human resourcing.

Study level/applicability

This case study is intended for use in graduate, executive level management and doctoral programs. The case study illustrates a combined IT and HR driven participative management control system in a flexible organization structure. It is intended for a class discussion rather than to illustrate either effective or ineffective handling of an administrative situation.

Case overview

The case describes the situation of managing unskilled workforces (≥14,000 workers) during the construction phase of the 4 × 250MW power plants both for purposes of turnout as well as due compensation, in the event of an accident. The approved labour forces appointed for 45 × 8 h. Man-days after a rigorous fitness test and approvals of the safety officer are allocated housing and other necessary amenities and a commensurate compensation system.

Expected learning outcomes

These include: illustrating typical organizational responsibility structure at a construction site of a large power plant; illustrating the planning and administrative control mechanism in implementing strategy at a construction site of a large power plant; offering students the opportunity to understand and view a typical operational (project) structure; allowing students to speculate adaptations in the wake of an ever-changing business and company environment; and providing an opportunity to introduce a power scenario in India, Indian labour laws and radio frequency identification technology and to relate this to the case in context.

Supplementary materials

Teaching notes are available; please consult your librarian for access.

Details

Emerald Emerging Markets Case Studies, vol. 2 no. 8
Type: Case Study
ISSN: 2045-0621

Keywords

Case study
Publication date: 26 November 2014

Warren Maroun and Robert Garnett

Financial reporting.

Abstract

Subject area

Financial reporting.

Study level/applicability

Postgraduate (honours and masters in financial reporting).

Case overview

Transnet is the utility company responsible for, inter alia, the operation, construction and management of South Africa's fuel pipeline infrastructure. The company is wholly owned by the South African Government and prepares its financial statements in compliance with International Financial Reporting Standards (IFRS). One of Transnet's capital projects involves the construction of an upgraded multi-fuel pipeline. The expected costs of construction ballooned from ZAR12.6 billion (approximately USD120 million) to ZAR24 billion (approximately USD240 million) over a five-year period. This has raised questions about the prudential management of the company's capital projects and the basis on which the government subsidises Transnet's capital costs. The significant increase in project costs also begs the question: how should the cost of the self-constructed pipeline be accounted for in Transnet's annual financial statements?

Expected learning outcomes

Describe and explain the qualitative characteristics of useful information in terms of the Conceptual Framework (2010) and summarise the framework's key principles. Evaluate these principles, drawing connections between them and the relevant academic theory (as per the prescribed readings), with specific reference to the accounting for self-constructed plant and equipment.

Supplementary materials

Teaching Notes are available for educators only. Please contact your library to gain login details or email support@emeraldinsight.com to request teaching notes.

Subject code

CSS 1: Accounting and Finance

Details

Emerald Emerging Markets Case Studies, vol. 4 no. 7
Type: Case Study
ISSN: 2045-0621

Keywords

Abstract

Subject area

Strategic Management.

Study level/applicability

The case is designed for a) MBA students b) Short-duration executive MBA courses.

Case overview

The case refers to India’s leading steel company Tata Steel. Tata Tiscon, the steel rebar brand, is the organization’s leading retail brand. The case chronicles the period between the birth of the retail brand in the year 2000, its dramatic rise and dominance, to the end of 2013 when some of its initiatives had failed. Tata Tiscon was established as a pan Indian brand on the dint of a distribution network comprising 33 distributors and over 2000 retailers, many of them exclusive to the brand. The brand spawned a series of innovation in the category like “selling by piece”, fixed price concept and “free” home delivery. Together with its channel partners, the company achieved dramatic success which was reflected in its leading market share coupled with significant price premium in a category where price had traditionally being the only selling pitch. After 2010, the company saw an emerging challenge in the form of a new business model, where some companies were gearing to provide the complete portfolio of construction material including cement, steel, etc., and a turnkey construction solution for house builders. Tata Tiscon responded by attempting to enter the service space by launching a building design solution and later a construction supervision solution. Both of these initiatives failed. The protagonist of the case is Mr Keshav Viswanath (Chief of Marketing for retail business at Tata Steel), who is concerned with the failures of these key initiatives and is wondering how to ensure the “leader” status of Tata Tiscon in coming years.

Expected earning outcomes

The students are expected to understand how a core strategy like differentiation is implemented successfully in “practice”; understand the exploitation–exploration dichotomy in an organization; appreciate difference between radical innovation (based on new organizational routines, new business partners and new relationships) and incremental innovation based on fine tuning of existing organizational routines and relationships.

Supplementary materials

Rebar production: www.youtube.com/watch?v=J6n9sci8j-8; Tata TISCON AV: www.youtube.com/watch?v=89kOUsbnaYQ; TQM – The Toyota Way: www.youstube.com/watch?v=qf3gdrIMxRw; Disruptive vs. Incremental Innovation: www.youtube.com/watch?v=kOOL_GiaLTo; Approach to innovation is dead wrong: www.youtube.com/watch?v=pii8tTx1UYM

Subject code

CSS 11: Strategy.

Details

Emerald Emerging Markets Case Studies, vol. 6 no. 1
Type: Case Study
ISSN: 2045-0621

Keywords

Case study
Publication date: 1 January 2011

Margie Parikh

Leadership development, career planning and management, management of start-ups, construction industry in India.

Abstract

Subject area

Leadership development, career planning and management, management of start-ups, construction industry in India.

Study level/applicability

Post graduate management courses, executive training programs/modules in leadership development; organizational culture and construction management.

Case overview

This case illustrates the shortcomings of both the management and leadership at a start-up business within a growing industry. The rapidly growing construction equipment manufacture and renting activity in India and the lack of structure, systems and resources characteristic of start-ups are complicated more by the fact that Itsun Heavy Industry India Pvt. Ltd (IHIIPL) was in India while its head quarter was in China. In exploring the diverse human, organizational and operational problems shadowing IHIIPL and their causes, students cannot only diagnose what went wrong and why for Dilip, but also sense how he could have handled these issues more effectively.

Expected learning outcomes

Dilip's case cautions managers against issues common to many industries and organizations and students will examine: self assessment and career choices: the case raises question of the gap between what was needed at IHIIPL and what skills and qualities Dilip brought to the job; leadership and leadership challenge: the case raises question of what kind of attitudes and actions constitute effective leadership; and managing the company performance for a start-up: Dilip faced a constant stream of operating problems: lack of procedures and systems, a non-supportive headquarter in China, inexperienced staff, shortages of resources and material and internal conflicts.

Supplementary materials

Teaching note.

Details

Emerald Emerging Markets Case Studies, vol. 1 no. 1
Type: Case Study
ISSN: 2045-0621

Keywords

Case study
Publication date: 17 October 2012

Gaunette Sinclair-Maragh

The proposed areas of study for this case are strategic management, marketing, tourism planning and development, hospitality management, attraction management and special event…

Abstract

Subject area

The proposed areas of study for this case are strategic management, marketing, tourism planning and development, hospitality management, attraction management and special event planning and management.

Study level/applicability

The case is suitable for undergraduate and graduate students pursuing courses in the areas of strategic management, marketing, tourism planning and development, hospitality and tourism management, attraction management and special event planning and management.

Case overview

The Denbigh Showground located in the parish of Clarendon, Jamaica, is the venue of the annual Agricultural and Industrial Show. Three separate studies conducted indicated the need for its development to enable the use of the facility all year round and to contribute to the socio-economic development of the parish. Suggested development options from these studies included a fun and amusement park, a site for eco-tourism and a multi-purpose agri-cultural facility with linkages to the parish's cultural legacies and places of interest. The large land acreage could facilitate its development, making the property a leading “agri-cultural” attraction concept.

Expected learning outcomes

he students should be able to: identify the typology of the Denbigh Showground as an attraction; categorize the product offerings of the Denbigh Showground from a marketing perspective; explain the factors to consider regarding the development of the showground; analyze the socio-economic contributions of the facility to the parish of Clarendon and the community's attitude towards the development of the showground; discuss the potential uses of the Denbigh Showground that can make it a leading international “agri-cultural” attraction; synthesize the concept of sustainable tourism development and its importance to the development and viability of the attraction for future generations; and assess other tourism concepts such as community-based tourism, special interest tourism and alternative tourism and how they relate to the development of the Denbigh Showground.

Social implications

This case study will help students understand the concept of an agri-cultural attraction and its impact on the socio-economic development of the surrounding communities and the country as a whole. The case will contribute to the existing body of knowledge in the areas of community development and residents’ perception regarding tourism development. It offers insights to both potential and current investors; provides practical guidance to the government and other tourism planners to enable better planning for the areas’ future growth and development; and serves as a reference for academicians as well as undergraduate and graduate students.

Supplementary materials

Teaching notes are available for educators only. Please contact your library to gain login details or e-mail: support@emeraldinsight.com to request teaching notes.

Case study
Publication date: 29 October 2021

Vanita Bhoola, Vineeta Dwivedi and Ayalur Vedpuriswar

Project Management, Entrepreneurship, Risk Management, Communication.

Abstract

Subject area

Project Management, Entrepreneurship, Risk Management, Communication.

Study level/applicability

Study level: MBA and Executive Education.

Applicability: This case can be taught in the project management course. It will cover the project-planning phase, which is an iterative or progressive elaboration for the entire project lifecycle. The case will help in discussing how project management is an important discipline to manage projects and stakeholders effectively.

Case overview

The case depicts the dilemma of a passionate entrepreneur who is setting up an ambitious dairy business but project execution goes awry. The case discusses the challenges related to project planning and execution.

It captures the essence of proactive risk management, measures that can mitigate risks and create opportunities. The case also discusses the entire project lifecycle from project initiation to closure and the challenges a manager has to face in terms of stakeholder engagement, risk management, stakeholder communication and scope change.

Expected learning outcomes

To understand the alignment of the project with the organisation strategy; to learn to create a project plan and monitor and control the scope, schedule, resources and costs; to accurately estimate project costs, timelines, and quality and schedule, using tools like MS Project; to learn the risk management techniques for managing projects, teams and stakeholders; and to manage stakeholder communication effectively.

Supplementary materials

Teaching notes are available for educators only.

Subject code

CSS 2: Built Environment.

Details

Emerald Emerging Markets Case Studies, vol. 11 no. 4
Type: Case Study
ISSN: 2045-0621

Keywords

1 – 10 of 754