1 – 10 of 33Stephen Akunyumu, Frank D.K. Fugar and Emmanuel Adinyira
The purpose of this study was to assess the readiness of construction companies in Ghana to partner with foreign companies in international construction joint ventures (ICJVs).
Abstract
Purpose
The purpose of this study was to assess the readiness of construction companies in Ghana to partner with foreign companies in international construction joint ventures (ICJVs).
Design/methodology/approach
Using the Verify End-User e-Readiness using a Diagnostic Tool (VERDICT) model, a survey with 31 construction companies was conducted to assess their readiness through four pre-defined elements of readiness.
Findings
The results indicated the readiness of construction companies to collaborate with potential foreign partners in ICJVs. Notwithstanding, certain areas such as management commitment to change, employee buy-in, process flexibility and technology infrastructure need improvement in some firms to achieve readiness. Government has a role in ensuring the readiness of domestic firms for the international market.
Originality/value
This study applies the VERDICT model, a tool originally designed to assess construction organizations’ readiness for e-commerce, to assess the readiness of Ghanaian construction companies for ICJVs.
Details
Keywords
Titus Ebenezer Kwofie, Florence Akyaa Ellis, Michael Nii Addy, Samuel Amos-Abanyie, Clinton Aigbavboa and Samuel Owusu Afram
The link between relationship typologies and effectiveness of conflict resolution approaches remains to be tested despite its significance in conflict management in construction…
Abstract
Purpose
The link between relationship typologies and effectiveness of conflict resolution approaches remains to be tested despite its significance in conflict management in construction project delivery. By using the four relationships attributes based on the group attachment theory, the purpose of the study was to explore the cluster of relationships among project teams and organisations and the performance of conflict management strategies across these clusters in the Ghanaian construction industry.
Design/methodology/approach
Using a deductive questionnaire survey in the Ghanaian construction industry, a total of 137 responses were gathered and analyzed using cluster analysis, mean scores and ANOVA to reveal the relationship clusters and performance of conflict management strategies across these clusters.
Findings
The results revealed eight relationship clusters that exist among project teams and organisations with distinct influence of roles & tasks function, cognition, emotions and behavior attributes across the relationship clusters. In the aspect of the effectiveness of conflict management strategies, it was noted that the performance of these strategies were significantly different across the groups. For instance, integrating as a conflict management strategy was deemed to be effective in resolving conflict in unitary, adversarial, pluralist, mutuality, collaborative and partnering relationship clusters. In the case of coopetitive and coercive relationships, the performance of integrating as a conflict management strategy was less effective. This study thus has empirically proved that, different relationship clusters of teams and organizations exist within the Ghanaian construction industry, and that they perform different roles & tasks functions, cognition, emotions and behavioural attributes in their formation. Additionally, the performance effectiveness of conflict management strategies differed across the relationship clusters.
Originality/value
By aligning the relationship attributes to the dynamics of relationship clusters experienced in project teams and organisations, relationship quality, suitability and effectiveness of conflict management strategies can be optimized. The findings can inform project teams and stakeholders to develop fit-for-purpose relationship attributes among teams and organisations to enhance team effectiveness, relationship quality and conflict management in the industry.
Details
Keywords
Tirivavi Moyo and Benviolent Chigara
Increased construction risk due to the complexity and numerous construction performance challenges requires improved construction project managers’ competence. However, contextual…
Abstract
Purpose
Increased construction risk due to the complexity and numerous construction performance challenges requires improved construction project managers’ competence. However, contextual interrogation of these competencies is limited. This paper aims to report on a study that sought to determine the expected competencies of construction project managers and assesses the existence of statistically significant differences due to gender, designation and educational levels of respondents.
Design/methodology/approach
A quantitative research design was instituted through the administration of a questionnaire survey on Project Managers, Architects, Engineers and Quantity surveyors working for consultants and contractors’ organizations. Descriptive and inferential statistics analysed significant differences due to demographic variables. Factor analysis was also used to reveal interrelated significant sets of competencies expected of construction project managers.
Findings
Factor analysis determined 11 significant components with the highest-ranked components comprising organizational savvy and experience in managing project constraints. The univariate analysis determining effective communication, leadership and good team-building skills as being the three most critical expected competencies. Significant differences due to educational levels were established, with shortcomings existing in those with Diplomas.
Research limitations/implications
The higher education institutions need to establish curricula designs that align with the competency expectations. Mentorship programmes within construction organizations can also be significant in bridging the existing competence gap. However, due to the exploratory nature of the study, the insights of clients were not considered.
Originality/value
The study determined competencies for construction project managers and demographic-specific interventions.
Details
Keywords
Isik Ates Kiral and Sevilay Demirkesen
This study aims to observe the impact of peripheral vision on construction safety. The study further intends to create awareness of eye diseases in construction safety, an…
Abstract
Purpose
This study aims to observe the impact of peripheral vision on construction safety. The study further intends to create awareness of eye diseases in construction safety, an important root cause for most construction-related hazards and accidents.
Design/methodology/approach
This study focuses on the impact of peripheral vision in terms of construction site safety. Experiments were conducted with construction employees with different qualifications, ages, expertise and previous safety training experience. The experiments were conducted with an experiment set consisting of a tangent screen to measure the peripheral angle of the participants. The study measured peripheral vision, which helped determine the vision field accordingly. In this context, a total of 32 participants were investigated in terms of their peripheral visual angle and the field of vision. The data collected were analyzed in terms of several statistical tests such as One-Sample t-test, multivariate ANOVA and multiple linear regression.
Findings
The results of the study indicated that there are significant differences in peripheral vision in terms of age of participants, work qualification, work experience, area of expertise and previous safety training experience. The study further revealed that most of the participants failed to satisfy both OSHA requirements about peripheral vision, and normal limits defined in the previous literature. The study further implies that participants, who reported previous sight problems or eye diseases are more vulnerable to construction site accidents.
Originality/value
Construction site safety remains a major concern for most construction companies despite the latest developments in technology. Several companies are struggling with poor safety performance, occupational injuries and illnesses, and work-related accidents resulting in fatalities. However, the root causes behind several construction accidents are still vague due to different dynamics in the construction industry. Among these root causes, poor sight, vision and or eye diseases constitute an important part. Hence, the study provides empirical evidence with the workers checked for eye health to help policymakers and industry practitioners in terms of developing awareness for eye-related injuries and accidents and review their safety programs accordingly.
Details
Keywords
Augustine Senanu Komla Kukah, De-Graft Owusu-Manu, Edward Badu and David John Edwards
This paper aims to evaluate the risk factors and determines the overall risk level (ORL) of public-private-partnership (PPP) power projects in Ghana using fuzzy synthetic…
Abstract
Purpose
This paper aims to evaluate the risk factors and determines the overall risk level (ORL) of public-private-partnership (PPP) power projects in Ghana using fuzzy synthetic evaluation methodology (FSEM).
Design/methodology/approach
In this paper review of literature led to the development of a 67-factor risk list which was ranked by experts and industry practitioners through a questionnaire survey.
Findings
These factors were grouped into principal risk factors (PRFs) using component analysis and they served as the input variables for fuzzy analysis. The seven components were: Contract and Payment risks, Environmental risks, Financial and Cost risks, Legal and Guarantee risks, Operation risks, Socio-Political and Performance risks (SPR) and Tender and Negotiation risks. Study showed that the ORL of Ghanaian PPP power projects is high implying they are risky to both the public and private sectors. Fuzzy analysis also confirmed SPR as the most critical principal factor.
Originality/value
This study is significant and demonstrates that fuzzy methodology can be used as a useful risk evaluation tool and risk assessment framework for private investors, policy makers and public sector.
Details
Keywords
Augustine Senanu Komla Kukah, De-Graft Owusu-Manu, Edward Badu, David J. Edwards and Eric Asamoah
Public-private partnership (PPP) power projects are associated with varying risk factors. This paper aims to develop a fuzzy quantitative risk allocation model (QRAM) to guide…
Abstract
Purpose
Public-private partnership (PPP) power projects are associated with varying risk factors. This paper aims to develop a fuzzy quantitative risk allocation model (QRAM) to guide decision-making on risk allocation in PPP power projects in Ghana.
Design/methodology/approach
A total of 67 risk factors and 9 risk allocation criteria were established from literature and ranked in a two-round Delphi survey using questionnaires. The fuzzy synthetic evaluation method was used in developing the risk allocation model.
Findings
The model’s output variable is the risk allocation proportions between the public body and private body based on their capability to manage the risk factors. Out of the 37 critical risk factors, the public sector was allocated 12 risk factors with proportions = 50%, while the private sector was allocated 25 risk factors with proportions = 50%.
Originality/value
To the best of the authors’ knowledge, this research presents the first attempt in Ghana at endeavouring to develop a QRAM for PPP power projects. There is confidence in the model to efficiently allocate risks emanating from PPP power projects.
Details
Keywords
Audrey Mertens, Yaprak Hamarat and Catherine Elsen
This research focuses on the interactions between architects and end-users during the design process of housing projects, both experiencing challenges and friction points when…
Abstract
Purpose
This research focuses on the interactions between architects and end-users during the design process of housing projects, both experiencing challenges and friction points when meeting.
Design/methodology/approach
The authors conducted a systematic literature review (SLR), based on and adapted from Kitchenham and Charters' work (2007). The thematic analysis of N = 104 identified articles reveals 13 main themes and 30 subthemes specific to architects, end-users and the interactions of architects and end-users, and 3 main groups of other actors intervening in these dynamics. The authors organize the data by actors and the actors' social encounters, themes and subthemes. The authors focus on some aspects, given possible evolution of practices.
Findings
The authors question the role of architects and the ways both parties share respective knowledge. The authors also discuss the various scales of social encounters depicted through literature, from traditional discursive meetings to participatory practices, and raise the lack of convincing tools genuinely used in current housing architecture practices. Finally, the authors point out the need for further field research in order to practically bridge the gap between researchers and practitioners.
Originality/value
The authors present an overview of the most relevant papers, organized in a table and grouped by themes. This represents a major output of this SLR, and gives the concerned readers the opportunity to get a grasp on readers' sub/theme of interest.
Details
Keywords
Matthew Osivue Ikuabe, Clinton Ohis Aigbavboa, Wellington Didibhuku Thwala, Donald Chiyangwa and Ayodeji Emmanuel Oke
Joint ventures (JVs) serve as a viable tool in mitigating some of the challenges posed to the effective delivery of construction projects. However, JVs are highly susceptible to…
Abstract
Purpose
Joint ventures (JVs) serve as a viable tool in mitigating some of the challenges posed to the effective delivery of construction projects. However, JVs are highly susceptible to failure in most developing countries. Therefore, this study seeks to unravel the critical factors influencing the failure of JVs in the South African construction industry.
Design/methodology/approach
A quantitative approach was adopted for the study using a well-structured questionnaire as the instrument for data collection. Respondents for the study were built environment professionals in Gauteng province in South Africa. Data elicited from respondents were analyzed using a four-pronged process which included descriptive statistics, one sample t-test, exploratory factor analysis and confirmatory factor analysis.
Findings
Resulting from the analysis conducted, four critical components emerged as the major factors influencing the failure of JVs in the South African construction industry, which are inefficient financial framework, divergent organizational culture, poor project governance and inadequacies from project stakeholders.
Practical implications
The outcome of this study presents a roadmap for stakeholders in the construction industry with the requisite knowledge of the critical factors leading to the failure of JVs, consequently providing a clear path for the successful delivery of JV mandates.
Originality/value
Evidence from literature suggests that several studies have been conducted on the various aspects of JVs in the South African construction industry; however, none has focused on the leading factors attributed to the failure of JVs. Also, the findings of this study cultivate a good theoretical platform for future studies on JVs.
Details
Keywords
Millicent Asah-Kissiedu, Patrick Manu, Colin Anthony Booth, Abdul-Majeed Mahamadu and Kofi Agyekum
For construction organisations to be effective at implementing an integrated safety, health and environmental (SHE) management system, they require the right level of…
Abstract
Purpose
For construction organisations to be effective at implementing an integrated safety, health and environmental (SHE) management system, they require the right level of organisational capability. This capability includes the policies, systems and resources of the organisation. However, within the academic literature, it is unclear which organisational attributes of construction companies are important for implementing integrated SHE management. This study aims to explore the organisational attributes that determine integrated SHE management capability and their relative priorities.
Design/methodology/approach
The study used a literature review supported by expert verification and a subsequent three-round expert Delphi technique accompanied by applying the voting analytical hierarchy process.
Findings
The study identified 20 attributes grouped under five main thematic categories. These are strategy (the organisation’s vision and top management commitment); process (the organisation’s procedures and processes for SHE management); people (organisation’s human resources, their competence, roles, responsibilities and involvement in SHE management); resources (organisation’s physical and financial resources for SHE management) and information (SHE related documents, data, records and their communication across an organisation). While these thematic categories and the attributes within carry different weights of importance, the strategy-related attributes are the most important, followed by the people-related attributes.
Originality/value
The results of this study should enable construction companies and key industry stakeholders to understand construction companies’ capability to successfully implement an integrated SHE management system. Furthermore, construction companies should be able to prioritise efforts or investments to enhance their SHE management capability.
Details
Keywords
Emmanuel Dele Omopariola, Abimbola Olukemi Windapo, David John Edwards, Clinton Ohis Aigbavboa, Sunday Ukwe-Nya Yakubu and Onimisi Obari
Previous studies have postulated that an advance payment system (APS) positively impacts the contractor's working capital and is paramount to ensuring an efficient and effective…
Abstract
Purpose
Previous studies have postulated that an advance payment system (APS) positively impacts the contractor's working capital and is paramount to ensuring an efficient and effective project cash flow process. However, scant research has been undertaken to empirically establish the cash flow performance and domino effect of APS on project and organisational performance.
Design/methodology/approach
The epistemological design adopted a positivist philosophical stance augmented by deductive reasoning to explore the phenomena under investigation. Primary quantitative data were collected from 504 Construction Industry Development Board (CIDB) registered contractors (within the grade bandings 1–9) in South Africa. A five-point Likert scale was utilised, and subsequent data accrued were analysed using structural equation modelling (SEM).
Findings
Emergent findings reveal that the mandatory use of an APS does not guarantee a positive project cash flow, an improvement in organisational performance or an improvement in project performance.
Practical implications
The ensuing discussion reveals the contributory influence of APS on positive cash flow and organisational performance, although APS implementation alone will not achieve these objectives. Practically, the research accentuates the need for various measures to be concurrently adopted (including APS) towards ensuring a positive project cash flow and improved organisational and project performance.
Originality/value
There is limited empirical research on cash flow performance and the domino effect of APS on project and organisational performance in South Africa, nor indeed, the wider geographical location of Africa as a continent. This study addresses this gap in the prevailing body of knowledge.