Article
Publication date: 23 January 2023

Amir Naser Ghanbaripour, Craig Langston, Roksana Jahan Tumpa and Greg Skulmoski

Despite considerable research on the subject, there is still some misunderstanding about what characterizes successful project delivery in construction projects. Evaluating…

461

Abstract

Purpose

Despite considerable research on the subject, there is still some misunderstanding about what characterizes successful project delivery in construction projects. Evaluating project delivery success is crucial for organizations since it enables them to prepare for future growth through more effective project management mechanisms and rank the organization's projects for continuous improvement. There is considerable disagreement over a set of success criteria that can be applied to all kinds of projects when evaluating project delivery success, making it a complicated procedure for practitioners and scholars. This research seeks to alleviate the problem by validating and testing a systematic project delivery success model (3D integration model) in the Australian construction industry. The aim is to establish a dependable approach built upon prior research and reliable in evaluating delivery success for any project type.

Design/methodology/approach

Based on a novel project delivery success model, this research applies a case study methodology to analyse 40 construction projects undertaken by a single Australian project management consultancy. The research utilizes a mixed-method research approach and triangulates three sets of data. First, the project delivery success (PDS) scores of the projects are calculated by the model. Second, a qualitative analysis targeting the performance of the same projects using a different system called the performance assessment review (PAR) scores was obtained. These culminate in two sets of ranking. The third step seeks validation of results from the head of the partnering organization that has undertaken the projects.

Findings

The findings of this study indicate that the 3D integration model is accurate and reliable in measuring the success of project delivery in construction projects of various sizes, locations and durations. While the model uses six key performance indicators (KPIs) to measure delivery success, it is evident that three of these may significantly improve the likelihood of PDS: value, speed and impact. Project managers should focus on these priority aspects of performance to generate better results.

Research limitations/implications

Restrictions inherent to the case study approach are identified for this mixed-method multiple-case study research. There is a limitation on the sample size in this study. Despite the researcher's best efforts, no other firm was willing to share such essential data; therefore, only 40 case studies could be analysed. Nonetheless, the number of case studies met the literature's requirements for adequate units for multiple-case research. This research only looked at Australian construction projects. Thus, the conclusions may not seem applicable to other countries or industries. The authors investigated testing the PDS in the construction sector. It can assist in improving efficiency and resource optimization in this area. Nonetheless, the same technique may be used to analyse and rank the success of non-construction projects.

Originality/value

Despite the research conducted previously on the PDS of construction projects, there is still confusion among researchers and practitioners about what constitutes a successful project delivery. Although several studies have attempted to address this confusion, no consensus on consistent performance metrics or a practical project success model has been formed. More importantly, (1) the ability to measure success across multiple project types, (2) the use of triple bottom line (TBL) to incorporate sustainability in evaluating delivery success and (3) the use of a complexity measurement tool to adjust delivery success scores set the 3D integration model apart from others.

Details

Smart and Sustainable Built Environment, vol. 13 no. 3
Type: Research Article
ISSN: 2046-6099

Keywords

Article
Publication date: 25 March 2022

Innocent Chigozie Osuizugbo, Kevin Chuks Okolie and Olalekan Shamsideen Oshodi

Improving buildability of building designs with the aid of buildability assessment is essential because of the effect of designs on construction. Despite the plethora of research…

Abstract

Purpose

Improving buildability of building designs with the aid of buildability assessment is essential because of the effect of designs on construction. Despite the plethora of research into buildability reported over the years, a review of the literature shown a dearth of research into the factors supporting the implementation of buildability assessment. Because buildability assessment has been confirmed to be highly beneficial to construction business, this study aims to investigate the factors supporting the implementation of buildability assessment as a tool for buildability improvement using Nigeria as a representative case.

Design/methodology/approach

Survey research method was adopted for the study. Questionnaires were administered to a purposively selected group of architects, engineers, builders and quantity surveyors involved in construction project delivery within client, consulting and contracting organisations in Nigeria. A total of 368 questionnaires were distributed among the sampled participants, out of which, a total of 219 representing 60% were sufficiently filled and returned. Data collected were analysed using inferential and descriptive statistics.

Findings

The results revealed owner’s commitment, clients’ awareness of the benefits of conducting buildability assessment on building design, unity amongst different professionals in the construction industry, designers consider buildability important, adequate coordination amongst different design disciplines, adequate channel for co-ordination and communication between designers and constructors at the design stage and adequate support from the government as the top most seven factors supporting buildability assessment implementation in construction sector of Nigeria. Secondly, the results from the research revealed that there is no statistically significant difference in factors supporting buildability assessment implementation in construction between clients and consulting and contracting construction organisations in Nigeria.

Originality/value

The findings provide in-depth insight of the factors supporting the implementation of buildability assessment in construction that can help principal stakeholders in construction to facilitate development of strategies required in supporting the adoption and implementation of buildability assessment tool for buildability improvement.

Details

Journal of Engineering, Design and Technology , vol. 22 no. 3
Type: Research Article
ISSN: 1726-0531

Keywords

Article
Publication date: 28 March 2022

Muhammad Ayat, Azmat Ullah and Changwook Kang

The primary purpose of this study is to explore the relationship between the unsolicited proposal (USP) and the performance of private participation infrastructure (PPI) projects…

Abstract

Purpose

The primary purpose of this study is to explore the relationship between the unsolicited proposal (USP) and the performance of private participation infrastructure (PPI) projects in developing countries.

Design/methodology/approach

The main data set for this study was collected from the World Bank database consisting of 8,951 PPI projects that occurred in developing countries from 1996 to 2020. Hierarchical logistic regression was applied for investigating the effects of USPs on project success. Three moderators, namely, control of corruption, presence of local sponsor and project size were also included in the model to test the impact of their interactions with the USP on the performance of PPI projects. Further, to assess the impact of the effect of USPs, the average marginal effect was calculated. The framework used in this study consists of 18 control variables, three moderators and one noncontrolled independent variable (the USP).

Findings

The results of hierarchical logistic regression indicate that USPs have a significant and negative effect on the success of PPI projects occurring in developing countries. The negative effect of a USP weakens with the presence of local sponsors and stronger control of corruption in the host country. However, contrary to the authors’ expectations, the results show that project size does not significantly affect the association between USPs and the success of PPI projects. Moreover, the results of average marginal effects show that the negative impact of USP on the success of PPI projects ranges between 2.4% and 3.8%.

Originality/value

This study quantifies the negative impact of USP on the success of PPI projects in developing countries, which will be helpful for the practitioners to understand the associated risk with USP projects. Furthermore, it also identifies the moderating roles of control of corruption and the presence of local sponsors on the relationship between USP and the success of PPI projects.

Details

Journal of Engineering, Design and Technology , vol. 22 no. 3
Type: Research Article
ISSN: 1726-0531

Keywords

Open Access
Article
Publication date: 16 October 2023

Emmanuel Dele Omopariola, Abimbola Olukemi Windapo, David John Edwards, Clinton Ohis Aigbavboa, Sunday Ukwe-Nya Yakubu and Onimisi Obari

Previous studies have postulated that an advance payment system (APS) positively impacts the contractor's working capital and is paramount to ensuring an efficient and effective…

Abstract

Purpose

Previous studies have postulated that an advance payment system (APS) positively impacts the contractor's working capital and is paramount to ensuring an efficient and effective project cash flow process. However, scant research has been undertaken to empirically establish the cash flow performance and domino effect of APS on project and organisational performance.

Design/methodology/approach

The epistemological design adopted a positivist philosophical stance augmented by deductive reasoning to explore the phenomena under investigation. Primary quantitative data were collected from 504 Construction Industry Development Board (CIDB) registered contractors (within the grade bandings 1–9) in South Africa. A five-point Likert scale was utilised, and subsequent data accrued were analysed using structural equation modelling (SEM).

Findings

Emergent findings reveal that the mandatory use of an APS does not guarantee a positive project cash flow, an improvement in organisational performance or an improvement in project performance.

Practical implications

The ensuing discussion reveals the contributory influence of APS on positive cash flow and organisational performance, although APS implementation alone will not achieve these objectives. Practically, the research accentuates the need for various measures to be concurrently adopted (including APS) towards ensuring a positive project cash flow and improved organisational and project performance.

Originality/value

There is limited empirical research on cash flow performance and the domino effect of APS on project and organisational performance in South Africa, nor indeed, the wider geographical location of Africa as a continent. This study addresses this gap in the prevailing body of knowledge.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 13
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 4 November 2022

Alan J. McNamara, Sara Shirowzhan and Samad M.E. Sepasgozar

This paper aims to identify the relevant contributing constructs of readiness for the implementation of intelligent contracts (iContracts) in the construction industry. This study…

Abstract

Purpose

This paper aims to identify the relevant contributing constructs of readiness for the implementation of intelligent contracts (iContracts) in the construction industry. This study investigates the relationship between the personality dimensions of technology readiness index (TRI) and the system specific factors of technology acceptance model (TAM) within the context of iContracts.

Design/methodology/approach

Drawing insights from the extant literature and the author's previous qualitative investigations into iContract readiness constructs, a quantitative approach is used to operationalise the constructs by offering relevant statements to be measured and validated through a multiple-item scale against the users intent to accept the future iContract technology.

Findings

This study confirms and validates the relationship of the proposed iContract readiness index (iCRI) statements against the established TAM factors by offering 18 new constructs influencing technology readiness of the iContract technology. This study proves 9 of the 12 hypotheses highlighting key factors to be addressed for the successful development of the iContract technology.

Practical implications

This paper contributes to the body of knowledge by proposing a novel iCRI that informs an iContract technology readiness acceptance model (iCTRAM) for a trending technology. The iCTRAM can guide developers in producing an appropriate iContract solution and assess the readiness of users and organisations for the successful adoption of the iContract concept.

Originality/value

This study offers a unique theoretical framework, in an embryonic field, for predicting the success of iContract implementation within construction organisations. This study combines the established studies of TRI and TAM in producing a predictive iContract readiness assessment tool.

Details

Construction Innovation , vol. 24 no. 3
Type: Research Article
ISSN: 1471-4175

Keywords

Open Access
Article
Publication date: 1 August 2023

Jacob Guerrero and Susanne Engström

By adopting the “hard” and “soft” project management (PM) approaches from the PM-literature, this paper aims to problematize the expected role of client organizations in driving…

Abstract

Purpose

By adopting the “hard” and “soft” project management (PM) approaches from the PM-literature, this paper aims to problematize the expected role of client organizations in driving innovation in the transport infrastructure sector.

Design/methodology/approach

Addressing a large public client in Sweden, a case study design was initially applied to provide in-depth insights and perspectives of client project managers’ views and experiences of managing projects expected to drive innovation. In this paper, the concepts of “hard” and “soft” are used to discuss empirical findings on challenges associated with adopting a PM-approach for driving innovation in projects. The empirical material consists of interview data, complemented with observations and archival data.

Findings

Findings reveal challenges associated with combining hard and soft approaches, frequently demonstrating difficulties in balancing short-term project expectations with the promotion of innovation. In line with the literature, project managers note that there is a need for soft approaches to promote development and drive innovation. Yet, findings reflect a situation in which operational success criteria predominate, whereas soft approaches are not sufficiently used to create the grounds required for fostering innovation.

Originality/value

Insights are provided into how PM-approaches may impact construction innovation in the infrastructure sector, demonstrating a need for further research on the challenges and implications of applying and combining hard and soft PM-approaches.

Details

Construction Innovation , vol. 24 no. 7
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 23 April 2024

Mahmoud Sabry Shided Keniwe, Ali Hassan Ali, Mostafa Ali Abdelaal, Ahmed Mohamed Yassin, Ahmed Farouk Kineber, Ibrahim Abdel-Rashid Nosier, Ola Diaa El Monayeri and Mohamed Ashraf Elsayad

This study focused on exploring the performance factors (PFs) that impact Infrastructure Sanitation Projects (ISSPs) in the construction sector. The aim was twofold: firstly, to…

12

Abstract

Purpose

This study focused on exploring the performance factors (PFs) that impact Infrastructure Sanitation Projects (ISSPs) in the construction sector. The aim was twofold: firstly, to identify these crucial PFs and secondly, to develop a robust performance model capable of effectively measuring and assessing the intricate interdependencies and correlations within ISSPs. By achieving these objectives, the study aimed to provide valuable insights into and tools for enhancing the efficiency and effectiveness of sanitation projects in the construction industry.

Design/methodology/approach

To achieve the study's aim, the methodology for identifying the PFs for ISSPs involved several steps: extensive literature review, interviews with Egyptian industry experts, a questionnaire survey targeting industry practitioners and an analysis using the Relative Importance Index (RII), Pareto principle and analytic network process (ANP). The RII ranked factor importance,  and Pareto identified the top 20% for ANP, which determined connections and interdependencies among these factors.

Findings

The literature review identified 36 PFs, and an additional 13 were uncovered during interviews. The highest-ranked PF is PF5, while PF19 is the lowest-ranked. Pareto principle selected 11 PFs, representing the top 20% of factors. The ANP model produced an application for measuring ISSP effectiveness, validated through two case studies. Application results were 92.25% and 91.48%, compared to actual results of 95.77% and 97.37%, indicating its effectiveness and accuracy, respectively.

Originality/value

This study addresses a significant knowledge gap by identifying the critical PFs that influence ISSPs within the construction industry. Subsequently, it constructs a novel performance model, resulting in the development of a practical computer application aimed at measuring and evaluating the performance of these projects.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 8 November 2022

Anna Pistoni, Anna Arcari and Chiara Gigliarano

This study analyses the link between product/service innovation, partnerships and Managerial Control System (MCS). Particularly, it aims to analyse empirically the role of MCS in…

Abstract

Purpose

This study analyses the link between product/service innovation, partnerships and Managerial Control System (MCS). Particularly, it aims to analyse empirically the role of MCS in supporting the innovation partnership successful functioning and management.

Design/methodology/approach

The sample of this study consists of 106 Italian manufacturing firms belonging to the sectors of the Italian economy with the largest number of registered patents according to the European trend chart on innovation.

Findings

The results show that MCS may play a key role in reducing risks and lowering the likelihood of failure of innovation partnerships. Particularly, the authors found a positive correlation between the use of informal control mechanisms and a partnership’s successful performance. Moreover, among informal control, the findings show that trust is the only true informal mechanism that can guarantee a successful collaboration. The results of this study may offer relevant implications for practitioners. With regard to the control of the partnership’s activities, the initiatives and creativity of those who are actively involved in the innovation process should not be inhibited; therefore, stifling them with strict rules and procedures would be ineffective but if a firm is not willing to give up formal control mechanisms altogether because it does not believe that a trust-based coordination is sufficiently reassuring, it should opt for “weak”, albeit formal, control mechanisms based on a shared production and management of plans and reports, thus ensuring a perfect information symmetry among different partners.

Originality/value

Notwithstanding the different opportunities provided by partnerships and strategic alliances to support there is a growing body of evidence of a high failure rate in such organisational forms. One of the causes cited in the literature is the high level of risk associated with alliances as compared to internal development of innovation. The risks mainly arise from the difficulties to obtain cooperation with partners that might have different objectives, and from the potential opportunistic behaviour of some of the partners. This is particularly true in innovation networks where the uncertainty of producing an interesting result is very high and the investments that the partners make are considerable. In this context, MCS could play a relevant role in reducing the risks and decreasing the likelihood of failure.

Details

European Journal of Innovation Management, vol. 27 no. 4
Type: Research Article
ISSN: 1460-1060

Keywords

Article
Publication date: 17 October 2023

Qiong Wu, Qiwei Zhou and Kathryn Cormican

Shared leadership is an effective mechanism for managing project teams. Its performance-enhancing benefits have been demonstrated in many studies. Nonetheless, there is an obvious…

Abstract

Purpose

Shared leadership is an effective mechanism for managing project teams. Its performance-enhancing benefits have been demonstrated in many studies. Nonetheless, there is an obvious silence about how to promote shared leadership in Lean Six Sigma (LSS) project teams. To address this deficit, the purposes of this study are to investigate the influence of shared leadership on LSS project success and to explore how team psychological safety, project task complexity and project task interdependence influence shared leadership.

Design/methodology/approach

A multi-source, time-lagged survey design with a four-month interval was conducted. To do this, the authors collected data from 71 project teams (comprising 71 project managers and 352 project members) using LSS approaches in the manufacturing and service industries.

Findings

The findings show that shared leadership positively influences LSS project success. The authors also found that team psychological safety fosters the development of shared leadership and, more importantly, these effects are stronger when the tasks are more complex and more interdependent.

Practical implications

These findings advance our understanding of the factors that enable shared leadership and equip LSS project managers with practical techniques to improve shared leadership for the success of their projects.

Originality/value

This study extends the theory of shared leadership to the context of LSS project management and is among the first, to the best of the authors’ knowledge, to theoretically propose and empirically validate how to promote shared leadership in LSS project teams.

Details

International Journal of Lean Six Sigma, vol. 15 no. 3
Type: Research Article
ISSN: 2040-4166

Keywords

Open Access
Article
Publication date: 28 June 2022

Sahar Jawad, Ann Ledwith and Rashid Khan

There is growing recognition that effective project control systems (PCS) are critical to the success of projects. The relationship between the individual elements of PCS and…

1619

Abstract

Purpose

There is growing recognition that effective project control systems (PCS) are critical to the success of projects. The relationship between the individual elements of PCS and successfully achieving project objectives has yet to be explored. This research investigates the enablers and barriers that influence the elements of PCS success and drive project objectives.

Design/methodology/approach

This study adopts a mixed approach of descriptive analysis and regression models to explore the impact of six PCS elements on project outcomes. Petroleum and chemical projects in Saudi Arabia were selected as a case study to validate the research model.

Findings

Data from a survey of 400 project managers in Saudi’s petroleum and chemical industry reveal that successful PCS are the key to achieving all project outcomes, but they are particularly critical for meeting project cost objectives. Project Governance was identified as the most important of the six PCS elements for meeting project objectives. A lack of standard processes emerged as the most significant barrier to achieving effective project governance, while having skilled and experienced project team members was the most significant enabler for implementing earned value.

Practical implications

The study offers a direction for implementing and developing PCS as a strategic tool and focuses on the PCS elements that can improve project outcomes.

Originality/value

This research contributes to project management knowledge and differs from previous attempts in two ways. Firstly, it investigates the elements of PCS that are critical to achieving project scope, schedule and cost objectives; secondly, enablers and barriers of PCS success are examined to see how they influence each element independently.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 13
Type: Research Article
ISSN: 0969-9988

Keywords