Publication date: 8 December 2022

Rajenlall Siriram

The objective of this research is to explore integration and transition activities in large industrial projects. The purpose is to (a) obtain a better understanding of the…

1715

Abstract

Purpose

The objective of this research is to explore integration and transition activities in large industrial projects. The purpose is to (a) obtain a better understanding of the integration and transition activities between the project front-end (FE) and project initiation phases (PIPs), (b) explore what, how and when these integrations and transitions occur, and (c) explore what the integration and transition activities mean to project practitioners.

Design/methodology/approach

A qualitative research design methodology is followed, based on interviews using open-ended questions. An expert panel is used to provide responses to questions pertaining to the integration and transition between the project FE and PIP. The research is focused on managing large projects in the South African electrical engineering industrial projects industry. A literature review combined with empirical analysis reflects the importance of integrating and transitioning in project business.

Findings

The findings provide guidance to researchers and practitioners on integration and transition mechanisms, how and when these occur. It highlights the benefits of integration and transition activities. Important lessons for researchers and practitioners are provided together with areas for future research.

Originality/value

This is an interpretative analysis of expert opinion. Expert panel members are experienced at senior decision-making level, and their expertise was accessed based on experience, education and knowledge. This extensive experience is shared in this paper providing insights into their opinions, experiences, success and failures. These inputs together with the literature review provide interesting implications for both a theoretical foundation as well as practical implications for practitioners.

Details

International Journal of Managing Projects in Business, vol. 16 no. 8
Type: Research Article
ISSN: 1753-8378

Keywords

Open Access
Article
Publication date: 4 April 2023

Andrew Ebekozien, Clinton Ohis Aigbavboa and Mantoa Ramotshela

Stakeholder engagement in construction projects is an ingredient that contributes to project optimal performance. Many developing countries have a paucity of literature about…

4695

Abstract

Purpose

Stakeholder engagement in construction projects is an ingredient that contributes to project optimal performance. Many developing countries have a paucity of literature about stakeholders' engagement in construction projects. Therefore, the study investigated South Africa's shareholders' engagement in construction projects and recommended possible measures to mitigate potential limitations.

Design/methodology/approach

The researchers collated data from South African experts in stakeholder engagement via a phenomenology type of qualitative research design. They explored the “perceived hindrances” facing stakeholders' engagement in construction projects and proffer measures to mitigate them. The study analysed collected data via thematic analysis and achieved saturation. Three themes emerged from the analysed data.

Findings

Findings show that efficient stakeholder engagement will enhance team collaboration and integrated construction project delivery. Results identified the perceived limitations facing stakeholders' engagement in South Africa's construction projects and categorised them into individual perceived hindrances, organisational perceived hindrances and government-related perceived hindrances. Also, findings proffer measures to mitigate perceived hindrances via policies and programmes within the sector.

Practical implications

Besides enhancing policymakers and other stakeholders in South Africa's construction industry to understand the benefits of stakeholder engagement better, the study may stir up the construction sector's stakeholders to embrace enhanced and effective stakeholders' management.

Originality/value

This study contributes to construction project practice that involves stakeholders, as it reveals the underlying causes of perceived hindrances facing stakeholders' engagement in construction projects. Also, it proffers feasible solutions to mitigate these hindrances and enhance stakeholders' engagement within South Africa's construction projects.

Details

Benchmarking: An International Journal, vol. 31 no. 3
Type: Research Article
ISSN: 1463-5771

Keywords

Open Access
Article
Publication date: 5 April 2022

Danstan Bwalya Chiponde, Barry Gledson and David Greenwood

In his 1943 paper “A Theory of Human Motivation”, Maslow suggested the “Hierarchy of Needs” as a classification system that described the stimuli for human behaviour. Presently…

2626

Abstract

Purpose

In his 1943 paper “A Theory of Human Motivation”, Maslow suggested the “Hierarchy of Needs” as a classification system that described the stimuli for human behaviour. Presently, project behaviour research, which inspired this work, encourages undertaking research on behavioural aspects within and across organisational and project settings. Therefore, the purpose of this paper is to analyse project-based organisations’ (PBOs) seemingly reluctance in engaging in organisational learning from past project failures by drawing upon both institutional theory (since it focuses on how firms interact) and Maslow’s model within a project behaviour piece of research.

Design/methodology/approach

Interviews were held with purposively selected construction professionals from the UK construction industry, and data were analysed using thematic analysis.

Findings

Besides the need to learn from failures, PBOs’ main competing needs revolve around their “competitiveness”; “profitability and productivity”; “repeat business” and “reputation and partnering”. Mirroring these needs against Maslow’s hierarchy of needs, “competitiveness” and “profitability” are analogous to foundational “physiological” and “safety” needs. The need for “repeat business” and “reputation” is approximated with Maslow’s “affiliation” and “self-esteem” needs, and organisational learning is associated with “self-actualisation”. From an institutional theory perspective, such response to failure is influenced by the need to show legitimacy and conformity imposed by institutional factors.

Practical implications

Instead of taking a simplified approach to learning from failure such as the use of technological tools, PBOs and the sector at large should consider more robust approaches, by appreciating the influence of institutional factors and the external environment on their efforts to learn from failure.

Originality/value

Unlike past studies that present organisational learning within PBOs as a straightforward process, this study instead highlights the need of understanding various competing needs within a PBO and the external pressure.

Details

Frontiers in Engineering and Built Environment, vol. 2 no. 2
Type: Research Article
ISSN: 2634-2499

Keywords

Open Access
Article
Publication date: 25 June 2019

Guoqiang Tian, Yupu Zhao and Rukai Gong

In the transitional process of promoting market-oriented interest rate, China is confronted with an important theoretical and practical issue: how to avoid bank runs and realize…

1346

Abstract

Purpose

In the transitional process of promoting market-oriented interest rate, China is confronted with an important theoretical and practical issue: how to avoid bank runs and realize the smooth operation of the financial system. The purpose of this paper is to construct a bank-run dynamic model by taking into account a market environment with the transmission of multiple rounds of noise information, a comprehensive consideration of depositors’ expectation of return on assets (or earning rate/yields of assets), the efficiency of information processing and dissemination, and the different motives for premature withdrawal.

Design/methodology/approach

The authors discussed the dynamic process of bank runs, furnished the ratio and number of each round of bank run, and characterized the corresponding dynamic equilibrium as well. Furthermore, the authors expanded the benchmark model by incorporating the deposit insurance system (DIS) to discuss the action mechanism of DIS overruns.

Findings

The results show that DIS implementation has two opposite effects: stabilized expectation and moral hazard, by virtue of its influence over the two types of premature withdrawal motives of depositors; the implementation effect of DIS rests with the dual-effect comparison, which is endogenous to the institutional environment.

Originality/value

The policy implications are as follows: while implementing DIS, it is necessary to establish and improve the corresponding institutional construction and supporting measures, to consolidate market discipline and improve the supervisory role of the bank’s internal governance mechanism, so as to reduce the potential moral hazards. The financial system reform shall be furthered and the processing and dissemination efficiency of information be elevated to prompt depositors to form stable withdrawal expectations, thereby enhancing the stabilizing effect of DIS.

Details

China Political Economy, vol. 2 no. 1
Type: Research Article
ISSN: 2516-1652

Keywords

Open Access
Article
Publication date: 7 November 2016

Ali Tarhini, Mazen El-Masri, Maged Ali and Alan Serrano

A number of studies have shown that internet banking (IB) implementation is not only determined by banks or government support, but also by perceptions and experience of IB users…

24294

Abstract

Purpose

A number of studies have shown that internet banking (IB) implementation is not only determined by banks or government support, but also by perceptions and experience of IB users. IB studies have showed encouraging results from academics in developed countries. Yet little is known about the user adoption of IB in Lebanon. The purpose of this paper is to investigate the factors that may hinder or facilitate the acceptance and usage of IB in Lebanon.

Design/methodology/approach

A conceptual framework was developed through extending the unified theory of acceptance and use of technology (UTAUT) by incorporating two additional factors namely; perceived credibility (PC) and task-technology fit (TTF). A quantitative approach based on cross-sectional survey was used to collect data from 408 IB consumers. Data were analysed using structural equation modelling based on AMOS 20.0.

Findings

The results of the structural path revealed that performance expectancy (PE), social influence, PC and TTF to be significant predictors in influencing customers’ behavioural intention (BI) to use IB and explained 61 per cent of its variance, with PE was found the strongest antecedent of BI. Contrary to the UTAUT, the effect of effort expectancy on BI was insignificant. In addition, both BI and facilitating conditions were found to affect the actual usage behaviour and explained 64 per cent of its variance

Practical implications

This study would be helpful for bank managers and policy makers to explain the currently relatively low penetration rate of IB in formulating strategies to encourage the adoption and acceptance of IB by Lebanese customers, where IB is still considered an innovation.

Originality/value

This study is the first research that extend the UTAUT by incorporating two additional factors namely; PC and TTF to study the IB in the Lebanese context. This study contributes to the research on computer technology usage by looking at IB adoption and incorporation into the lives of customers via the BI to use and actual usage of IB in Lebanon.

Open Access
Article
Publication date: 23 December 2022

Rouzbeh Shabani, Tobias Onshuus Malvik, Agnar Johansen and Olav Torp

Uncertainty management (UM) in projects has been a point of attention for researchers for many years. Research on UM has mainly been aimed at uncertainty analyses in the front-end…

2056

Abstract

Purpose

Uncertainty management (UM) in projects has been a point of attention for researchers for many years. Research on UM has mainly been aimed at uncertainty analyses in the front-end and managing uncertainty in the construction phase. In contrast, UM components in the design phase have received less attention. This research aims to improve knowledge about the key components of UM in the design phase of large road projects.

Design/methodology/approach

This study adopted a literature review and case study. The literature review was used to identify relevant criteria for UM. These criteria helped to design the interview guide. Multiple case study research was conducted, and data were collected through document study and interviews with project stakeholders in two road projects. Each case's owners, contractors and consultants were interviewed individually.

Findings

The data analysis obtained helpful information on the involved parties, process and exploit tools and techniques during the design phase. Johansen's (2015) framework [(a) human and organisation, (b) process and (c) tools and techniques)] was completed and developed by identifying relevant criteria (such as risk averse or risk-taker, culture and documentation level) for each component. These criteria help to measure UM performance. The authors found that owners and contractors are major formal UM actors, not consultants. Empirical data showed the effectiveness of Web-based tools in UM.

Research limitations/implications

The studied cases were Norwegian, and this study focussed on uncertainties in the project's design phase. Relevant criteria did not cover all the criteria for evaluating the performance of UM. Qualitative evaluation of criteria allows further quantitative analysis in the future.

Practical implications

This paper gave project owners and managers a better understanding of relevant criteria for measuring UM in the owners and managers' projects. The paper provides policy-makers with a deeper understanding of creating rigorous project criteria for UM during the design phase. This paper also provides a guideline for UM in road projects.

Originality/value

This research gives a holistic evaluation of UM by noticing relevant criteria and criteria's interconnection in the design phase.

Details

International Journal of Managing Projects in Business, vol. 16 no. 8
Type: Research Article
ISSN: 1753-8378

Keywords

Open Access
Article
Publication date: 25 August 2021

Tahir Ali, Aurangzeab Butt, Ahmad Arslan, Shlomo Yedidia Tarba, Sniazhana Ana Sniazhko and Minnie Kontkanen

This study investigates an under-researched yet fundamental question of how a developed country multinational enterprises (DMNE) perceives and manages political risks when…

9940

Abstract

Purpose

This study investigates an under-researched yet fundamental question of how a developed country multinational enterprises (DMNE) perceives and manages political risks when undertaking infrastructure projects in the emerging markets (EMs).

Design/methodology/approach

The authors use an abduction-based qualitative research approach to analyze six international project operations of a multinational enterprise originating from Finland in five EMs.

Findings

The findings suggest that the overall nature of political risks in EMs is not the same, except few political risk factors that are visible in most EMs. Consequently, the applied risk management mechanisms vary between EMs, except with few common mechanisms. The authors develop an integrative analytical framework of political risk management based on the findings.

Originality/value

This paper is one of the first studies to identify political risk factors for western MNEs while undertaking international project operations and link them to reduction mechanisms used by them. The authors go beyond the notion of risk being conceptualized at a general level and evaluate 20 specific political risk factors referred to in extant literature. The authors further link these political risk factors with both social exchange and transaction cost theories conceptually as well as empirically. Finally, the authors develop a relatively comprehensive analytical framework of political risk management based on the case projects' findings that combine several strands of literature, including the social exchange theory, transaction cost theory, international market entry, project management and finance literature streams.

Details

International Marketing Review, vol. 38 no. 6
Type: Research Article
ISSN: 0265-1335

Keywords

Open Access
Article
Publication date: 16 February 2021

Priscila Ferreira de Araújo Lima, Sara Marcelino-Sadaba and Chiara Verbano

Despite the emergence and strategic importance of project risk management (PRM), its diffusion is limited mainly to large companies, leaving a lack of empirical evidence…

22701

Abstract

Purpose

Despite the emergence and strategic importance of project risk management (PRM), its diffusion is limited mainly to large companies, leaving a lack of empirical evidence addressing SMEs. Given the socio-economic importance of SMEs and their need to manage risks to ensure the success of their strategic and innovative projects, this research aims to investigate how to adopt PRM in SMEs with a positive cost–benefit ratio.

Design/methodology/approach

This study presents an exploratory and explanatory research conducted through multiple-case studies involving 10 projects performed in Spanish and Italian small and medium-sized enterprises (SMEs).

Findings

The results obtained highlight how project features (commitment type, innovativeness, strategic relevance and managerial complexity) and firms' characteristics (sector of activity, production system and access to public incentives) influence PRM adoption, leading to different levels and types of benefits.

Originality/value

The paper offers practical indications about PRM phases, activities, tools and organizational aspects to be considered in different contexts to ensure the project's success and, ultimately, the company's growth and sustainability. Such indications could not be found in the literature.

Details

International Journal of Managing Projects in Business, vol. 14 no. 4
Type: Research Article
ISSN: 1753-8378

Keywords

Open Access
Article
Publication date: 25 March 2024

Roope Nyqvist, Antti Peltokorpi and Olli Seppänen

The objective of this research is to investigate the capabilities of the ChatGPT GPT-4 model, a form of artificial intelligence (AI), in comparison to human experts in the context…

1253

Abstract

Purpose

The objective of this research is to investigate the capabilities of the ChatGPT GPT-4 model, a form of artificial intelligence (AI), in comparison to human experts in the context of construction project risk management.

Design/methodology/approach

Employing a mixed-methods approach, the study draws a qualitative and quantitative comparison between 16 human risk management experts from Finnish construction companies and the ChatGPT AI model utilizing anonymous peer reviews. It focuses primarily on the areas of risk identification, analysis, and control.

Findings

ChatGPT has demonstrated a superior ability to generate comprehensive risk management plans, with its quantitative scores significantly surpassing the human average. Nonetheless, the AI model's strategies are found to lack practicality and specificity, areas where human expertise excels.

Originality/value

This study marks a significant advancement in construction project risk management research by conducting a pioneering blind-review study that assesses the capabilities of the advanced AI model, GPT-4, against those of human experts. Emphasizing the evolution from earlier GPT models, this research not only underscores the innovative application of ChatGPT-4 but also the critical role of anonymized peer evaluations in enhancing the objectivity of findings. It illuminates the synergistic potential of AI and human expertise, advocating for a collaborative model where AI serves as an augmentative tool, thereby optimizing human performance in identifying and managing risks.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 13
Type: Research Article
ISSN: 0969-9988

Keywords

Open Access
Article
Publication date: 27 April 2022

Marco Greco, Serena Strazzullo, Livio Cricelli, Michele Grimaldi and Benito Mignacca

Despite the multiple calls for research on the dark side of open innovation, very few studies have approached the topic so far. This study aims to analyse successful and…

2889

Abstract

Purpose

Despite the multiple calls for research on the dark side of open innovation, very few studies have approached the topic so far. This study aims to analyse successful and unsuccessful open innovation projects.

Design/methodology/approach

This study uses thematic analysis to describe the factors determining their (un)success. The researchers interviewed 27 managers and owners in the manufacturing sector. Then, the respondents were asked to discuss one successful and one unsuccessful open innovation project to explore the differences in triggers and setbacks, focusing on the causes that determined the failures.

Findings

Findings show that many interviewees are reluctant to identify failure cases, which somewhat explains the paucity of studies on the topic, and others do so when the failure is recognised by a third party (such as a public institution not granting funds to the project). This study discussed how this phenomenon is linked with the paradoxical relation between innovation success and failure. It is also found that triggers and setbacks determining the project's (un)success are markedly differently based on the technological intensity of the firm. Implications for scholars and practitioners are also drawn.

Originality/value

This study provides a balanced view between open innovation successes and failures to offer informative recommendations to practitioners. Furthermore, it contributes to filling the scarcity of studies related to risks and failures of open innovation projects. This gap has been addressed by studying the factors that determine the success and unsuccess of an open innovation project.

Details

European Journal of Innovation Management, vol. 25 no. 6
Type: Research Article
ISSN: 1460-1060

Keywords

1 – 10 of over 6000