1 – 10 of 10Anna-Therése Järvenpää, Johan Larsson and Per Erik Eriksson
This paper aims to identify how a public client’s use of control systems (process, output and social control) affect innovation possibilities in construction projects.
Abstract
Purpose
This paper aims to identify how a public client’s use of control systems (process, output and social control) affect innovation possibilities in construction projects.
Design/methodology/approach
Semi-structured interviews about six infrastructure projects were conducted to identify respondents’ views on innovation possibilities. These possibilities were then analyzed from an organizational control perspective within principal–agent relationships between the Swedish Transport Administration (STA) and their contractors.
Findings
How the client uses control systems affects innovation possibilities. Relying on process control could negatively affect innovation opportunities, whereas output control could have a positive influence. In addition, social control seems to have a weak effect, as the STA appears not to use social control to facilitate joint innovation. Public clients must comply with the Public Procurement Act and, therefore, retain the requirements specified in the tendering documents. Much of the steering of the execution is connected to the ex ante phase (before signing the contract), which affects innovation possibilities in the design and execution phases for the contractor.
Research limitations/implications
This study was conducted with only one client, thus limiting its generalizability. However, the findings provide an important stepping stone to further investigation into balancing control systems and creating innovation possibilities in a principal–agent relationship.
Originality/value
Although public procurement has increasingly been emphasized as a major potential source of innovation, studying how a public client’s use of organizational control systems affects innovation possibilities in the construction sector has received scant attention.
Details
Keywords
Jacob Guerrero and Susanne Engström
By adopting the “hard” and “soft” project management (PM) approaches from the PM-literature, this paper aims to problematize the expected role of client organizations in driving…
Abstract
Purpose
By adopting the “hard” and “soft” project management (PM) approaches from the PM-literature, this paper aims to problematize the expected role of client organizations in driving innovation in the transport infrastructure sector.
Design/methodology/approach
Addressing a large public client in Sweden, a case study design was initially applied to provide in-depth insights and perspectives of client project managers’ views and experiences of managing projects expected to drive innovation. In this paper, the concepts of “hard” and “soft” are used to discuss empirical findings on challenges associated with adopting a PM-approach for driving innovation in projects. The empirical material consists of interview data, complemented with observations and archival data.
Findings
Findings reveal challenges associated with combining hard and soft approaches, frequently demonstrating difficulties in balancing short-term project expectations with the promotion of innovation. In line with the literature, project managers note that there is a need for soft approaches to promote development and drive innovation. Yet, findings reflect a situation in which operational success criteria predominate, whereas soft approaches are not sufficiently used to create the grounds required for fostering innovation.
Originality/value
Insights are provided into how PM-approaches may impact construction innovation in the infrastructure sector, demonstrating a need for further research on the challenges and implications of applying and combining hard and soft PM-approaches.
Details
Keywords
Kai Hänninen, Jouni Juntunen and Harri Haapasalo
The purpose of this study is to describe latent classes explaining the innovation logic in the Finnish construction companies. Innovativeness is a driver of competitive…
Abstract
Purpose
The purpose of this study is to describe latent classes explaining the innovation logic in the Finnish construction companies. Innovativeness is a driver of competitive performance and vital to the long-term success of any organisation and company.
Design/methodology/approach
Using finite mixture structural equation modelling (FMSEM), the authors have classified innovation logic into latent classes. The method analyses and recognises classes for companies that have similar logic in innovation activities based on the collected data.
Findings
Through FMSEM analysis, the authors have identified three latent classes that explain the innovation logic in the Finnish construction companies – LC1: the internal innovators; LC2: the non-innovation-oriented introverts; and LC3: the innovation-oriented extroverts. These three latent classes clearly capture the perceptions within the industry as well as the different characteristics and variables.
Research limitations/implications
The presented latent classes explain innovation logic but is limited to analysing Finnish companies. Also, the research is quantitative by nature and does not increase the understanding in the same manner as qualitative research might capture on more specific aspects.
Practical implications
This paper presents starting points for construction industry companies to intensify innovation activities. It may also indicate more fundamental changes for the structure of construction industry organisations, especially by enabling innovation friendly culture.
Originality/value
This study describes innovation logic in Finnish construction companies through three models (LC1–LC3) by using quantitative data analysed with the FMSEM method. The fundamental innovation challenges in the Finnish construction companies are clarified via the identified latent classes.
Details
Keywords
Caroline Ingvarsson, Anette Hallin and Christof Kier
The purpose of this paper is to explore how gamification may be used for project stakeholder engagement.
Abstract
Purpose
The purpose of this paper is to explore how gamification may be used for project stakeholder engagement.
Design/methodology/approach
The paper presents the results of a systematic literature review of extant research concerning the gamification of projects. Based on this, an agenda for future studies is outlined.
Findings
Extant research on the gamification of projects is scarce and scattered among various disciplines, but the engineering fields dominate. The research performed does indicate that gamification may be used for involving stakeholders in projects, primarily by promoting learning, but also by engaging them, motivating action and solving problems.
Research limitations/implications
In several cases, extant research display poor quality in research design and a lack in cross-disciplinary perspectives, which means that more research is needed. The users’ perspective is often lacking. Furthermore, the ideas gamification might be “hidden” within other technologies.
Practical implications
The findings of this research may assist project management practitioners in the endeavor of adopting gamification principles to better involve stakeholders.
Originality/value
The study fills a gap in summarizing the research on how gamification may be used to promote project stakeholder engagement. Based on this, it proposes a research agenda for future research on the use of gamification to promote project stakeholder engagement.
Details
Keywords
Vartenie Aramali, George Edward Gibson, Hala Sanboskani and Mounir El Asmar
Earned value management systems (EVMS), also called integrated project and program management systems, have been greatly examined in the literature, which has typically focused on…
Abstract
Purpose
Earned value management systems (EVMS), also called integrated project and program management systems, have been greatly examined in the literature, which has typically focused on their technical aspects rather than social. This study aims to hypothesize that improving both the technical maturity of EVMS and the social environment elements of EVMS applications together will significantly impact project performance outcomes. For the first time, empirical evidence supports a strong relationship between EVMS maturity and environment.
Design/methodology/approach
Data was collected from 35 projects through four workshops, attended by 31 industry practitioners with an average of 19 years of EVMS experience. These experts, representing 23 organizations, provided over 2,800 data points on sociotechnical integration and performance outcomes, covering projects totaling $21.8 billion. Statistical analyses were performed to derive findings on the impact of technical maturity and social environment on project success.
Findings
The results show statistically significant differences in cost growth, compliance, meeting project objectives and business drivers and customer satisfaction, between projects with high EVMS maturity and environment and projects with poor EVMS maturity and environment. Moreover, the technical and social dimensions were found to be significantly correlated.
Originality/value
Key contributions include a novel and tested performance-driven framework to support integrated project management using EVMS. The adoption of this detailed assessment framework by government and industry is driving a paradigm shift in project management of some of the largest and most complex projects in the U.S.; specifically transitioning from a project assessment based upon a binary approach for EVMS technical maturity (i.e. compliant/noncompliant to standards) to a wide-ranging scale (i.e. 0–1,000) across two dimensions.
Details
Keywords
Gunilla Carlsson, Oskar Jonsson, Stefan Olander, Marianne Salén, Eva Månsson Lexell and Björn Slaug
This study aims to explore how an accessibility database (AD) has been developed and implemented as a tool for facility managers to evaluate and increase the accessibility of…
Abstract
Purpose
This study aims to explore how an accessibility database (AD) has been developed and implemented as a tool for facility managers to evaluate and increase the accessibility of public facilities.
Design/methodology/approach
Eight participants were strategically sampled for semi-structured interviews, and documents on the AD were gathered. The Consolidated Framework for Implementation Research (CFIR) was used for a directed content analysis of the data. The CFIR domains used for the analysis were: intervention characteristics, outer setting, inner setting, characteristics of individuals and process.
Findings
The development and implementation of the AD demonstrated the complexity in assessing and planning for increased accessibility. The communication and iterative processes within the inner as well as with the outer setting was an important part of the development and implementation, as well as anchoring each step locally, regionally and nationally, within public authorities and disability organizations.
Practical implications
The assessments of environmental barriers and the results reported in the AD can serve as a guide for identification of accessibility issues. However, singular identified barriers were reported as a fragmentation of the building regulations, and thereby when retrofitting is carried out, experts who have the competence to suggest solutions based on the entirety need to be involved to reach the goals of increased accessibility and countering of exclusion and discrimination.
Originality/value
By structuring the implementation process by means of the CFIR, facilitators and barriers of using an AD as a basis for retrofitting were revealed. The practical challenges outlined in assessing and increasing accessibility can guide facility managers when considering actions to increase accessibility.
Details
Keywords
Emmanuel Dele Omopariola, Abimbola Olukemi Windapo, David John Edwards, Clinton Ohis Aigbavboa, Sunday Ukwe-Nya Yakubu and Onimisi Obari
Previous studies have postulated that an advance payment system (APS) positively impacts the contractor's working capital and is paramount to ensuring an efficient and effective…
Abstract
Purpose
Previous studies have postulated that an advance payment system (APS) positively impacts the contractor's working capital and is paramount to ensuring an efficient and effective project cash flow process. However, scant research has been undertaken to empirically establish the cash flow performance and domino effect of APS on project and organisational performance.
Design/methodology/approach
The epistemological design adopted a positivist philosophical stance augmented by deductive reasoning to explore the phenomena under investigation. Primary quantitative data were collected from 504 Construction Industry Development Board (CIDB) registered contractors (within the grade bandings 1–9) in South Africa. A five-point Likert scale was utilised, and subsequent data accrued were analysed using structural equation modelling (SEM).
Findings
Emergent findings reveal that the mandatory use of an APS does not guarantee a positive project cash flow, an improvement in organisational performance or an improvement in project performance.
Practical implications
The ensuing discussion reveals the contributory influence of APS on positive cash flow and organisational performance, although APS implementation alone will not achieve these objectives. Practically, the research accentuates the need for various measures to be concurrently adopted (including APS) towards ensuring a positive project cash flow and improved organisational and project performance.
Originality/value
There is limited empirical research on cash flow performance and the domino effect of APS on project and organisational performance in South Africa, nor indeed, the wider geographical location of Africa as a continent. This study addresses this gap in the prevailing body of knowledge.
Details
Keywords
Solmaz Mansoori, Janne Harkonen and Harri Haapasalo
This study aims to facilitate consistency of information in building information modelling (BIM) and address the current BIM gaps through the perspectives of the productization…
Abstract
Purpose
This study aims to facilitate consistency of information in building information modelling (BIM) and address the current BIM gaps through the perspectives of the productization concept and product structure (PS).
Design/methodology/approach
The study follows a conceptual research approach in conjunction with a single case study. First, the previous studies on BIM implementation, productization and PS are reviewed. Further, a case study is used to analyse the current state of productization in the construction sector and develop a functional PS for construction.
Findings
A Part-Phase-Elements Matrix is proposed as a construction-specific PS to facilitate consistency in information and to enhance BIM. The proposed matrix provides new avenues to facilitate consistent information exchange through the interconnection between conceptual PS and standard building objects library, and encourage collaborative communication between stakeholders.
Originality/value
This study explores the core of the productization concept and PS as means to facilitate consistency of information and thus address the current gaps in BIM. This as building projects progressively move towards systematic modular and prefabricated construction where the flow of reliable information about product and construction offerings becomes increasingly important.
Details
Keywords
Sahar Jawad, Ann Ledwith and Rashid Khan
There is growing recognition that effective project control systems (PCS) are critical to the success of projects. The relationship between the individual elements of PCS and…
Abstract
Purpose
There is growing recognition that effective project control systems (PCS) are critical to the success of projects. The relationship between the individual elements of PCS and successfully achieving project objectives has yet to be explored. This research investigates the enablers and barriers that influence the elements of PCS success and drive project objectives.
Design/methodology/approach
This study adopts a mixed approach of descriptive analysis and regression models to explore the impact of six PCS elements on project outcomes. Petroleum and chemical projects in Saudi Arabia were selected as a case study to validate the research model.
Findings
Data from a survey of 400 project managers in Saudi’s petroleum and chemical industry reveal that successful PCS are the key to achieving all project outcomes, but they are particularly critical for meeting project cost objectives. Project Governance was identified as the most important of the six PCS elements for meeting project objectives. A lack of standard processes emerged as the most significant barrier to achieving effective project governance, while having skilled and experienced project team members was the most significant enabler for implementing earned value.
Practical implications
The study offers a direction for implementing and developing PCS as a strategic tool and focuses on the PCS elements that can improve project outcomes.
Originality/value
This research contributes to project management knowledge and differs from previous attempts in two ways. Firstly, it investigates the elements of PCS that are critical to achieving project scope, schedule and cost objectives; secondly, enablers and barriers of PCS success are examined to see how they influence each element independently.