To read this content please select one of the options below:

Investigating the causes of construction delay on the perspective of organization-sectors involved in the construction industry of Bangladesh

Mohammad Nafe Assafi (Graduate, Department of Building Engineering and Construction Management, Khulna University of Engineering and Technology, Khulna, Bangladesh)
Md. Ikramul Hoque (Department of Building Engineering and Construction Management, Khulna University of Engineering and Technology, Khulna, Bangladesh)
Md. Mehrab Hossain (Department of Building Engineering and Construction Management, Khulna University of Engineering and Technology, Khulna, Bangladesh)

International Journal of Building Pathology and Adaptation

ISSN: 2398-4708

Article publication date: 12 April 2022

536

Abstract

Purpose

Construction delay always causes massive damage to the advancing construction industries, which is no different in the case of Bangladeshi construction industries. This paper aims to investigate the major delay factors causing construction delays in public-funded, mixed and private-funded construction projects of Bangladesh. Also, it offers preventive suggestions from expert stakeholders to reduce the recurrence of delays.

Design/methodology/approach

At first, an extensive literature review was conducted to identify the thirty-seven major delay factors categorized under seven groups. A questionnaire was then developed for survey at ongoing construction projects at a different division of Bangladesh. Next, data from 110 respondents were collected, and the delay factors were ranked based on the Relative Importance Index (RII); lastly, probable solutions were suggested for top-ranked delay factors based on opinions from expert stakeholders in the construction sector of Bangladesh.

Findings

The overall RII ranking of the 37 delay factors showed “Construction mistakes and defective work,” “Contract modifications by the client” and “Adverse weather condition” as the top three factors causing the delay. For public-funded projects, “Construction mistakes and defective work” and “Slow decision making by a consultant” are the top delay factors. For mixed projects, “Slow decision making of the client” and “Construction mistakes and defective work ranked top, and for private-funded projects, “Financial problems and payment delay of the client” and “Adverse weather condition” ranked top. These nuances of ranking in individual project types ascertain that the causes of delay vary in terms of project features.

Practical implications

The outcome of this project will help identify the significant delay factors based on their severity of effectiveness associated with public-funded, mixed and private-funded projects in Bangladesh. The suggestions regarding preventing these delay factors obtained through the opinions of expert stakeholders can help reduce the effect of these delays in the context of Bangladesh and in countries where the similarity in construction environment prevails.

Originality/value

Previously, studies on construction delays in Bangladesh focused mainly on identifying the delays using qualitative analysis techniques. This study is based on a unique methodology of integrating quantitative research on delay factor identification and qualitative research on preventive measures following the opinions gathered from expert stakeholders in the construction sector.

Keywords

Acknowledgements

The authors would like to convey their gratitude to the Department of Building Engineering and Construction Management, Khulna University of Engineering and Technology for the allocation of stipend during undergraduate thesis which was used to fund this project and to all the people affiliated with the construction sector of Bangladesh who helped in terms of gathering information used in this study.

Citation

Nafe Assafi, M., Hoque, M.I. and Hossain, M.M. (2022), "Investigating the causes of construction delay on the perspective of organization-sectors involved in the construction industry of Bangladesh", International Journal of Building Pathology and Adaptation, Vol. ahead-of-print No. ahead-of-print. https://doi.org/10.1108/IJBPA-10-2021-0137

Publisher

:

Emerald Publishing Limited

Copyright © 2022, Emerald Publishing Limited

Related articles