Publication date: 27 February 2024

Vartenie Aramali, George Edward Gibson, Hala Sanboskani and Mounir El Asmar

Earned value management systems (EVMS), also called integrated project and program management systems, have been greatly examined in the literature, which has typically focused on…

Abstract

Purpose

Earned value management systems (EVMS), also called integrated project and program management systems, have been greatly examined in the literature, which has typically focused on their technical aspects rather than social. This study aims to hypothesize that improving both the technical maturity of EVMS and the social environment elements of EVMS applications together will significantly impact project performance outcomes. For the first time, empirical evidence supports a strong relationship between EVMS maturity and environment.

Design/methodology/approach

Data was collected from 35 projects through four workshops, attended by 31 industry practitioners with an average of 19 years of EVMS experience. These experts, representing 23 organizations, provided over 2,800 data points on sociotechnical integration and performance outcomes, covering projects totaling $21.8 billion. Statistical analyses were performed to derive findings on the impact of technical maturity and social environment on project success.

Findings

The results show statistically significant differences in cost growth, compliance, meeting project objectives and business drivers and customer satisfaction, between projects with high EVMS maturity and environment and projects with poor EVMS maturity and environment. Moreover, the technical and social dimensions were found to be significantly correlated.

Originality/value

Key contributions include a novel and tested performance-driven framework to support integrated project management using EVMS. The adoption of this detailed assessment framework by government and industry is driving a paradigm shift in project management of some of the largest and most complex projects in the U.S.; specifically transitioning from a project assessment based upon a binary approach for EVMS technical maturity (i.e. compliant/noncompliant to standards) to a wide-ranging scale (i.e. 0–1,000) across two dimensions.

Details

International Journal of Managing Projects in Business, vol. 17 no. 8
Type: Research Article
ISSN: 1753-8378

Keywords

Open Access
Article
Publication date: 25 March 2024

Roope Nyqvist, Antti Peltokorpi and Olli Seppänen

The objective of this research is to investigate the capabilities of the ChatGPT GPT-4 model, a form of artificial intelligence (AI), in comparison to human experts in the context…

1253

Abstract

Purpose

The objective of this research is to investigate the capabilities of the ChatGPT GPT-4 model, a form of artificial intelligence (AI), in comparison to human experts in the context of construction project risk management.

Design/methodology/approach

Employing a mixed-methods approach, the study draws a qualitative and quantitative comparison between 16 human risk management experts from Finnish construction companies and the ChatGPT AI model utilizing anonymous peer reviews. It focuses primarily on the areas of risk identification, analysis, and control.

Findings

ChatGPT has demonstrated a superior ability to generate comprehensive risk management plans, with its quantitative scores significantly surpassing the human average. Nonetheless, the AI model's strategies are found to lack practicality and specificity, areas where human expertise excels.

Originality/value

This study marks a significant advancement in construction project risk management research by conducting a pioneering blind-review study that assesses the capabilities of the advanced AI model, GPT-4, against those of human experts. Emphasizing the evolution from earlier GPT models, this research not only underscores the innovative application of ChatGPT-4 but also the critical role of anonymized peer evaluations in enhancing the objectivity of findings. It illuminates the synergistic potential of AI and human expertise, advocating for a collaborative model where AI serves as an augmentative tool, thereby optimizing human performance in identifying and managing risks.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 13
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 23 October 2023

Mariam Bader, Jiju Antony, Raja Jayaraman, Vikas Swarnakar, Ravindra S. Goonetilleke, Maher Maalouf, Jose Arturo Garza-Reyes and Kevin Linderman

The purpose of this study is to examine the critical failure factors (CFFs) linked to various types of process improvement (PI) projects such as Kaizen, Lean, Six Sigma, Lean Six…

Abstract

Purpose

The purpose of this study is to examine the critical failure factors (CFFs) linked to various types of process improvement (PI) projects such as Kaizen, Lean, Six Sigma, Lean Six Sigma and Agile. Proposing a mitigation framework accordingly is also an aim of this study.

Design/methodology/approach

This research undertakes a systematic literature review of 49 papers that were relevant to the scope of the study and that were published in four prominent databases, including Google Scholar, Scopus, Web of Science and EBSCO.

Findings

Further analysis identifies 39 factors that contribute to the failure of PI projects. Among these factors, significant emphasis is placed on issues such as “resistance to cultural change,” “insufficient support from top management,” “inadequate training and education,” “poor communication” and “lack of resources,” as primary causes of PI project failures. To address and overcome the PI project failures, the authors propose a framework for failure mitigation based on change management models. The authors present future research directions that aim to enhance both the theoretical understanding and practical aspects of PI project failures.

Practical implications

Through this study, researchers and project managers can benefit from well-structured guidelines and invaluable insights that will help them identify and address potential failures, leading to successful implementation and sustainable improvements within organizations.

Originality/value

To the best of the author’s knowledge, this paper is the first study of its kind to examine the CFFs of five PI methodologies and introduces a novel approach derived from change management theory as a solution to minimize the risk associated with PI failure.

Details

International Journal of Lean Six Sigma, vol. 15 no. 3
Type: Research Article
ISSN: 2040-4166

Keywords

Article
Publication date: 27 November 2023

Li Ma and Yongqiang Lu

The purpose of this study is to examine how construction project managers’ conflict management styles (CMSs) affect project team resilience from the perspective of social identity…

Abstract

Purpose

The purpose of this study is to examine how construction project managers’ conflict management styles (CMSs) affect project team resilience from the perspective of social identity theory.

Design/methodology/approach

This study adopted a cross-sectional survey design and collected paired data from 110 construction project managers and 474 employees in China. Based on the data collected, the authors tested the proposed hypotheses using hierarchical regression analysis.

Findings

The results show that a project manager’s cooperative CMS positively affects team resilience, and a project manager’s competitive and avoidant CMS negatively affects team resilience. Team followership plays a mediating role in this relationship. The team power distance moderates the effects of a project manager’s cooperative and avoidant CMSs on team followership.

Originality/value

This paper enriches the existing literature on conflict management in construction projects and have potential guiding significance and application value for team resilience management practices.

Details

International Journal of Conflict Management, vol. 35 no. 3
Type: Research Article
ISSN: 1044-4068

Keywords

Article
Publication date: 13 October 2023

Eduardo André Cândido Da Silva, Flávio Santino Bizarrias, Renato Penha, Luciano Ferreira da Silva and Cristiane Drebes Pedron

Despite the significant interest from researchers and practitioners, the literature on project value measurement from the perspective of the customer is non-existent. This study…

Abstract

Purpose

Despite the significant interest from researchers and practitioners, the literature on project value measurement from the perspective of the customer is non-existent. This study aims to address this gap by developing and validating a scale to measure project value through a customer lens called the customer perception of project value scale.

Design/methodology/approach

A list of items was initially generated based on 762 sample responses through a systematic review of the literature and with the participation of specialists. Exploratory and confirmatory factorial analyses and structural equation modelling were used to develop and validate the scale.

Findings

The authors formulated a four-dimension scale. The dimensions used to measure the second-order construct are customer centrality, process, delivery and cost-benefit. This was validated using a nomological structure.

Research limitations/implications

The non-consensual nature of what is value in projects restricts the results of this study to the context of a specific group of stakeholders only, that is, the consumers of the projects. The authors also see limitations in the absence of competing scales, which do not allow the comparison of the instrument with alternative measures.

Practical implications

This study allows project managers and other professionals to measure a project’s perceived value from the customer’s point of view and manage the improvement of this perception.

Originality/value

To the best of the authors’ knowledge, this is the first study to propose a scale to measure project value, which advances the literature on project management and value and contributes to academic knowledge and practice by measuring project value from the customer standpoint.

Details

European Business Review, vol. 36 no. 3
Type: Research Article
ISSN: 0955-534X

Keywords

Article
Publication date: 23 January 2023

Amir Naser Ghanbaripour, Craig Langston, Roksana Jahan Tumpa and Greg Skulmoski

Despite considerable research on the subject, there is still some misunderstanding about what characterizes successful project delivery in construction projects. Evaluating…

466

Abstract

Purpose

Despite considerable research on the subject, there is still some misunderstanding about what characterizes successful project delivery in construction projects. Evaluating project delivery success is crucial for organizations since it enables them to prepare for future growth through more effective project management mechanisms and rank the organization's projects for continuous improvement. There is considerable disagreement over a set of success criteria that can be applied to all kinds of projects when evaluating project delivery success, making it a complicated procedure for practitioners and scholars. This research seeks to alleviate the problem by validating and testing a systematic project delivery success model (3D integration model) in the Australian construction industry. The aim is to establish a dependable approach built upon prior research and reliable in evaluating delivery success for any project type.

Design/methodology/approach

Based on a novel project delivery success model, this research applies a case study methodology to analyse 40 construction projects undertaken by a single Australian project management consultancy. The research utilizes a mixed-method research approach and triangulates three sets of data. First, the project delivery success (PDS) scores of the projects are calculated by the model. Second, a qualitative analysis targeting the performance of the same projects using a different system called the performance assessment review (PAR) scores was obtained. These culminate in two sets of ranking. The third step seeks validation of results from the head of the partnering organization that has undertaken the projects.

Findings

The findings of this study indicate that the 3D integration model is accurate and reliable in measuring the success of project delivery in construction projects of various sizes, locations and durations. While the model uses six key performance indicators (KPIs) to measure delivery success, it is evident that three of these may significantly improve the likelihood of PDS: value, speed and impact. Project managers should focus on these priority aspects of performance to generate better results.

Research limitations/implications

Restrictions inherent to the case study approach are identified for this mixed-method multiple-case study research. There is a limitation on the sample size in this study. Despite the researcher's best efforts, no other firm was willing to share such essential data; therefore, only 40 case studies could be analysed. Nonetheless, the number of case studies met the literature's requirements for adequate units for multiple-case research. This research only looked at Australian construction projects. Thus, the conclusions may not seem applicable to other countries or industries. The authors investigated testing the PDS in the construction sector. It can assist in improving efficiency and resource optimization in this area. Nonetheless, the same technique may be used to analyse and rank the success of non-construction projects.

Originality/value

Despite the research conducted previously on the PDS of construction projects, there is still confusion among researchers and practitioners about what constitutes a successful project delivery. Although several studies have attempted to address this confusion, no consensus on consistent performance metrics or a practical project success model has been formed. More importantly, (1) the ability to measure success across multiple project types, (2) the use of triple bottom line (TBL) to incorporate sustainability in evaluating delivery success and (3) the use of a complexity measurement tool to adjust delivery success scores set the 3D integration model apart from others.

Details

Smart and Sustainable Built Environment, vol. 13 no. 3
Type: Research Article
ISSN: 2046-6099

Keywords

Open Access
Article
Publication date: 31 May 2022

Kari-Pekka Tampio and Harri Haapasalo

The purpose of this paper is to identify the areas and logic of integration of different stakeholders using different methods and to analyse their applicability and challenges in…

1056

Abstract

Purpose

The purpose of this paper is to identify the areas and logic of integration of different stakeholders using different methods and to analyse their applicability and challenges in practical projects. The main aim is to describe how these different methods impact value creation.

Design/methodology/approach

Action design research was carried out in a large hospital construction project where the first author acted as an “involved researcher” and the second author acted as an “outside researcher”. Two workshops were organised to evaluate the direct and indirect challenges and benefits of the applied four methods and to explain how different methods enable value creation.

Findings

All the studied methods provide good results in terms of usability and commitment to the aims of the project, thus delivering the direct benefits expected. Process, people and tools logic works well in this case project when applying the methods properly. Significant evidence was provided on secondary deliverables of the methods, and all analysed methods had a significant impact in the area of leading people, clarifying what “focus on people” means and how it is enabled.

Practical implications

Focus on people can be achieved through different operative methods if applied in the right way. It is necessary to select the most suitable methods based on all the direct and indirect deliverables.

Originality/value

This case project offered a platform to analyse integration methods in a real-life project using the collaborative contract method. The authors were able to participate in the analysis by taking action from the very beginning of the project in terms of training, learning, continuous development and coaching of these methods and evaluating the applicability.

Details

Construction Innovation , vol. 24 no. 7
Type: Research Article
ISSN: 1471-4175

Keywords

Open Access
Article
Publication date: 3 March 2023

Amy B.C. Tan, Desirée H. van Dun and Celeste P.M. Wilderom

With the growing need for employees to be innovative, public-sector organizations are investing in employee training. This study aims to examine the effects of a combined Lean Six…

4416

Abstract

Purpose

With the growing need for employees to be innovative, public-sector organizations are investing in employee training. This study aims to examine the effects of a combined Lean Six Sigma and innovation training, using action learning, on public-sector employees’ creative role identity and innovative work behavior.

Design/methodology/approach

The authors studied a public service agency in Singapore in which a five-day Lean Innovation Training was implemented, using a combination of Lean Six Sigma and Creative Problem-Solving tools, with a simulation on day one and subsequent team-based project coaching, spread over six months. The authors administered pre- and postintervention surveys among all the employees, and initiated group interviews and observations before, during and after the intervention.

Findings

Creative role identity and innovative work behavior had significantly improved six months after the intervention, enabled through senior management’s transformational leadership. The training induced managers to role-model innovative work behaviors while cocreating, with their employees, a renewal of their agency’s core processes. The three completed improvement projects contributed to an innovative work culture and reduced service turnaround time.

Originality/value

Starting with a role-playing simulation on the first day, during which leaders and followers swapped roles, the action-learning type training taught all the organizational members to use various Lean Six Sigma and Creative Problem-Solving tools. This nimble Lean Innovation Training, and subsequent team-based project coaching, exemplifies how advancing the staff’s creative role identity can have a positive impact.

Details

International Journal of Lean Six Sigma, vol. 15 no. 8
Type: Research Article
ISSN: 2040-4166

Keywords

Open Access
Article
Publication date: 1 August 2023

Jacob Guerrero and Susanne Engström

By adopting the “hard” and “soft” project management (PM) approaches from the PM-literature, this paper aims to problematize the expected role of client organizations in driving…

Abstract

Purpose

By adopting the “hard” and “soft” project management (PM) approaches from the PM-literature, this paper aims to problematize the expected role of client organizations in driving innovation in the transport infrastructure sector.

Design/methodology/approach

Addressing a large public client in Sweden, a case study design was initially applied to provide in-depth insights and perspectives of client project managers’ views and experiences of managing projects expected to drive innovation. In this paper, the concepts of “hard” and “soft” are used to discuss empirical findings on challenges associated with adopting a PM-approach for driving innovation in projects. The empirical material consists of interview data, complemented with observations and archival data.

Findings

Findings reveal challenges associated with combining hard and soft approaches, frequently demonstrating difficulties in balancing short-term project expectations with the promotion of innovation. In line with the literature, project managers note that there is a need for soft approaches to promote development and drive innovation. Yet, findings reflect a situation in which operational success criteria predominate, whereas soft approaches are not sufficiently used to create the grounds required for fostering innovation.

Originality/value

Insights are provided into how PM-approaches may impact construction innovation in the infrastructure sector, demonstrating a need for further research on the challenges and implications of applying and combining hard and soft PM-approaches.

Details

Construction Innovation , vol. 24 no. 7
Type: Research Article
ISSN: 1471-4175

Keywords

Open Access
Article
Publication date: 28 June 2022

Sahar Jawad, Ann Ledwith and Rashid Khan

There is growing recognition that effective project control systems (PCS) are critical to the success of projects. The relationship between the individual elements of PCS and…

1628

Abstract

Purpose

There is growing recognition that effective project control systems (PCS) are critical to the success of projects. The relationship between the individual elements of PCS and successfully achieving project objectives has yet to be explored. This research investigates the enablers and barriers that influence the elements of PCS success and drive project objectives.

Design/methodology/approach

This study adopts a mixed approach of descriptive analysis and regression models to explore the impact of six PCS elements on project outcomes. Petroleum and chemical projects in Saudi Arabia were selected as a case study to validate the research model.

Findings

Data from a survey of 400 project managers in Saudi’s petroleum and chemical industry reveal that successful PCS are the key to achieving all project outcomes, but they are particularly critical for meeting project cost objectives. Project Governance was identified as the most important of the six PCS elements for meeting project objectives. A lack of standard processes emerged as the most significant barrier to achieving effective project governance, while having skilled and experienced project team members was the most significant enabler for implementing earned value.

Practical implications

The study offers a direction for implementing and developing PCS as a strategic tool and focuses on the PCS elements that can improve project outcomes.

Originality/value

This research contributes to project management knowledge and differs from previous attempts in two ways. Firstly, it investigates the elements of PCS that are critical to achieving project scope, schedule and cost objectives; secondly, enablers and barriers of PCS success are examined to see how they influence each element independently.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 13
Type: Research Article
ISSN: 0969-9988

Keywords