Nathaniel Ayinde Olatunde, Imoleayo Abraham Awodele and Henry Agboola Odeyinka

The purpose of the study is to examine the stakeholder identification (SI) methods used in building projects procured by private corporate organisations in Southwestern Nigeria to…

4624

Abstract

Purpose

The purpose of the study is to examine the stakeholder identification (SI) methods used in building projects procured by private corporate organisations in Southwestern Nigeria to draw a correlation between methods used for SI and project performance in the study area, thereby enhancing project performance.

Design/methodology/approach

The study used a census survey to purposively select 30 projects managers (who indicated from a first-stage questionnaire) that they have participated in structured stakeholder management (SM) from a list of 106 project managers and client representatives who have been involved in SM of building projects procured by private corporate organisations between 2008 and 2017 in the study area. A second-stage questionnaire was designed to elicit information from the respondents. The quantitative data that were collected were analysed using mean score (MS) analysis and Analysis of variance (ANOVA).

Findings

The study found that brainstorming in group meetings (MS = 4.33), interviews with the expert (MS = 3.20) and identification by other stakeholders (MS = 3.00) are the most frequently used SI methods in the study area. It was also found that the use of a questionnaire (MS = 0.87), Delphi method (MS = 0.80) and public hearing (MS = 0.57) was rare for SI in the study area. A further result showed that there was no significant difference in the opinion of project managers on 85% of methods used for SI in the study area irrespective of the procurement method employed.

Practical implications

The study examined the methods project managers used for SI on building projects procured by private corporate organisations to advocate for more robust and all-inclusive SI methods.

Originality/value

The study empirically examined methods used for SI and correlated them to project performance.

Details

Frontiers in Engineering and Built Environment, vol. 1 no. 2
Type: Research Article
ISSN: 2634-2499