Project control and forecast assessment of building projects in Pakistan using earned value management

Hafiz Zahoor (Construction Engineering and Management, National University of Sciences and Technology, Risalpur Campus, Risalpur, Pakistan)
Rashid Mehmood Khan (Management Sciences Department, National University of Modern Languages, Islamabad, Pakistan)
Ahsan Nawaz (Institute of Construction Management, College of Civil Engineering and Architecture, Zhejiang University, Hangzhou, China)
Muhammad Ayaz (Construction Engineering and Management, National University of Sciences and Technology, Risalpur Campus, Risalpur, Pakistan)
Ahsen Maqsoom (Civil Engineering Department, COMSATS University Islamabad, Wah Campus, Islamabad, Pakistan)

Engineering, Construction and Architectural Management

ISSN: 0969-9988

Article publication date: 25 March 2021

Issue publication date: 8 March 2022

730

Abstract

Purpose

Earned Value Management (EVM) is widely used as a project performance measurement and forecasting technique. Nonetheless, it has not been fully explored in Pakistani construction industry; where conventional progress reporting methodology (CPRM) is being followed having certain confines. It reports only the financial progress of a project, expresses feeble association between the duration and cost of activities, and forecasts flawed schedule and completion cost. This research implements EVM on under-construction building projects in Pakistan, and compares its upshots with the projects' actual records and with the outcomes of CPRM.

Design/methodology/approach

To assess the implementation of EVM on building projects, a set of specific criteria was established. Work Breakdown Structure, Organization Breakdown Structure and Control Points were established. The study has compared the EVM metrics with CPRM outcomes on three under-study building projects, and has deliberated on their mutual differences as well as their relationship with actual cost and schedule performance. Monthly figures of actual spending and completed activities were periodically recorded and compared with planned values for status indication. The graphs were generated to observe the correlation between the results of EVM and CPRM. The data was then extrapolated to forecast the schedule and cost values at completion.

Findings

The study discovered that trends of EVM in quantifying the project's cost and schedule performance were strongly correlated and were closer to the actual progress. It has also verified the EVM's soundness in forecasting the cost and schedule, required for project's completion. Contrarily, CPRM metrics could not precisely visualize the current and future, cost and schedule performance.

Originality/value

The case study concludes that EVM's incorporation in progress reporting regime can revolutionize the assessment procedures in Pakistan by rightly indicating the project's current status as well as visualizing the future performance. The study's methodology can also be extrapolated in other countries having similar work environment and economic conditions.

Keywords

Acknowledgements

The authors extend special gratitude to the industrial experts who responded to the data collection and contributed with their valued input. The financial support provided by National University of Sciences and Technology (NUST), Risalpur Campus, Pakistan, is gratefully acknowledged. Lastly, reviewers' support in refining the manuscript through their valuable comments is also appreciated.Conflicts of Interest: The authors declare that they have no conflict of interest in this article.

Citation

Zahoor, H., Khan, R.M., Nawaz, A., Ayaz, M. and Maqsoom, A. (2022), "Project control and forecast assessment of building projects in Pakistan using earned value management", Engineering, Construction and Architectural Management, Vol. 29 No. 2, pp. 842-869. https://doi.org/10.1108/ECAM-11-2020-0989