Dynamic spatial–temporal conflict quantification of construction machinery for pouring blocks in arch dams

Zhipeng Liang (Key Laboratory of Intelligent Health Perception and Ecological Restoration of Rivers and Lakes, Ministry of Education, Hubei University of Technology, Wuhan, China) (School of Civil Engineering, Architecture and Environment, Hubei University of Technology, Wuhan, China)
Chunju Zhao (Key Laboratory of Intelligent Health Perception and Ecological Restoration of Rivers and Lakes, Ministry of Education, Hubei University of Technology, Wuhan, China) (School of Civil Engineering, Architecture and Environment, Hubei University of Technology, Wuhan, China)
Huawei Zhou (Key Laboratory of Intelligent Health Perception and Ecological Restoration of Rivers and Lakes, Ministry of Education, Hubei University of Technology, Wuhan, China) (School of Civil Engineering, Architecture and Environment, Hubei University of Technology, Wuhan, China)
Yihong Zhou (Key Laboratory of Intelligent Health Perception and Ecological Restoration of Rivers and Lakes, Ministry of Education, Hubei University of Technology, Wuhan, China) (School of Civil Engineering, Architecture and Environment, Hubei University of Technology, Wuhan, China)
Quan Liu (School of Water Resources and Hydropower Engineering, Wuhan University, Wuhan, China)
Tao Fang (Sinohydro Bureau 3 Co., Ltd PowerChina, Xian, China)
Fang Wang (Key Laboratory of Intelligent Health Perception and Ecological Restoration of Rivers and Lakes, Ministry of Education, Hubei University of Technology, Wuhan, China) (School of Civil Engineering, Architecture and Environment, Hubei University of Technology, Wuhan, China)

Engineering Computations

ISSN: 0264-4401

Article publication date: 24 September 2024

26

Abstract

Purpose

The spatial–temporal conflicts in the construction process of concrete arch dams are related to the construction quality and duration, especially for pouring blocks with a continuous high-strength and high-density construction process. Furthermore, the complicated construction technology and limited space resources aggravate the spatial–temporal conflicts in the process of space resource allocation and utilization, directly affecting the pouring quality and progress of concrete. To promote the high-strength, quality-preserving and rapid construction of dams and to clarify the explosion moment and influence degree of the spatial–temporal conflicts of construction machinery during the pouring process, a quantification method and algorithm for a “Conflict Bubble” (CB) between construction machines is proposed based on the “Time–Space Microelement” (TSM).

Design/methodology/approach

First, the concept of a CB is proposed, which is defined as the spatial overlap of different entities in the movement process. The subsidiary space of the entity is divided into three layered spaces: the physical space, safe space and efficiency space from the inside to the outside. Second, the processes of “creation,” “transition” and “disappearance” of the CB at different levels with the movement of the entity are defined as the evolution of the spatial–temporal state of the entity. The mapping relationship between the spatial variation and the running time of the layered space during the movement process is defined as “Time–Space” (TS), which is intended to be processed by a microelement.

Findings

The quantification method and algorithm of the CB between construction machinery are proposed based on the TSM, which realizes the quantification of the physical collision accident rate, security risk rate and efficiency loss rate of the construction machinery at any time point or time period. The risk rate of spatial–temporal conflicts in the construction process was calculated, and the outbreak condition of spatial–temporal conflict in the pouring process was simulated and rehearsed. The quantitative calculation results show that the physical collision accident rate, security risk rate and efficiency loss rate of construction machinery at any time point or time period can be quantified.

Originality/value

This study provides theoretical support for the quantitative evaluation and analysis of the spatial–temporal conflict risk in the pouring construction process. It also serves as a reference for the rational organization and scientific decision-making for pouring blocks and provides new ideas and methods for the safe and efficient construction and the scientific and refined management of dams.

Keywords

Acknowledgements

This research work was supported by the Youth Fund project of the National Natural Science Foundation of China (No. 52109157). The authors thank the reviewers and editors for useful comments and suggestions, which assisted them in improving the paper. We thank LetPub (www.letpub.com) for its linguistic assistance during the preparation of this manuscript.

Citation

Liang, Z., Zhao, C., Zhou, H., Zhou, Y., Liu, Q., Fang, T. and Wang, F. (2024), "Dynamic spatial–temporal conflict quantification of construction machinery for pouring blocks in arch dams", Engineering Computations, Vol. ahead-of-print No. ahead-of-print. https://doi.org/10.1108/EC-04-2024-0346