APRT-FMEA buffer sizing method in scheduling of a wind farm construction project
Engineering, Construction and Architectural Management
ISSN: 0969-9988
Article publication date: 10 May 2019
Issue publication date: 10 July 2019
Abstract
Purpose
The purpose of this paper is to present an efficient model for project buffer sizing by taking failure mode and effects analysis (FMEA) into account to reach a more realistic schedule.
Design/methodology/approach
In the first phase of the project, several turbines were installed according to the primary schedule with an average duration of 142 days. Then, some of critical chain project management algorithms were separately applied in the implementation and installation of the other wind turbines. The adaptive procedure with resource tightness (APRT) method turned out to be the best method in terms of obtaining a more realistic schedule in this case study. Finally, FMEA was simultaneously applied with APRT.
Findings
Applying the hybrid method to the scheduling of the wind turbines, yielded the more realistic schedule than traditional.
Research limitations/implications
The proposed hybrid APRT-FMEA algorithm was implemented on a real wind farm construction project which was completed with 37 percent shorter duration than the initial estimation; in spite of the initial estimation of 142 days, the project completed in 103 days.
Practical implications
Introducing and implementing a new algorithm which is a combination of buffer sizing algorithms and one of the well-known and mostly used risk assessment methods in order to provide the more realistic project schedule in the construction of wind turbines.
Originality/value
Introducing and implementing a novel algorithm which is a combination of conventional buffer sizing method and one of the efficient risk assessment methods in order to make the schedule more realistic.
Keywords
Acknowledgements
The authors are grateful to all of those with whom they have had the pleasure to work during this and other related projects.
Citation
Zohrehvandi, S. and Khalilzadeh, M. (2019), "APRT-FMEA buffer sizing method in scheduling of a wind farm construction project", Engineering, Construction and Architectural Management, Vol. 26 No. 6, pp. 1129-1150. https://doi.org/10.1108/ECAM-04-2018-0161
Publisher
:Emerald Publishing Limited
Copyright © 2019, Emerald Publishing Limited