A development process for extending buildings vertically – based on a case study of four extended buildings

Rikard Sundling (Department of Construction Management, Lunds Universitet, Helsingborg, Sweden)

Construction Innovation

ISSN: 1471-4175

Publication date: 7 July 2019

Abstract

Purpose

The purpose of the study, upon which this paper is based, was to contribute an improved understanding of the vertical extension of buildings, by presenting a development process for its implementation in which the key aspects to consider when planning such extensions are highlighted.

Design/methodology/approach

The approach is based on linking the diffusion of innovation together with case study research to stimulate further development in vertically extending buildings. Four cases of vertically extended buildings in Sweden were selected for the study.

Findings

The development process highlights seven key areas for decisions when planning a vertical extension. These areas are: opportunities for vertical extension; strategies for implementation; detailed planning process; concept development; evaluation; building permit; and procurement. The development processes and lessons learnt from each case are presented, covering both success and failure.

Research limitations/implications

The research is based on four cases of vertically extended buildings. The findings offer valuable insights into the development process which should provide the research community with an improved understanding of the challenges faced.

Practical implications

The findings will help planners, housing owners, housing developers and facility managers better understand the conditions that favour successful implementation of vertical extensions.

Originality/value

The paper provides the reader with an understanding of the challenges faced in the vertical extension of a building and the means of overcoming them to create a simplified development process.

Keywords

Citation

Sundling, R. (2019), "A development process for extending buildings vertically – based on a case study of four extended buildings", Construction Innovation, Vol. 19 No. 3, pp. 367-385. https://doi.org/10.1108/CI-05-2018-0040

Publisher

:

Emerald Publishing Limited

Copyright © 2019, Emerald Publishing Limited

To read the full version of this content please select one of the options below

You may be able to access this content by logging in via Shibboleth, Open Athens or with your Emerald account.
To rent this content from Deepdyve, please click the button.
If you think you should have access to this content, click the button to contact our support team.