To read this content please select one of the options below:

The value of data from construction project site meeting minutes in predicting project duration

Jaques van Niekerk (Department of Civil Engineering, Stellenbosch University, Stellenbosch, South Africa)
Jan Wium (Department of Civil Engineering, Stellenbosch University, Stellenbosch, South Africa)
Nico de Koker (Department of Civil Engineering, Stellenbosch University, Stellenbosch, South Africa)

Built Environment Project and Asset Management

ISSN: 2044-124X

Article publication date: 7 April 2022

Issue publication date: 10 August 2022

164

Abstract

Purpose

Construction projects generate large volumes of data which can be used for better management of projects. In this paper, key project data is manually extracted from project site meeting minutes. Knowledge discovery technologies are then used to predict the final project duration of active projects.

Design/methodology/approach

Project planning and effective leadership/governance were identified from literature as the most significant factors that impact the duration of projects. These factors were hence considered as the main features for a data mining process. Items supporting these factors were extracted from site meeting minutes to create a database of 27 civil engineering projects executed over the last ten years. Data mining algorithms were used to predict from this data whether or not an active project will be completed on time.

Findings

The research showed that information from project site meetings can be used to predict final project duration of active projects with accuracy of above 80% when using random forest algorithms from Orange and RapidMiner data mining applications. The value of data to predict project duration from project site meeting minutes is demonstrated but it only becomes practically useable if the format of minutes is suitably standardised.

Practical implications

Some of the data mining algorithms provided accuracies of above 80% in predicting final project duration and proved the value of project data from site meeting minutes. The random forest algorithms are particularly suited to this type of data. The factors with the highest impact on the prediction of the project duration are those related to the progress of the project.

Originality/value

This study for the first time shows that data from site meeting minutes of past and current projects can be used to make accurate predictions of final project duration of active projects and serve as a project management tool to activate remedial measures.

Keywords

Acknowledgements

The authors are indebted to the organisation, who made the site meeting minutes available, for their willingness to share the information.

Citation

van Niekerk, J., Wium, J. and de Koker, N. (2022), "The value of data from construction project site meeting minutes in predicting project duration", Built Environment Project and Asset Management, Vol. 12 No. 5, pp. 738-753. https://doi.org/10.1108/BEPAM-03-2021-0047

Publisher

:

Emerald Publishing Limited

Copyright © 2022, Emerald Publishing Limited

Related articles