To read this content please select one of the options below:

Integrating numerical tools in underground construction process

Ahmed Attar (Faculty of Engineering, University Saâd Dahlab‐Blida, Blida, Algeria)
Mohamed Amine Boudjakdji (Faculty of Engineering, University Saâd Dahlab‐Blida, Blida, Algeria)
Nadia Bhuiyan (Mechanical and Industrial Department, Concordia University, Montréal, Canada)
Khaled Grine (Faculty of Engineering, University Saâd Dahlab‐Blida, Blida, Algeria)
Said Kenai (Faculty of Engineering, University Saâd Dahlab‐Blida, Blida, Algeria)
Ali Aoubed (Faculty of Engineering, University Saâd Dahlab‐Blida, Blida, Algeria)

Engineering, Construction and Architectural Management

ISSN: 0969-9988

Article publication date: 3 July 2009

985

Abstract

Purpose

The purpose of this paper is to show how the time frame for the execution of a construction project in Algeria is rarely respected because of organizational problems and uncertainties encountered while the execution is underway.

Design/methodology/approach

A case study on the construction of a metro station is used as a pilot project to show the effectiveness of replacing traditional construction processes by more innovative procedures. Concurrent engineering (CE) is applied to optimize the execution time of the underground structure. A numerical simulation is integrated into the construction process in order to update design parameters with real site conditions observed during the construction process.

Findings

The results show that the implementation of CE is efficient in reducing the completion time, with an 18 per cent reduction observed in this case study. A cost reduction of 20 per cent on the steel frame support and a total cost reduction of 3 per cent were obtained.

Research limitations/implications

The study demonstrates that the application of CE methods can be quite valuable in large, complex construction projects. Vulgarizing it as “the solution” to adjust time frame delay, control quality and cost, might be an issue for local construction enterprises in Algeria.

Originality/value

Using the concept of CE by overlapping different activities involved in a construction project and making use of simulation tools in the process at different stages of the execution have resulted in modifying the excavation method and hence reducing the completion times.

Keywords

Citation

Attar, A., Amine Boudjakdji, M., Bhuiyan, N., Grine, K., Kenai, S. and Aoubed, A. (2009), "Integrating numerical tools in underground construction process", Engineering, Construction and Architectural Management, Vol. 16 No. 4, pp. 376-391. https://doi.org/10.1108/09699980910970851

Publisher

:

Emerald Group Publishing Limited

Copyright © 2009, Emerald Group Publishing Limited

Related articles