Simulation‐based scheduling of module assembly yards: case study

Yasser Mohamed (Department of Civil and Environmental Engineering, Hole School of Construction, University of Alberta, Edmonton, Canada)
Davila Borrego (Department of Civil and Environmental Engineering, Hole School of Construction, University of Alberta, Edmonton, Canada)
Luis Francisco (Department of Civil and Environmental Engineering, Hole School of Construction, University of Alberta, Edmonton, Canada)
Mohamed Al‐Hussein (Department of Civil and Environmental Engineering, Hole School of Construction, University of Alberta, Edmonton, Canada)
Simaan AbouRizk (Department of Civil and Environmental Engineering, Hole School of Construction, University of Alberta, Edmonton, Canada)
Ulrich Hermann (Project Managed PCL Construction, Edmonton, Canada)

Engineering, Construction and Architectural Management

ISSN: 0969-9988

Article publication date: 8 May 2007

1464

Abstract

Purpose

Pipe‐spool module assembly involves a variety of uncertain factors and constraints, which complicate the assembly scheduling process. These factors also pose a challenge for the scheduler who struggles to produce a schedule that optimizes both the use of available resources (e.g. space) and meets the project's delivery deadlines. In the relatively quick production cycle of module assembly, the scheduling process plays an operative role. Thus, automation of the process would enhance productivity of the schedule updating process. This paper seeks to address this issue.

Design/methodology/approach

A simulation‐based approach is presented for scheduling pipe‐spool module assembly. This approach incorporates physical and logical constraints. General purpose simulation (GPS) is used to model these logical and heuristic constraints.

Findings

The application of the proposed model to an actual case study demonstrates the significant improvement in the assembly schedule when compared to traditional CPM‐based scheduling techniques.

Originality/value

The proposed model allows schedulers to experiment with various rules in order to improve the scheduling process by, for example, instantly updating the schedule.

Keywords

Citation

Mohamed, Y., Borrego, D., Francisco, L., Al‐Hussein, M., AbouRizk, S. and Hermann, U. (2007), "Simulation‐based scheduling of module assembly yards: case study", Engineering, Construction and Architectural Management, Vol. 14 No. 3, pp. 293-311. https://doi.org/10.1108/09699980710744926

Publisher

:

Emerald Group Publishing Limited

Copyright © 2007, Emerald Group Publishing Limited

Related articles