1 – 8 of 8Tiep Nguyen, Nicholas Chileshe, Duc Ty Ho, Viet Thanh Nguyen and Quang Phu Tran
Urban rail projects are typically large-scale transport infrastructure projects (megaprojects) which have many potential risks that can influence the strategic goals of owners…
Abstract
Purpose
Urban rail projects are typically large-scale transport infrastructure projects (megaprojects) which have many potential risks that can influence the strategic goals of owners. However, there is a paucity of studies which explore the impact of risks on both “urban rail” project time and cost together considering quantitative assessments. Therefore, this paper focuses on investigating critical risks and quantifying such risk impacts on urban railway project schedule and cost in practice.
Design/methodology/approach
A combination of qualitative and quantitative research methods comprising semi-interviews with five experts and a questionnaire survey of 132 professional respondents is used. The data were modeled using Monte Carlo Simulation to predict the probability of project schedule and cost.
Findings
The results show that 30 risk variables are categorized into seven main groups which have significant impacts on both project time and cost. Outstanding five risk variables were highlighted as follows: (1) project site clearance and land compensation; (2) design changes; (3) physical project resources; (4) contractors’ competencies and (5) project finance. Such findings were supported by Monte Carlo simulation which predicted in the worst case that the project may suffer 11.03 months’ delays and have cost overrun with a contingency of US$287.68 million.
Originality/value
This study expands our knowledge about time and cost contingency of urban metro railway implementation across developing economies and particularly within the context of Vietnam. Policymakers will not only gain an understanding about risk structure but will also recognize the significant impacts of critical risk through risk impact modeling and simulation. Such an approach provides insights into risk treatment priorities for planners so that they can proactively establish suitable strategies for risk mitigation in practice.
Details
Keywords
Dara Sruthilaya, Aneetha Vilventhan and P.R.C. Gopal
The purpose of this paper is to identify and analyze the interdependence of project complexity factors (PCFs) in metro rail projects using the Decision-Making Trial and Evaluation…
Abstract
Purpose
The purpose of this paper is to identify and analyze the interdependence of project complexity factors (PCFs) in metro rail projects using the Decision-Making Trial and Evaluation Laboratory (DEMATEL). The study provides qualitative and quantitative analysis of project complexities factors and their relationships. The results of the study facilitate effective project planning, proactive risk management and informed decision-making by stakeholders.
Design/methodology/approach
This study employs a case-based method for identifying PCFs and a DEMATEL method for analyzing the interdependence of complexity factors in metro rail projects. Initially, PCFs were identified through an extensive literature review. To validate and refine these factors, semi-structured interviews were conducted with thirty experienced professionals, each having 5–20 years of experience in roles such as project management, engineering, and planning. Further, elevated and underground metro rail projects were purposefully selected as cases, for identifying the similarities and differences in PCFs. A questionnaire survey was conducted with various technical experts in metro rail projects. These experts rated the impact of PCFs on a five-point Likert scale, for the evaluation of the interdependence of PCFs. The DEMATEL technique was used to analyze the interdependencies of the PCFs.
Findings
Metro rail projects are influenced by project complexity, which significantly impacts their performance. The analysis reveals that “design problems with existing structures,” “change in design or construction” and “land acquisition” are the key factors contributing to project complexity.
Originality/value
The study of project complexity in metro rail projects is limited because most of the studies have studies on examining complexity in mega projects. The existing literature lacks adequate attention in identifying project complexity and its effects on metro rail project performance. This research aims to bridge this gap by examining project complexity and interdependencies in metro rail projects.
Details
Keywords
Nirodha Fernando, Kasun Dilshan T.A. and Hexin (Johnson) Zhang
The Government’s investment in infrastructure projects is considerably high, especially in bridge construction projects. Government authorities must establish an initial…
Abstract
Purpose
The Government’s investment in infrastructure projects is considerably high, especially in bridge construction projects. Government authorities must establish an initial forecasted budget to have transparency in transactions. Early cost estimating is challenging for Quantity Surveyors due to incomplete project details at the initial stage and the unavailability of standard cost estimating techniques for bridge projects. To mitigate the difficulties in the traditional preliminary cost estimating methods, there is a requirement to develop a new initial cost estimating model which is accurate, user friendly and straightforward. The research was carried out in Sri Lanka, and this paper aims to develop the artificial neural network (ANN) model for an early cost estimate of concrete bridge systems.
Design/methodology/approach
The construction cost data of 30 concrete bridge projects which are in Sri Lanka constructed within the past ten years were trained and tested to develop an ANN cost model. Backpropagation technique was used to identify the number of hidden layers, iteration and momentum for optimum neural network architectures.
Findings
An ANN cost model was developed, furnishing the best result since it succeeded with around 90% validation accuracy. It created a cost estimation model for the public sector as an accurate, heuristic, flexible and efficient technique.
Originality/value
The research contributes to the current body of knowledge by providing the most accurate early-stage cost estimate for the concrete bridge systems in Sri Lanka. In addition, the research findings would be helpful for stakeholders and policymakers to propose policy recommendations that positively influence the prediction of the most accurate cost estimate for concrete bridge construction projects in Sri Lanka and other developing countries.
Details
Keywords
Guus Keusters, Hans Bakker and Erik-Jan Houwing
Civil engineering projects around the world have been underperforming for a long time. While the complexity of these projects will continue to increase, there is an urgent need to…
Abstract
Purpose
Civil engineering projects around the world have been underperforming for a long time. While the complexity of these projects will continue to increase, there is an urgent need to perform better. Although the integrated design process is critical for project success, the literature lacks studies describing the link to project performance. Therefore, this study aims to investigate the dominant variables that affect the integrated design process and consequently project performance.
Design/methodology/approach
A multiple case study was conducted to determine the dominant variables that affect the integrated design process and project performance. The research included four projects. Semi-structured interviews were the main source of data.
Findings
The cases indicated that the extent to which an integrated approach is achieved in the design process is essential for project performance. This applies to the integration of stakeholders’ interests as well as the integration of disciplines. Above all, it was concluded that the project team participants’ competencies for integration are a dominant factor for project performance, as the integrated design process has changed from a technical challenge to an integrative one.
Originality/value
This study provides insights into the dominant variable of the integrated design process that affects project performance, which is underexposed in the literature. The study results reveal the importance of competencies related to integration and adoption of the design problem context, which are not yet included in civil engineering design methods. In this respect, empathy is introduced as a new and critical competence for the civil engineering industry, which needs further research.
Details
Keywords
Mahmoud Ershadi and Fredelino Lijauco
In this paper, a systematic review of 284 articles published between 2015 and 2022 and a full-text thematic analysis of 70 selected articles was conducted to catalog and…
Abstract
Purpose
In this paper, a systematic review of 284 articles published between 2015 and 2022 and a full-text thematic analysis of 70 selected articles was conducted to catalog and synthesize factors in a framework. Thematic analysis subsequently revealed 18 selective codes under three groups of drivers, barriers, and outcomes. These three groups were explained by four key aspects including organization, stakeholders, infrastructure, and business environment that set a framework for the digitalization of construction. The study finally concluded digitalization strategies with a focus on support mechanisms, government incentives, regulations, the transition from manual labor to technicians, organizational technology culture, methodology development, and innovation processes. Such strategies provide insight into prioritizing resources towards smooth digital transformation in construction businesses.
Design/methodology/approach
A two-stage methodology is adopted by undertaking a systematic literature review followed by thematic content analysis. This work concludes with an analysis of remaining research gaps and suggestions for potential future research.
Findings
In this paper, a systematic review of 284 articles published between 2015 and 2022 and a full-text thematic analysis of 70 selected articles was conducted to catalog and synthesize variables in a framework. Thematic analysis subsequently revealed a set of variables and factors describing construction digitalization under three groups of success factors, barriers, and outcomes. A critical content analysis of the representative studies was conducted to identify five future research trends as well as associated research gaps and directions on the topic.
Practical implications
This study contributes to practice by providing directions concerning the key strategies and priorities associated with the digitalization of construction businesses.
Originality/value
This ground-breaking research brings to light a classified set of factors that are important for the digitalization of construction businesses. The elicited framework contributes to the current body of knowledge by offering a unique conceptualization of both driving and adverse aspects for the seamless digital transformation of construction.
Details
Keywords
Sustainable construction re-engineers the conventional project lifecycle to integrate sustainability solutions. The additional sustainability requirements introduce new layers of…
Abstract
Purpose
Sustainable construction re-engineers the conventional project lifecycle to integrate sustainability solutions. The additional sustainability requirements introduce new layers of complexity, challenges and risks that if unaddressed, can derail the gains in sustainable construction projects. This study developed a multidimensional risk assessment model for sustainable construction projects in the United Arab Emirates (UAE).
Design/methodology/approach
The research activities a comprised comprehensive literature review to shortlist relevant risks, an analysis of the probability – impact rating of the shortlisted risks – and the development of a risk assessment model for SC projects in the UAE. The model is developed based on the multicriteria framework and mathematical formulation of the fuzzy synthetic evaluation approach.
Findings
The developed model quantified the overall risk level in sustainable construction projects to be 3.71 on a 5-point Likert scale, indicating that investment in SC projects in the UAE is risky and should be carefully managed. The developed model further revealed that each of the risk groups, comprising management (3.82), technical (3.78), stakeholder (3.68), regulatory (3.66), material (3.53) and economic risks (3.502), presents a significant threat to realizing outcomes typical of SC projects.
Originality/value
This study developed a multidimensional risk assessment model capable of objectively quantifying the overall risk level and provides decision support to project teams to improve risk management in sustainable construction projects.
Details
Keywords
Kai Hänninen, Jouni Juntunen and Harri Haapasalo
The purpose of this study is to describe latent classes explaining the innovation logic in the Finnish construction companies. Innovativeness is a driver of competitive…
Abstract
Purpose
The purpose of this study is to describe latent classes explaining the innovation logic in the Finnish construction companies. Innovativeness is a driver of competitive performance and vital to the long-term success of any organisation and company.
Design/methodology/approach
Using finite mixture structural equation modelling (FMSEM), the authors have classified innovation logic into latent classes. The method analyses and recognises classes for companies that have similar logic in innovation activities based on the collected data.
Findings
Through FMSEM analysis, the authors have identified three latent classes that explain the innovation logic in the Finnish construction companies – LC1: the internal innovators; LC2: the non-innovation-oriented introverts; and LC3: the innovation-oriented extroverts. These three latent classes clearly capture the perceptions within the industry as well as the different characteristics and variables.
Research limitations/implications
The presented latent classes explain innovation logic but is limited to analysing Finnish companies. Also, the research is quantitative by nature and does not increase the understanding in the same manner as qualitative research might capture on more specific aspects.
Practical implications
This paper presents starting points for construction industry companies to intensify innovation activities. It may also indicate more fundamental changes for the structure of construction industry organisations, especially by enabling innovation friendly culture.
Originality/value
This study describes innovation logic in Finnish construction companies through three models (LC1–LC3) by using quantitative data analysed with the FMSEM method. The fundamental innovation challenges in the Finnish construction companies are clarified via the identified latent classes.
Details
Keywords
Francis Nuako, Frank Ato Ghansah and Thomas Adusei
It is widely accepted that one criterion for determining if a construction project is successful is whether it is completed within the expected budget. There have been…
Abstract
Purpose
It is widely accepted that one criterion for determining if a construction project is successful is whether it is completed within the expected budget. There have been advancements in the management of building projects throughout time but cost overruns remain a key concern in the construction sector internationally, particularly in emerging economies such as Ghana. This study aims to answer the question, “What are the critical success factors (CSFs) that can assist reduce cost overruns in public sector infrastructure projects in the Ghanaian construction industry?”
Design/methodology/approach
This study used a quantitative survey method. The questionnaire was pre-tested by interviewing 15 contractors to ascertain the validity of the content. Factor analysis and multiple regression were adopted to analyze the data.
Findings
This study discovered that the critical factors that can reduce cost overruns in construction projects in Ghana are directly linked to five themes: early contractor involvement in the project planning stage, adequate funding, good project team relations, competent managers/supervisors and project participant incentives/bonuses. This study identifies indestructible, empirically measurable important success criteria for reducing cost overruns in public building projects in Ghana.
Practical implications
When well thought through from the project initiation stage to completion, these critical successes can also be used to deal with damaging economic effects such as allocative inefficiency of scarce resources, further delays, contractual disputes, claims and litigation, project failure and total abandonment.
Originality/value
The uniqueness of this research resides in the fact that it is, to the best of the authors’ knowledge, a first-of-its-kind investigation of the CSFs for reducing cost overruns in public building projects in developing countries.