Open Access
Article
Publication date: 7 August 2017

Per Erik Eriksson

The purpose of this study is to investigate how procurement strategies may be designed to facilitate exploration and exploitation in construction projects.

12349

Abstract

Purpose

The purpose of this study is to investigate how procurement strategies may be designed to facilitate exploration and exploitation in construction projects.

Design/methodology/approach

This paper is based on a literature review of organizational research and construction management literature together with a brief interview study of Swedish clients and contractors.

Findings

The theoretical and empirical findings propose that small and simple projects with low uncertainty and scarce resources may focus on exploitation to enhance short-term efficiency through traditional procurement strategies including delivery systems that separate the actors and their activities (i.e. pure design-build- or design-bid-build-contracts), fixed price payment and price focus in bid evaluation. Large complex projects with high uncertainty and customization benefit from combining exploration and exploitation to enhance sustainable performance. This requires collaborative procurement strategies including joint specification through early contractor involvement, cost reimbursement coupled with incentive-based payment, bid evaluation based on multiple criteria and collaborative tools and activities in partnering arrangements.

Research limitations/implications

This paper contributes to organizational learning literature by pinpointing the need for integrating procurement strategies that enhance combination of exploration and exploitation. The main contribution to the construction management literature involves the investigation of how procurement strategies may affect exploration and exploitation, as identified and articulated in the propositions developed in this paper.

Practical implications

From a practical perspective, the findings highlight the importance of tailoring procurement strategies to project characteristics to enhance a suitable balance between exploration and exploitation in construction projects.

Originality/value

The explicit focus on the operational project-level is uncommon but relevant in organizational learning literature.

Details

Journal of Financial Management of Property and Construction, vol. 22 no. 2
Type: Research Article
ISSN: 1366-4387

Keywords

Open Access
Article
Publication date: 3 February 2020

Paulos A. Wondimu, Ole Jonny Klakegg and Ola Lædre

Early contractor involvement (ECI) faces many barriers because it differs from traditional business practices. Public owners, especially, face a major challenge because they must…

9334

Abstract

Purpose

Early contractor involvement (ECI) faces many barriers because it differs from traditional business practices. Public owners, especially, face a major challenge because they must comply with international and national legislation. The purpose of this paper is to develop a framework that illustrates the various approaches that public project owners can take to implement ECI.

Design/methodology/approach

In addition to a literature review, three groups of case studies were carried out. The case studies were based on 54 semi-structured in-depth interviews with key personnel from 21 Norwegian public projects and document study.

Findings

In all, 25 approaches to ECI were identified during the research. Twelve of these were used in the cases studied.

Social implications

There are several approaches to ECI that are suitable for public owners. However, the contractor’s contribution depends on which approach is implemented and how it is implemented.

Originality/value

As original contribution, this study presents a novel framework that defines options for implementing ECI in public projects. Furthermore, this paper provides insights on how ECI can be implemented in public projects based on Norwegian experiences. Although the empirical data of the study is limited to Norwegian public projects, this study contributes to knowledge about how to implement ECI internationally.

Details

Journal of Public Procurement, vol. 20 no. 1
Type: Research Article
ISSN: 1535-0118

Keywords

Open Access
Book part
Publication date: 1 May 2019

Pertti Lahdenperä

The paper aims to describe the evolution and use of project alliancing in Finland: how the model was discovered, and then, little by little, became an established practice.

Abstract

Purpose

The paper aims to describe the evolution and use of project alliancing in Finland: how the model was discovered, and then, little by little, became an established practice.

Design/Methodology/Approach

The paper is based on a long-term observation of the construction sector activities, involvement in their development and a review of related research and practice documents.

Findings

The paper illustrates how a major change may be laborious. It also reveals that the application of project alliancing seems to have been successful so far, but there are still threats on the horizon.

Research Limitations/Implications

The overview ignores many meaningful details and does not include a critical review of the positive experiences reported by the industry. There certainly is need for related research.

Practical Implications

The study offers a point of reference for evaluation of the smoothness of the progress of industry wide changes.

Originality/Value

This paper seems to be the first one providing a more comprehensive picture of the progress and use of alliancing in Finland, thus supplementing existing view- and project-specific examinations.

Details

10th Nordic Conference on Construction Economics and Organization
Type: Book
ISBN: 978-1-83867-051-1

Keywords

Open Access
Article
Publication date: 16 October 2023

Emmanuel Dele Omopariola, Abimbola Olukemi Windapo, David John Edwards, Clinton Ohis Aigbavboa, Sunday Ukwe-Nya Yakubu and Onimisi Obari

Previous studies have postulated that an advance payment system (APS) positively impacts the contractor's working capital and is paramount to ensuring an efficient and effective…

Abstract

Purpose

Previous studies have postulated that an advance payment system (APS) positively impacts the contractor's working capital and is paramount to ensuring an efficient and effective project cash flow process. However, scant research has been undertaken to empirically establish the cash flow performance and domino effect of APS on project and organisational performance.

Design/methodology/approach

The epistemological design adopted a positivist philosophical stance augmented by deductive reasoning to explore the phenomena under investigation. Primary quantitative data were collected from 504 Construction Industry Development Board (CIDB) registered contractors (within the grade bandings 1–9) in South Africa. A five-point Likert scale was utilised, and subsequent data accrued were analysed using structural equation modelling (SEM).

Findings

Emergent findings reveal that the mandatory use of an APS does not guarantee a positive project cash flow, an improvement in organisational performance or an improvement in project performance.

Practical implications

The ensuing discussion reveals the contributory influence of APS on positive cash flow and organisational performance, although APS implementation alone will not achieve these objectives. Practically, the research accentuates the need for various measures to be concurrently adopted (including APS) towards ensuring a positive project cash flow and improved organisational and project performance.

Originality/value

There is limited empirical research on cash flow performance and the domino effect of APS on project and organisational performance in South Africa, nor indeed, the wider geographical location of Africa as a continent. This study addresses this gap in the prevailing body of knowledge.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 13
Type: Research Article
ISSN: 0969-9988

Keywords

Open Access
Article
Publication date: 1 May 2020

Juliana Pacheco Barbosa, Joisa Dutra Saraiva and Julia Seixas

The purpose of this paper is to highlight the opportunity for the energy policy in Brazil to tackle the very high cost-effectiveness potencial of solar energy to the power system…

3412

Abstract

Purpose

The purpose of this paper is to highlight the opportunity for the energy policy in Brazil to tackle the very high cost-effectiveness potencial of solar energy to the power system. Three mechanisms to achieve ambitious reductions in the greenhouse gas emissions from the power sector by 2030 and 2040 are assessed wherein treated as solar targets under ambitious reductions in the greenhouse gas emissions from the power sector. Then, three mechanisms to achieve these selected solar targets are suggested.

Design/methodology/approach

This paper reviews current and future incentive mechanisms to promote solar energy. An integrated energy system optimization model shows the most cost-efficient deployment level. Incentive mechanisms can promote renewable sources, aiming to tackle climate change and ensuring energy security, while taking advantage of endogenous energy resources potential. Based on a literature review, as well as on the specific characteristics of the Brazilian power system, under restrictions for the expansion of hydroelectricity and ambitious limitation in the emissions of greenhouse gases from the power sector.

Findings

The potential unexploited of solar energy is huge but it needs the appropriate incentive mechanism to be deployed. These mechanisms would be more effective if they have a specific technological and temporal focus. The solar energy deployment in large scale is important to the mitigation of climate change.

Originality/value

The value of the research is twofold: estimations of the cost-effective potential of solar technologies, generated from an integrated optimization energy model, fully calibrated for the Brazilian power system, while tacking the increasing electricity demand, the expected reduction of greenhouse gas emissions and the need to increase the access to clean and affordable energy, up to 2040; proposals of three mechanisms to deploy centralized PV, distributed PV and solar thermal power, taking the best experiences in several countries and the recent Brazilian cases.

Details

International Journal of Climate Change Strategies and Management, vol. 12 no. 3
Type: Research Article
ISSN: 1756-8692

Keywords

Open Access
Article
Publication date: 27 September 2021

Monique Rieger Rodrigues and Søren Munch Lindhard

The traditional construction delivery method is challenged by low trust and collaboration issues, resulting in increased project costs. The integrated project delivery (IPD…

5796

Abstract

Purpose

The traditional construction delivery method is challenged by low trust and collaboration issues, resulting in increased project costs. The integrated project delivery (IPD) method is developed, through a contractual agreement, to overcome these challenges by creating a common set of terms, expectations and project goals.

Design/methodology/approach

A singular construction case was followed during a four-month period. Data collection consisted of contract documents and a series of semi-structured interviews with representatives from the owner, design-group and contractors.

Findings

The IPD contract was found to have a number of positive effects; it improved project behavior (e.g. trust, collaboration and communication), increased ownership among project participants and improved buildability of the design, leading to fewer surprises and interruptions in the construction phase. The study also revealed a number of challenges including contractual and legal challenges and involving too many participants in the early phases. Moreover, co-location was identified as a particular important supporting element, to build relations and improve collaboration.

Originality/value

This research identified lessons learned from the application, as well as initial barriers and persistent barriers for implementing IPD. To improve IPD application the top three lessons were as follows: 1) the contractual documents should be adapted and signed at an early stage as this increases financial transparency, 2) cost estimates should be carried as an iterative process and project main concept be freezed at an early stage to increase understanding and minimize risks, 3) only the most important project developers should be involved in the early phases, to avoid going into detailed design issues before the main concept is completed.

Details

Construction Innovation , vol. 23 no. 2
Type: Research Article
ISSN: 1471-4175

Keywords

Open Access
Article
Publication date: 25 August 2021

Tahir Ali, Aurangzeab Butt, Ahmad Arslan, Shlomo Yedidia Tarba, Sniazhana Ana Sniazhko and Minnie Kontkanen

This study investigates an under-researched yet fundamental question of how a developed country multinational enterprises (DMNE) perceives and manages political risks when…

9844

Abstract

Purpose

This study investigates an under-researched yet fundamental question of how a developed country multinational enterprises (DMNE) perceives and manages political risks when undertaking infrastructure projects in the emerging markets (EMs).

Design/methodology/approach

The authors use an abduction-based qualitative research approach to analyze six international project operations of a multinational enterprise originating from Finland in five EMs.

Findings

The findings suggest that the overall nature of political risks in EMs is not the same, except few political risk factors that are visible in most EMs. Consequently, the applied risk management mechanisms vary between EMs, except with few common mechanisms. The authors develop an integrative analytical framework of political risk management based on the findings.

Originality/value

This paper is one of the first studies to identify political risk factors for western MNEs while undertaking international project operations and link them to reduction mechanisms used by them. The authors go beyond the notion of risk being conceptualized at a general level and evaluate 20 specific political risk factors referred to in extant literature. The authors further link these political risk factors with both social exchange and transaction cost theories conceptually as well as empirically. Finally, the authors develop a relatively comprehensive analytical framework of political risk management based on the case projects' findings that combine several strands of literature, including the social exchange theory, transaction cost theory, international market entry, project management and finance literature streams.

Details

International Marketing Review, vol. 38 no. 6
Type: Research Article
ISSN: 0265-1335

Keywords

Open Access
Article
Publication date: 4 July 2022

Shiyu Wan, Yisheng Liu, Grace Ding, Goran Runeson and Michael Er

This article aims to establish a dynamic Energy Performance Contract (EPC) risk allocation model for commercial buildings based on the theory of Incomplete Contract. The purpose…

1553

Abstract

Purpose

This article aims to establish a dynamic Energy Performance Contract (EPC) risk allocation model for commercial buildings based on the theory of Incomplete Contract. The purpose is to fill the policy vacuum and allow stakeholders to manage risks in energy conservation management by EPCs to better adapt to climate change in the building sector.

Design/methodology/approach

The article chooses a qualitative research approach to depict the whole risk allocation picture of EPC projects and establish a dynamic EPC risk allocation model for commercial buildings in China. It starts with a comprehensive literature review on risks of EPCs. By modifying the theory of Incomplete Contract and adopting the so-called bow-tie model, a theoretical EPC risk allocation model is developed and verified by interview results. By discussing its application in the commercial building sector in China, an operational EPC three-stage risk allocation model is developed.

Findings

This study points out the contract incompleteness of the risk allocation for EPC projects and offered an operational method to guide practice. The reasonable risk allocation between building owners and Energy Service Companies can realize their bilateral targets on commercial building energy-saving benefits, which makes EPC more attractive for energy conservation.

Originality/value

Existing research focused mainly on static risk allocation. Less research was directed to the phased and dynamic risk allocation. This study developed a theoretical three-stage EPC risk allocation model, which provided the theoretical support for dynamic EPC risk allocation of EPC projects. By addressing the contract incompleteness of the risk allocation, an operational method is developed. This is a new approach to allocate risks for EPC projects in a dynamic and staged way.

Details

International Journal of Climate Change Strategies and Management, vol. 15 no. 4
Type: Research Article
ISSN: 1756-8692

Keywords

Open Access
Article
Publication date: 28 March 2019

Wenting Zou, Saara A. Brax, Mervi Vuori and Risto Rajala

To build a more comprehensive understanding of factors affecting the success of service contracting, the purpose of this paper is to investigate the influences of service…

6970

Abstract

Purpose

To build a more comprehensive understanding of factors affecting the success of service contracting, the purpose of this paper is to investigate the influences of service complexity, contract structure and contracting process on the buyer-perceived supplier performance in business-to-business (B2B) services.

Design/methodology/approach

A research model is developed based on transaction cost economics and the research on service contracting. The model is tested by the survey data collected. Professional focus groups on LinkedIn are used to generate the list of potential respondents. The sample consists of 177 purchasing professionals from 25 countries.

Findings

The results indicate that three major contract dimensions and follow-up management practices positively influence buyer-perceived supplier performance. Furthermore, service complexity amplifies the effects of incentives designed in the contract and the buyer’s follow-up contract management on perceived supplier performance.

Research limitations/implications

The sample consists of respondents from 25 countries and provides good geographic coverage. However, the results should be generalized with caution because not all countries were represented equally.

Practical implications

The study suggests a framework and guidelines for purchasing managers to improve the design and management of service contracts to secure good performance from their supplier.

Originality/value

This paper contributes to understanding the performance-enhancing aspects of designing and monitoring service contracts in B2B contexts. It also adds to the knowledge of the role of service complexity in successful B2B service purchasing.

Details

International Journal of Operations & Production Management, vol. 39 no. 4
Type: Research Article
ISSN: 0144-3577

Keywords

Open Access
Book part
Publication date: 1 May 2019

Per Fridtjof Larssen, Atle Engebø, Ola Lædre and Ole Jonny Klakegg

This paper aims to examine how a partnering contract facilitates project values and the culture in a construction project and the consequences of said facilitation. Hence, it…

Abstract

Purpose

This paper aims to examine how a partnering contract facilitates project values and the culture in a construction project and the consequences of said facilitation. Hence, it answers the following research questions: 1) How does the contractual framework in Bispevika facilitate relational culture? 2) What effects of this facilitation can be identified in the early phase of development?

Design/Methodology/Approach

An explorative approach is taken into a single case. A literature study into the topics of relational contracting and culture provides a backdrop for the study. The empirical work consists of a study of the construction contracts and six in-depth interviews with actors from the supply-chain.

Findings

Contractual elements affect the project organizations’ motivation. On the basis of existing literature, five contractual elements are identified explicitly in the contracts: “shared goals”, “incentives and bonus”, “open book”, “colocation”, and “design-build”.

Research Limitations/Implications

The data collection is restricted to a single point in time in a single project. Further research is necessary both at a later stage in the same case and in similar projects.

Practical Implications

The paper identifies the effects that proper use of contractual elements has on the relational culture in a construction project and is, therefore, important for subsequent research within the area.

Originality/Value

In addition to identifying the existing contractual elements, the interviews also revealed two additional practices that might be useful for subsequent research: “involvement of executive management” and “subsequent contracts dependent on previous project performance”.

Details

10th Nordic Conference on Construction Economics and Organization
Type: Book
ISBN: 978-1-83867-051-1

Keywords