Article
Publication date: 29 December 2023

Dara Sruthilaya, Aneetha Vilventhan and P.R.C. Gopal

The purpose of this paper is to identify and analyze the interdependence of project complexity factors (PCFs) in metro rail projects using the Decision-Making Trial and Evaluation…

Abstract

Purpose

The purpose of this paper is to identify and analyze the interdependence of project complexity factors (PCFs) in metro rail projects using the Decision-Making Trial and Evaluation Laboratory (DEMATEL). The study provides qualitative and quantitative analysis of project complexities factors and their relationships. The results of the study facilitate effective project planning, proactive risk management and informed decision-making by stakeholders.

Design/methodology/approach

This study employs a case-based method for identifying PCFs and a DEMATEL method for analyzing the interdependence of complexity factors in metro rail projects. Initially, PCFs were identified through an extensive literature review. To validate and refine these factors, semi-structured interviews were conducted with thirty experienced professionals, each having 5–20 years of experience in roles such as project management, engineering, and planning. Further, elevated and underground metro rail projects were purposefully selected as cases, for identifying the similarities and differences in PCFs. A questionnaire survey was conducted with various technical experts in metro rail projects. These experts rated the impact of PCFs on a five-point Likert scale, for the evaluation of the interdependence of PCFs. The DEMATEL technique was used to analyze the interdependencies of the PCFs.

Findings

Metro rail projects are influenced by project complexity, which significantly impacts their performance. The analysis reveals that “design problems with existing structures,” “change in design or construction” and “land acquisition” are the key factors contributing to project complexity.

Originality/value

The study of project complexity in metro rail projects is limited because most of the studies have studies on examining complexity in mega projects. The existing literature lacks adequate attention in identifying project complexity and its effects on metro rail project performance. This research aims to bridge this gap by examining project complexity and interdependencies in metro rail projects.

Details

Built Environment Project and Asset Management, vol. 14 no. 2
Type: Research Article
ISSN: 2044-124X

Keywords

Abstract

Details

Communicating Climate
Type: Book
ISBN: 978-1-83753-643-6

Article
Publication date: 15 February 2024

Abbas Ramdani, Ridwan Raji and Mohd. Khairie Ahmad

The acceleration of globalized commerce and economic activities has meant that conventional and Shariah (Islamic law) compliant organizations transact and negotiate among…

Abstract

Purpose

The acceleration of globalized commerce and economic activities has meant that conventional and Shariah (Islamic law) compliant organizations transact and negotiate among themselves. Therefore, this study aims to explore the concept of corporate negotiation and the communicative principles that guide the negotiation process among Shariah-compliant organizations.

Design/methodology/approach

The study uses a qualitative method through an inductive interpretative approach by conducting 20 in-depth interviews among four groups of experts. These consist of three muftis, ten academicians in Islamic assets, finance and asset jurisprudence; three practitioners in charge of inter-organizational negotiation and decision-making; and four shariah board members of selected Islamic banks.

Findings

The findings reported that business negotiation is used by Islamic organizations for reconciliation, consultation, resolving disagreements and as a means of achieving spiritual satisfaction. Furthermore, the key communicative principles of the negotiation process consist of the credibility of informational exchange, flexible interactions and the openness and truthful disclosure of information.

Research limitations/implications

The empirical data discussed in this study supports the claim that macro-environmental factors and social and cultural values should be considered when examining business negotiating behaviors. However, this study focuses only on the banking/service organization negotiation. Therefore, future research should focus on the Islamic negotiation process in the context of diplomatic and international relations.

Practical implications

The findings reported in this study offer insight for negotiators operating among Islamic organizations to understand the principles and process of negotiation in the purview of Shariah standards and principles.

Originality/value

In terms of theoretical implications, this study reveals a clear conceptual difference between the conventional concept and the Islamic perspective of corporate negotiation. Also, this study highlights the impact of organizational culture, specifically Islamic management strategies, on the business negotiation process and business communication principles.

Details

Journal of Islamic Marketing, vol. 15 no. 4
Type: Research Article
ISSN: 1759-0833

Keywords

Open Access
Article
Publication date: 15 August 2022

Ana Junça Silva, Patrícia Neves and António Caetano

This study draws on the affective events theory (AET) to understand how telework may influence workers' well-being. Hence this study aimed to (1) analyze the indirect relationship…

2506

Abstract

Purpose

This study draws on the affective events theory (AET) to understand how telework may influence workers' well-being. Hence this study aimed to (1) analyze the indirect relationship between telework and well-being via daily micro-events (DME), and (2) test whether procrastination would moderate this indirect effect.

Design/methodology/approach

To test the goals, data were gathered from a sample of teleworkers in the IT sector (N = 232). To analyze the data, a moderated mediation analysis was performed in SPSS with PROCESS macro.

Findings

The results showed that micro-daily events mediated the positive relationship between telework and well-being; however, this relation was conditional upon the levels of workers' levels of procrastination, that is, this link became weaker for those who were procrastinators.

Practical implications

By highlighting the importance of telework, DME and procrastination, this study offers managers distinct strategies for enhancing their employees' well-being.

Originality/value

Despite the existing research investigating the effect of telework on well-being, studies investigating the intervening mechanisms between these two constructs are scarce. Moreover, there is a lack of research investigating the moderating effect of procrastination in these relations. Hence, this study fills these gaps and advances knowledge on the process that explains how (via DME) and when (when procrastination is low) teleworking influences workers' well-being.

Details

International Journal of Manpower, vol. 45 no. 1
Type: Research Article
ISSN: 0143-7720

Keywords

Article
Publication date: 15 February 2023

Pilar Ficapal-Cusí, Joan Torrent-Sellens, Pedro Palos-Sanchez and Inés González-González

Due to the crisis originated by the COVID-19 pandemic, an important number of workers have been incorporating the telework modality. In this context, the distance from the…

Abstract

Purpose

Due to the crisis originated by the COVID-19 pandemic, an important number of workers have been incorporating the telework modality. In this context, the distance from the workplace generates new dilemmas for work performance. In the paper the authors study the role of some individual and social antecedents on telework outcomes. In particular, they empirically investigate the direct relationship between trust (TR) and telework performance (PER) and explore mediators of that relationship such as social isolation (SI) and fatigue (FA).

Design/methodology/approach

A theoretical model with three main hypotheses is proposed and tested using partial least square structural equation modeling (PLS-SEM). The study sample, of an exploratory nature, consists of a dataset of 201 teleworkers working in Spanish companies.

Findings

The relevance of the proposed model is demonstrated and FA is found to be the factor that most affects (negatively) PER, followed by TR (positively) and SI (negatively). Beyond the direct effects, the results provide support for the role of SI and FA in mediating the relationship between TR and PER.

Originality/value

This paper discusses the PER dilemma and proposes and tests a background model that may be useful for future research. The results are of interest to human resource managers, consultants, academics and telework tool developers and managers. Practices are proposed to improve TR or to reduce feelings of SI or FA. The research provides a practical evaluation tool for telework implementation.

Details

International Journal of Manpower, vol. 45 no. 1
Type: Research Article
ISSN: 0143-7720

Keywords

Article
Publication date: 26 March 2024

Yuanwen Han, Jiang Shen, Xuwei Zhu, Bang An and Xueying Bao

This study aims to develop an interface management risk interaction modeling and analysis methodology applicable to complex systems in high-speed rail construction projects…

Abstract

Purpose

This study aims to develop an interface management risk interaction modeling and analysis methodology applicable to complex systems in high-speed rail construction projects, reveal the interaction mechanism of interface management risk and provide theoretical support for project managers to develop appropriate interface management risk response strategies.

Design/methodology/approach

This paper introduces the association rule mining technique to improve the complex network modeling method. Taking China as an example, based on the stakeholder perspective, the risk factors and significant accident types of interface management of high-speed rail construction projects are systematically identified, and a database is established. Then, the Apriori algorithm is used to mine and analyze the strong association rules among the factors in the database, construct the complex network, and analyze its topological characteristics to reveal the interaction mechanism of the interface management risk of high-speed rail construction projects.

Findings

The results show that the network is both scale-free and small-world, implying that construction accidents are not random events but rather the result of strong interactions between numerous interface management risks. Contractors, technical interfaces, mechanical equipment, and environmental factors are the primary direct causal factors of accidents, while owners and designers are essential indirect causal factors. The global importance of stakeholders such as owners, designers, and supervisors rises significantly after considering the indirect correlations between factors. This theoretically explains the need to consider the interactions between interface management risks.

Originality/value

The interaction mechanism between interface management risks is unclear, which is an essential factor influencing the decision of risk response measures. This study proposes a new methodology for analyzing interface management risk response strategies that incorporate quantitative analysis methods and considers the interaction of interface management risks.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 14 February 2024

Tiep Nguyen, Nicholas Chileshe, Duc Ty Ho, Viet Thanh Nguyen and Quang Phu Tran

Urban rail projects are typically large-scale transport infrastructure projects (megaprojects) which have many potential risks that can influence the strategic goals of owners…

Abstract

Purpose

Urban rail projects are typically large-scale transport infrastructure projects (megaprojects) which have many potential risks that can influence the strategic goals of owners. However, there is a paucity of studies which explore the impact of risks on both “urban rail” project time and cost together considering quantitative assessments. Therefore, this paper focuses on investigating critical risks and quantifying such risk impacts on urban railway project schedule and cost in practice.

Design/methodology/approach

A combination of qualitative and quantitative research methods comprising semi-interviews with five experts and a questionnaire survey of 132 professional respondents is used. The data were modeled using Monte Carlo Simulation to predict the probability of project schedule and cost.

Findings

The results show that 30 risk variables are categorized into seven main groups which have significant impacts on both project time and cost. Outstanding five risk variables were highlighted as follows: (1) project site clearance and land compensation; (2) design changes; (3) physical project resources; (4) contractors’ competencies and (5) project finance. Such findings were supported by Monte Carlo simulation which predicted in the worst case that the project may suffer 11.03 months’ delays and have cost overrun with a contingency of US$287.68 million.

Originality/value

This study expands our knowledge about time and cost contingency of urban metro railway implementation across developing economies and particularly within the context of Vietnam. Policymakers will not only gain an understanding about risk structure but will also recognize the significant impacts of critical risk through risk impact modeling and simulation. Such an approach provides insights into risk treatment priorities for planners so that they can proactively establish suitable strategies for risk mitigation in practice.

Details

Built Environment Project and Asset Management, vol. 14 no. 2
Type: Research Article
ISSN: 2044-124X

Keywords

Content available
Book part
Publication date: 25 March 2024

Eleanor Ross

Abstract

Details

Communicating Climate
Type: Book
ISBN: 978-1-83753-643-6

Article
Publication date: 28 March 2024

Nikesh Nayak, Pushpesh Pant, Sarada Prasad Sarmah and Raj Tulshan

Logistics sector is recognized as one of the core enablers of the economic development of a nation. However, inefficiency in logistics operations impedes the achievement of…

Abstract

Purpose

Logistics sector is recognized as one of the core enablers of the economic development of a nation. However, inefficiency in logistics operations impedes the achievement of intended targets by increasing the cost of doing business. Also, it is difficult to improve the efficiency of a country’s logistics operations without a metric for evaluating and understanding logistics capabilities and efficiency. Therefore, the present study has developed In-country Logistics Performance Index (ILP Index) to propose a benchmarking tool to measure the in-country logistics competitiveness, particularly in the setting of emerging economies, i.e. India.

Design/methodology/approach

This study has developed a unified index using principal component analysis and quintile approach. In addition, the proposed index relies on several dimensions that are developed and illustrated using quantitative secondary panel data.

Findings

The findings of this study reveal that the quality of infrastructure, economy, and telecommunications are the three most important dimensions that may significantly support the growth of the transportation and logistics sector. The results reveal that Gujarat, Tamil Nadu, and Maharashtra are the top performers whereas, Bihar, Jharkhand, and Jammu and Kashmir scores the least due to the insufficient logistics infrastructure as compared to other Indian states.

Originality/value

Given the extensive focus on international-level logistics index (like World Bank’s LPI) in the existing literature, this study intends to develop in-country logistics index to evaluate the logistics capabilities at the regional and state level. In addition, unlike prior studies, this study utilizes quantitative secondary data to eliminate cognitive and opinion bias. Moreover, this benchmarking tool would assist decision-makers in idealizing standard practices toward sustainable logistics operations. Additionally, the ILP index could serve the international investors in crucial decision-making, as it provides valuable insights into a country’s logistics readiness, influencing their investment choices and trade preferences. Finally, the proposed approach is adaptable to measuring the overall performance of any other industry/economy.

Details

International Journal of Productivity and Performance Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1741-0401

Keywords

Article
Publication date: 25 March 2024

Francis Nuako, Frank Ato Ghansah and Thomas Adusei

It is widely accepted that one criterion for determining if a construction project is successful is whether it is completed within the expected budget. There have been…

Abstract

Purpose

It is widely accepted that one criterion for determining if a construction project is successful is whether it is completed within the expected budget. There have been advancements in the management of building projects throughout time but cost overruns remain a key concern in the construction sector internationally, particularly in emerging economies such as Ghana. This study aims to answer the question, “What are the critical success factors (CSFs) that can assist reduce cost overruns in public sector infrastructure projects in the Ghanaian construction industry?”

Design/methodology/approach

This study used a quantitative survey method. The questionnaire was pre-tested by interviewing 15 contractors to ascertain the validity of the content. Factor analysis and multiple regression were adopted to analyze the data.

Findings

This study discovered that the critical factors that can reduce cost overruns in construction projects in Ghana are directly linked to five themes: early contractor involvement in the project planning stage, adequate funding, good project team relations, competent managers/supervisors and project participant incentives/bonuses. This study identifies indestructible, empirically measurable important success criteria for reducing cost overruns in public building projects in Ghana.

Practical implications

When well thought through from the project initiation stage to completion, these critical successes can also be used to deal with damaging economic effects such as allocative inefficiency of scarce resources, further delays, contractual disputes, claims and litigation, project failure and total abandonment.

Originality/value

The uniqueness of this research resides in the fact that it is, to the best of the authors’ knowledge, a first-of-its-kind investigation of the CSFs for reducing cost overruns in public building projects in developing countries.

Details

Construction Innovation , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1471-4175