Article
Publication date: 15 December 2022

Cong Wang, Henry Liu, Michael C.P. Sing and Jin Wu

Pre-construction of a project comprises stages that are pivotal for the procurement performance. It is defined as the duration from the project's initiation to construction…

Abstract

Purpose

Pre-construction of a project comprises stages that are pivotal for the procurement performance. It is defined as the duration from the project's initiation to construction. However, Private Public Partnerships (PPPs) have been subjected to a long pre-construction, thereby leading to an inefficient development process. Therefore, the purpose of this paper is to pay attention to the influencing factors elongating the pre-construction duration.

Design/methodology/approach

Based on data of 5,677 PPP projects between 2009 and 2021 in China, the authors adopt the Accelerated Failure Time (AFT) model in duration analysis to empirically analyze the following underlying dynamics determining the duration of PPP pre-construction stages: (1) policy uncertainty; (2) corruption; and (3) procurement method selection. To observe the influencing paths more specifically, the authors divided the pre-construction duration into the pre-tendering period and tendering period and regressed them separately.

Findings

The results indicate that the pre-construction duration is significantly prolonged with increased policy uncertainty and corruption degree as well as the use of tendering methods. Meanwhile, the above factors have a greater impact on the pre-tendering period than the tendering period.

Originality/value

The contribution of this study is twofold: (1) theoretically, this paper provides new evidence on the impact of PPP policy uncertainty, corruption and procurement method selection on the pre-construction duration. It complements empirical studies on the factors elongating the time efficiency of PPPs projects. (2) In practice, it provides a specific path for the government to improve the time efficiency of PPPs.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 4
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 28 June 2023

Nur Faiza Ishak and Vinesh Thiruchelvam

The purpose of this study is to discuss policy review in the interest of sustainable innovations in Malaysia’s public procurement. This study also offers the overall relationship…

1926

Abstract

Purpose

The purpose of this study is to discuss policy review in the interest of sustainable innovations in Malaysia’s public procurement. This study also offers the overall relationship between existing policies related to sustainable innovations in public procurement and the coherences towards the four dimensions of sustainable innovations.

Design/methodology/approach

This study outlines the current policies in Malaysia which are related to sustainable innovation initiatives and explores the cohesiveness that appears disconnected and understood separately. Policy content analysis is conducted on the current policies related to sustainable innovations in the context of Malaysia’s public procurement.

Findings

This study observed that the current policies related to sustainable innovations in public procurement are actually interconnected with each other through a hierarchical framework. This study also demonstrates that the 12th Malaysia Plan has comprehensively encompassed every aspect of the environment, social, economic and innovation to contribute to one primary goal – green economic growth.

Research limitations/implications

The proposed policy framework is expected to be beneficial for the administrator executive among the civil servant to connect the independent policies and, at the same time, contribute to the overall goal of green economic growth. Through a broad policy structure too, this study helps the industry player to recognize their potential in any area related to sustainable innovation.

Originality/value

The policy framework illustrated is new to the literature, especially in Malaysia’s context. The compilation of current policy grounded by the 12th Malaysia Plan has not been presented in any publications.

Article
Publication date: 12 February 2024

Udara Willhelm Abeydeera Lebunu Hewage, Jayantha Wadu Mesthrige and Eric G. Too

This study explores the current status of risk management (RM) in Sri Lanka and the obstacles in implementing RM in Sri Lankan small construction projects.

Abstract

Purpose

This study explores the current status of risk management (RM) in Sri Lanka and the obstacles in implementing RM in Sri Lankan small construction projects.

Design/methodology/approach

The current research study adopted a quantitative research method. Using a purposeful sampling strategy, 100 construction companies engaged in small construction projects in Sri Lanka were selected and a questionnaire was distributed among top managerial employees of these companies. Employees belonging to 47 companies responded to the survey which provided information relating to 812 construction projects. The collected data were analyzed using the RM implementation index (RMII) and other quantitative measures such as mean, median and percentages.

Findings

The research findings indicated that RM incorporation was at a lower degree in small construction projects in Sri Lanka. The findings further indicated that RM incorporation was relatively high in the public construction projects compared to the private construction projects. The main obstacles identified through the survey for RM implementation were: “lack of funding”, “lack of time”, “low profit margin”, “not economical” and “lack of knowledge”.

Research limitations/implications

The study was limited to exploring RM implementation in small construction projects in Sri Lanka. The study was limited to the building construction companies under the 150-million-rupee (approx. below 450,000 USD) financial limit registered with the construction industry development authority in Sri Lanka.

Originality/value

RM in small construction projects in developing countries is a relatively less explored domain. Sri Lankan construction industry is another relatively less explored domain in terms of new management technique implementation such as RM and value management. The quantitative approach used for the study revealed that RM implementation is at a lower degree in the small construction projects. Moreover, several obstacles pertaining to RM implementation were recognized through this study. These findings will be useful for the construction stakeholders to overcome the recognized barriers and effectively use RM in their respective construction projects.

Details

Built Environment Project and Asset Management, vol. 14 no. 2
Type: Research Article
ISSN: 2044-124X

Keywords

Open Access
Article
Publication date: 21 July 2022

Anna-Therése Järvenpää, Johan Larsson and Per Erik Eriksson

This paper aims to identify how a public client’s use of control systems (process, output and social control) affect innovation possibilities in construction projects.

Abstract

Purpose

This paper aims to identify how a public client’s use of control systems (process, output and social control) affect innovation possibilities in construction projects.

Design/methodology/approach

Semi-structured interviews about six infrastructure projects were conducted to identify respondents’ views on innovation possibilities. These possibilities were then analyzed from an organizational control perspective within principal–agent relationships between the Swedish Transport Administration (STA) and their contractors.

Findings

How the client uses control systems affects innovation possibilities. Relying on process control could negatively affect innovation opportunities, whereas output control could have a positive influence. In addition, social control seems to have a weak effect, as the STA appears not to use social control to facilitate joint innovation. Public clients must comply with the Public Procurement Act and, therefore, retain the requirements specified in the tendering documents. Much of the steering of the execution is connected to the ex ante phase (before signing the contract), which affects innovation possibilities in the design and execution phases for the contractor.

Research limitations/implications

This study was conducted with only one client, thus limiting its generalizability. However, the findings provide an important stepping stone to further investigation into balancing control systems and creating innovation possibilities in a principal–agent relationship.

Originality/value

Although public procurement has increasingly been emphasized as a major potential source of innovation, studying how a public client’s use of organizational control systems affects innovation possibilities in the construction sector has received scant attention.

Details

Construction Innovation , vol. 24 no. 7
Type: Research Article
ISSN: 1471-4175

Keywords

Open Access
Article
Publication date: 2 April 2024

Șerban Filipon and Violeta Simionescu

Competency frameworks can support public procurement capacity development and performance. However, literature on connecting professionalisation with national procurement contexts…

Abstract

Purpose

Competency frameworks can support public procurement capacity development and performance. However, literature on connecting professionalisation with national procurement contexts is limited. This paper aims to explain and conceptualise recent Romanian experience with developing bespoke competency frameworks at national level for public procurement that reflect the features of the Romanian public procurement system. The approach used could guide in broad-brush, mutatis mutandis, other (national) public procurement systems with comparable features, mainly those seeking a shift from a rather administrative function of public procurement towards a strategic function.

Design/methodology/approach

This case study reflects on the methodology used for analysing the Romanian public procurement environment in EU context to develop bespoke professionalisation instruments, and on ways to integrate competency management approaches in Romanian public procurement culture. That methodological mix has been mainly qualitative and constructionist, within an applied research approach. It combined desk research with empirical research and included legal research in this context.

Findings

A principled, methodological and pragmatic approach tailored to the procurement environment in question is essential for developing competency frameworks capable to resonate to and address the specific practical needs of that procurement system.

Social implications

Competency frameworks can uphold societal objectives through public procurement.

Originality/value

Using valuable insights into the development of the Romanian public procurement competency frameworks, the paper provides a conceptual framework for instilling competency management approaches to public procurement professional development where the latter is governed by a rather distinct, public administration, paradigm. This conceptual framework can guide other public procurement systems and stimulate further research.

Expert briefing
Publication date: 18 April 2024

First cases pursued under the FSR show it could be one of the most far-reaching of the strategic autonomy measures introduced under this Commission. One Chinese company has…

Article
Publication date: 8 April 2024

Malik Lakshan Hasantha, Anuradha Samarajeewa Waidyasekara and Hasith Chathuranga Victar

Insufficient time allocation for the bidding period occurs, causing drawbacks to both parties, the client and the bidder. Hence, this study aims to evaluate the time allocated for…

Abstract

Purpose

Insufficient time allocation for the bidding period occurs, causing drawbacks to both parties, the client and the bidder. Hence, this study aims to evaluate the time allocated for preparing a bid proposal as per the National Competitive Bidding (NCB) in the Sri Lankan context.

Design/methodology/approach

The study has adopted a mixed method approach and expert interviews and document review to detect, analyse and validate the issues, and solutions based on NCB along with the adequacy of the allocated bidding period used as main data collection tools. Both qualitative and quantitative data were analysed through manual content analysis and inferential analysis respectively.

Findings

Overall, 24 local issues with the existing competitive bidding process and solutions for each were identified. Among the 24 local issues, it was unanimously agreed by all interviewees that three specific issues require attention and improvement. These issues are related to the standard and incompleteness of bidding documents, inaccurate BOQ quantities measured by the consultant or the main contractor, and the excessive number of bidding document amendments by the consultant. It was revealed that a maximum of 42 calendar days (6 weeks) is sufficient for the bidding process while a minimum of 21 calendar days (3 weeks) is insufficient.

Originality/value

The findings of this study would be recommended that Information and Communication Technology Agency (ICTA) understand the necessity of revising the NCB reference to the time allocated for the preparation of bids. By recognising the importance of sufficient time allocation for bid preparation, this research serves as a practical guide for authorities involved in policy formulation, aiding them in implementing revisions that align with the dynamic requirements of bidding procedures.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 27 March 2024

Valentina Patetta and Marta Enciso-Santocildes

The aim of this paper is to provide insights and knowledge about the motivations and implications for social enterprises' participation in SIBs, particularly in terms of…

Abstract

Purpose

The aim of this paper is to provide insights and knowledge about the motivations and implications for social enterprises' participation in SIBs, particularly in terms of collaboration and partnership with the public sector, as well as the different positions on this issue. The overall aim, therefore, is to show how social enterprises and public organisations have interacted in the context of SIBs and what has been achieved by participating.

Design/methodology/approach

This multiple case study approach applies qualitative methods like observations and semi-structured and unstructured interviews.

Findings

The study shows that SIBs can be an option for financing social enterprises within a strategy of income diversification and resource dependency. Despite tensions and complexities, SIBs can renew the traditional funding relationship by adding innovation, strengthening the co-creation process and creating a stable relationship.

Research limitations/implications

Research findings may lack generalisability due to the specific context in which the case study is rooted.

Practical implications

The paper offers practical implications in terms of insights and suggestions for social enterprises and the public sector interested in developing the scheme.

Originality/value

This paper adds the voice and perspective of social enterprises on the relationship with the public sector within the framework of SIBs initiatives.

Details

International Journal of Public Sector Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0951-3558

Keywords

Open Access
Article
Publication date: 9 November 2023

Abdulmohsen S. Almohsen, Naif M. Alsanabani, Abdullah M. Alsugair and Khalid S. Al-Gahtani

The variance between the winning bid and the owner's estimated cost (OEC) is one of the construction management risks in the pre-tendering phase. The study aims to enhance the…

Abstract

Purpose

The variance between the winning bid and the owner's estimated cost (OEC) is one of the construction management risks in the pre-tendering phase. The study aims to enhance the quality of the owner's estimation for predicting precisely the contract cost at the pre-tendering phase and avoiding future issues that arise through the construction phase.

Design/methodology/approach

This paper integrated artificial neural networks (ANN), deep neural networks (DNN) and time series (TS) techniques to estimate the ratio of a low bid to the OEC (R) for different size contracts and three types of contracts (building, electric and mechanic) accurately based on 94 contracts from King Saud University. The ANN and DNN models were evaluated using mean absolute percentage error (MAPE), mean sum square error (MSSE) and root mean sums square error (RMSSE).

Findings

The main finding is that the ANN provides high accuracy with MAPE, MSSE and RMSSE a 2.94%, 0.0015 and 0.039, respectively. The DNN's precision was high, with an RMSSE of 0.15 on average.

Practical implications

The owner and consultant are expected to use the study's findings to create more accuracy of the owner's estimate and decrease the difference between the owner's estimate and the lowest submitted offer for better decision-making.

Originality/value

This study fills the knowledge gap by developing an ANN model to handle missing TS data and forecasting the difference between a low bid and an OEC at the pre-tendering phase.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 13
Type: Research Article
ISSN: 0969-9988

Keywords

Abstract

Purpose

Competency frameworks can support public procurement capacity development and performance. However, literature on connecting professionalisation with national procurement contexts is limited. This paper aims to explain and conceptualise recent Romanian experience with developing bespoke competency frameworks at national level for public procurement that reflect the features of the Romanian public procurement system. The approach used could guide in broad-brush, mutatis mutandis, other (national) public procurement systems with comparable features, mainly those seeking a shift from a rather administrative function of public procurement towards a strategic function.

Design/methodology/approach

This case study reflects on the methodology used for analysing the Romanian public procurement environment in EU context to develop bespoke professionalisation instruments, and on ways to integrate competency management approaches in Romanian public procurement culture. That methodological mix has been mainly qualitative and constructionist, within an applied research approach. It combined desk research with empirical research and included legal research in this context.

Findings

A principled, methodological and pragmatic approach tailored to the procurement environment in question is essential for developing competency frameworks capable to resonate to and address the specific practical needs of that procurement system.

Social implications

Competency frameworks can uphold societal objectives through public procurement.

Originality/value

Using valuable insights into the development of the Romanian public procurement competency frameworks, the paper provides a conceptual framework for instilling competency management approaches to public procurement professional development where the latter is governed by a rather distinct, public administration, paradigm. This conceptual framework can guide other public procurement systems and stimulate further research.