Article
Publication date: 12 July 2023

Augustine Senanu Komla Kukah, De-Graft Owusu-Manu, Edward Badu, David J. Edwards and Eric Asamoah

Public-private partnership (PPP) power projects are associated with varying risk factors. This paper aims to develop a fuzzy quantitative risk allocation model (QRAM) to guide…

Abstract

Purpose

Public-private partnership (PPP) power projects are associated with varying risk factors. This paper aims to develop a fuzzy quantitative risk allocation model (QRAM) to guide decision-making on risk allocation in PPP power projects in Ghana.

Design/methodology/approach

A total of 67 risk factors and 9 risk allocation criteria were established from literature and ranked in a two-round Delphi survey using questionnaires. The fuzzy synthetic evaluation method was used in developing the risk allocation model.

Findings

The model’s output variable is the risk allocation proportions between the public body and private body based on their capability to manage the risk factors. Out of the 37 critical risk factors, the public sector was allocated 12 risk factors with proportions = 50%, while the private sector was allocated 25 risk factors with proportions = 50%.

Originality/value

To the best of the authors’ knowledge, this research presents the first attempt in Ghana at endeavouring to develop a QRAM for PPP power projects. There is confidence in the model to efficiently allocate risks emanating from PPP power projects.

Details

Journal of Financial Management of Property and Construction , vol. 29 no. 1
Type: Research Article
ISSN: 1366-4387

Keywords

Article
Publication date: 27 July 2022

Augustine Senanu Komla Kukah, De-Graft Owusu-Manu, Edward Badu and David John Edwards

Demand for private investment in infrastructure, notably in the power sector remains high, and this is anticipated to expand with the passage of time. Very little research…

Abstract

Purpose

Demand for private investment in infrastructure, notably in the power sector remains high, and this is anticipated to expand with the passage of time. Very little research currently exists on the power sector and specifically the private sector influencing factors (PSIFs) for entering into public–private partnerships (PPPs). The purpose of this study is to explore influencing factors for private sector participation in PPP power projects in Ghana.

Design/methodology/approach

Using purposive and snowball sampling techniques, questionnaires were used to gather responses from experts in the PPP power sector domain in a two-round Delphi survey. Reliability analysis was conducted using Cronbach’s alpha coefficient and level of agreement tested using Kendall’s concordance. Mean score ranking, analysis of variance (ANOVA) and Chi-square test were the main analysis conducted on the influencing factors.

Findings

The most significant PSIFs were: obtaining of investment support; improvement in private sector’s international image; synergy with public sector; sharing of risks; and gaining of profits. From ANOVA results, all the influencing factors had no significant different perception between the number of years in PPP practice and the motivations for the private sector entering into PPP power projects. Using Chi-square, the association between the variables indicated they were statistically significant.

Practical implications

The findings in this study are significant for multinational power generation firms that seek to enter the Ghanaian energy sector to help fill the generation gap and deficit.

Originality/value

The output of this research contributes to the checklist of influencing factors for private sector participation in PPP power projects and enhances the development of PPP practice.

Details

Journal of Facilities Management , vol. 22 no. 2
Type: Research Article
ISSN: 1472-5967

Keywords

Article
Publication date: 28 November 2022

Jiaqi Liu and Jicai Liu

This paper aims to determine the demand category and level of government and investors in public–private partnership (PPP) projects. It emphasizes the importance of meeting the…

Abstract

Purpose

This paper aims to determine the demand category and level of government and investors in public–private partnership (PPP) projects. It emphasizes the importance of meeting the demands of stakeholders and controlling the unreasonable demands. This study aims to improve the demand management of stakeholders in the PPP project and lay a foundation for the research on behavior based on the motivation theory.

Design/methodology/approach

This paper opted for a questionnaire survey to collect data based on indicators identified through literature. The participants come from the government and private sector (investors, contractors, operators, etc.) in China PPP Lecture Hall. The reliability, validity and variance analyses are used to test the reliability of data. Factor analysis and entropy method are used to determine demand categories and weights.

Findings

The government’s 14 demands are divided into four groups: satisfy public activities, self-interest, responsibility and relief financial pressure; 6 investor's demands are divided into development ability and satisfy social activities. The self-interest of government is higher than that of the publicity in PPP projects; investor's social reputation is most important, it is a foundation for obtaining external resources and achieving enterprise development.

Research limitations/implications

Because of the chosen research approach, the demand indexes cannot be exhausted. Therefore, researchers are encouraged to enrich relevant contents further.

Practical implications

This paper includes implications for a targeted demand control mechanism and for managing the unreasonable demand.

Originality/value

This paper comprehensively identifies the demand hierarchy of the government and investors, and provides the theoretical basis for the target management of stakeholders.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 4
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 15 December 2022

Cong Wang, Henry Liu, Michael C.P. Sing and Jin Wu

Pre-construction of a project comprises stages that are pivotal for the procurement performance. It is defined as the duration from the project's initiation to construction…

Abstract

Purpose

Pre-construction of a project comprises stages that are pivotal for the procurement performance. It is defined as the duration from the project's initiation to construction. However, Private Public Partnerships (PPPs) have been subjected to a long pre-construction, thereby leading to an inefficient development process. Therefore, the purpose of this paper is to pay attention to the influencing factors elongating the pre-construction duration.

Design/methodology/approach

Based on data of 5,677 PPP projects between 2009 and 2021 in China, the authors adopt the Accelerated Failure Time (AFT) model in duration analysis to empirically analyze the following underlying dynamics determining the duration of PPP pre-construction stages: (1) policy uncertainty; (2) corruption; and (3) procurement method selection. To observe the influencing paths more specifically, the authors divided the pre-construction duration into the pre-tendering period and tendering period and regressed them separately.

Findings

The results indicate that the pre-construction duration is significantly prolonged with increased policy uncertainty and corruption degree as well as the use of tendering methods. Meanwhile, the above factors have a greater impact on the pre-tendering period than the tendering period.

Originality/value

The contribution of this study is twofold: (1) theoretically, this paper provides new evidence on the impact of PPP policy uncertainty, corruption and procurement method selection on the pre-construction duration. It complements empirical studies on the factors elongating the time efficiency of PPPs projects. (2) In practice, it provides a specific path for the government to improve the time efficiency of PPPs.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 4
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 2 January 2024

Andreas Wibowo

This paper delves into the ex ante rates of return demanded by the private sector in Indonesian public–private partnership (PPP) infrastructure projects and the manifold factors…

Abstract

Purpose

This paper delves into the ex ante rates of return demanded by the private sector in Indonesian public–private partnership (PPP) infrastructure projects and the manifold factors emanating from project attributes that can influence these rates.

Design/methodology/approach

This paper analyzes feasibility studies of 37 PPP projects across different sectors. The studies were carefully selected based on relevance, completeness and validity of data. The analysis uses statistical techniques, including Levene’s tests, t-tests, ANOVA tests, Cohen’s effect size and Pearson correlations, to explore differences in cost of capital and excess returns across various attributes.

Findings

Based on the statistical analysis, no significant difference exists between the excess return of 200 basis points (bps) and the equity excess return of 0 bps. This suggests that the eligibility criteria for PPP projects require an internal rate of return (IRR) equal to the weighted average cost of capital plus 200 bps or an equity IRR equal to the cost of equity. The variations in the tested variables among diverse project attributes do not exhibit statistically significant disparities, even though specific attributes display moderate to high effect sizes.

Originality/value

This paper represents one of the first attempts to examine the rates of return demanded by the private sector in the context of Indonesian PPP projects. It comprehensively explores the factors that influence these rates, drawing on insights derived from feasibility studies.

Details

Built Environment Project and Asset Management, vol. 14 no. 2
Type: Research Article
ISSN: 2044-124X

Keywords

Abstract

Details

A Neoliberal Framework for Urban Housing Development in the Global South
Type: Book
ISBN: 978-1-83797-034-6

Abstract

Details

A Neoliberal Framework for Urban Housing Development in the Global South
Type: Book
ISBN: 978-1-83797-034-6

Article
Publication date: 26 March 2024

Neeru Bhooshan, Amarjeet Singh, Akriti Sharma and K.V. Prabhu

The role of Technology Transfer Units, examined in this study, was found to be vital to expedite the process of disseminating new varieties and their production technology.

Abstract

Purpose

The role of Technology Transfer Units, examined in this study, was found to be vital to expedite the process of disseminating new varieties and their production technology.

Design/methodology/approach

A total of 1,000 households were surveyed in the sampled states. A probit model was used to analyse.

Findings

Age, education, land holding, tractor use and number of working family members in agriculture were found to significantly affecting adoption of the new seed varieties. Technology transfer through licensing has impacted the adoption of new seed varieties positively by highlighting Punjab possessing the highest adoption and western Uttar Pradesh was majorly adopting the old variety.

Research limitations/implications

The authors believed in farmers’ memory to recall the varietal information of wheat.

Practical implications

The study recommended various incentives to attract the seed industry in UP to minimize the economic loss potentially suffered by them.

Social implications

Quality seeds are germane to increase the productivity of crops, and it is paramount to disburse the seed varieties to the end users in an efficient way to achieve the overall objective of productivity enhancement.

Originality/value

In this context, a study was conducted in three states of India, namely, Punjab, Haryana and Uttar Pradesh (UP) to find out the adoption rate of newly developed varieties of wheat, HD 3086 after three years (2014–2015) of its commercialization by IARI as well as HD 2967, which was released in 2011.

Details

Journal of Science and Technology Policy Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 2053-4620

Keywords

Article
Publication date: 29 February 2024

Mala Ali Modu, Maimunah Sapri and Zafirah Ab Muin

The provision of facilities management (FM) services, facilitated by a well-suited sourcing strategy, significantly influences the optimization of dwelling unit performance…

Abstract

Purpose

The provision of facilities management (FM) services, facilitated by a well-suited sourcing strategy, significantly influences the optimization of dwelling unit performance, augmentation of occupants’ living experiences and the establishment of a secure and comfortable environment. Consequently, this study aims to examine the sourcing approach used for delivering FM services in social housing within Nigeria’s semi-arid climate and to assess the effectiveness of the chosen sourcing approach in the provision of FM services.

Design/methodology/approach

Data collection involved one-on-one interviews conducted with five principal/senior staff members of the Borno State Housing Corporation in Maiduguri, Northern Nigeria. For data analysis, the NVivo R1 software package and Stata 13.0 were used. Thematic analysis was applied to the data, and the findings were presented through narrations and direct quotes from participants. Logistic regression analysis was subsequently used to assess the effectiveness of the adopted in-house approach in providing FM services in the context of social housing.

Findings

Administrators of social housing in the semi-arid climate of Nigeria exclusively adopted an in-house sourcing approach for providing FM services. Nevertheless, the in-house approach was conclusively determined to be ineffective in delivering FM services within the specific context of social housing in the semi-arid climate of Nigeria.

Originality/value

This investigation centred on examining the sourcing strategy used by social housing administrators for delivering FM services in social housing within a semi-arid climate of Nigeria. Additionally, the study delved into evaluating the efficacy of the chosen sourcing approach in the actual provision of FM services.

Details

Facilities , vol. 42 no. 5/6
Type: Research Article
ISSN: 0263-2772

Keywords

Article
Publication date: 26 March 2024

Duc-Anh Le, Chau Ngoc Dang, Long Le-Hoai and Viet Quoc Hoang

Official development assistance (ODA) education projects have played a crucial role in improving education and training fields in developing countries, but are often facing…

Abstract

Purpose

Official development assistance (ODA) education projects have played a crucial role in improving education and training fields in developing countries, but are often facing several considerable challenges (e.g. long implementation time). Thus, this study aims to identify critical success factors (CSFs) in ODA education projects and investigate the influences of CSFs on ODA project performance measured by 11 nonprofit outcomes (NPOs).

Design/methodology/approach

A comprehensive literature review and expert interviews were conducted to compile a list of 35 potential success factors for ODA education projects. Using a survey questionnaire, 143 valid responses were collected from practitioners joining ODA projects in Vietnam. Various statistical methods (e.g. mean score method, Spearman rank correlation test, analysis of variance test, factor analysis and regression analysis) were used to analyze the collected data.

Findings

This research identified seven CSFs for ODA education projects in Vietnam: comprehensive project management competency (C1), clarity and compliance in project execution (C2), transparency and committed funding (C3), external context conditions (C4), well-controlled design and project management procedures (C5), preparations in equipment and complexity insight (C6) and punctual site delivery (C7). Furthermore, the results of regression analysis indicated that comprehensive project management competency (C1) and transparency and committed funding (C3) could significantly affect various NPOs.

Originality/value

This study offers significant insights for practitioners (e.g. project managers) to improve ODA projects’ performance and effectiveness in the education and training sector of a developing country context (like Vietnam).