Open Access
Book part
Publication date: 1 May 2019

Marco A. Bragadin and Kalle Kähkönen

This paper is based on research addressing quality of construction schedules. The paper aims to structure a Schedule Health Assessment method and present it as a means to carry…

Abstract

Purpose

This paper is based on research addressing quality of construction schedules. The paper aims to structure a Schedule Health Assessment method and present it as a means to carry out the evaluation of construction schedules.

Design/Methodology/Approach

The development of the Schedule Health assessment method can be characterised as constructive research. The structuring of the method is based on analysis of factors forming the overall quality of construction schedules. The method has been tested in a proof of concept study. This comprised a case study in which four master schedules developed by junior production managers were evaluated using the Schedule Health assessment method.

Findings

It is possible to construct a method for the quality evaluation of construction schedules.

Research Limitations/Implications

The completed testing is still rather limited since it is based merely on experiences of junior production managers with a single case.

Practical Implications

The Schedule Health assessment method can in a useful manner make the quality evaluation of construction schedules easy to approach and effective process.

Originality/Value

This research has produced a novel method for the quality evaluation of construction schedules.

Details

10th Nordic Conference on Construction Economics and Organization
Type: Book
ISBN: 978-1-83867-051-1

Keywords

Content available
Book part
Publication date: 13 November 2018

Lana Kay Coble

Abstract

Details

Collaborative Risk Mitigation Through Construction Planning and Scheduling
Type: Book
ISBN: 978-1-78743-148-5

Content available
Book part
Publication date: 13 November 2018

Lana Kay Coble

Abstract

Details

Collaborative Risk Mitigation Through Construction Planning and Scheduling
Type: Book
ISBN: 978-1-78743-148-5

Open Access
Article
Publication date: 21 May 2018

Parvaneh Shahsavand, Akbar Marefat and Majid Parchamijalal

The purpose of this paper is to reveal the main causes of delays in the projects are from the client (relative importance index (RII)=0.716), labor and equipment (RII=0.701) and…

45453

Abstract

Purpose

The purpose of this paper is to reveal the main causes of delays in the projects are from the client (relative importance index (RII)=0.716), labor and equipment (RII=0.701) and contractor (RII=0.698). Hence determining the contractual responsibility of delay is the most likely source of dispute in construction projects and many techniques have been used in the courts to demonstrate the criticalities of a delay event on the project schedule. Therefore, authors try to investigate all process-based techniques of delay claims and evaluated and conformed them with principles by Society of Construction Law (SCL) protocol and Association for the Advancement of Cost Engineering International (AACEI) in order to choose the best techniques based on the specific circumstances of each project.

Design/methodology/approach

This section is divided into two distinct parts: refers to the methods used to assess the perceptions of clients, consultants, and contractors on the relative importance of causes of delay in construction industry; and refers to advantages and disadvantages of various techniques used to analyze delays and their conform with SCL protocol. A questionnaire was developed to assess the perceptions of clients, consultants, and contractors on the relative importance of causes of delay in Iranian construction industry. The respondents were asked to indicate their response category on 78 well-recognized construction delay factors identified by authors.

Findings

In total, 78 causes of delay were identified through research. The identified causes are combined into seven groups. The field survey included 58 contractors, 55 consultants, and 62 client. Data collected were analyzed by RII and Statistical Package for Social Sciences (SPSS). The authors identified main causes of delay and ten most important causes, according to Table AII, from the perspective of three major groups of participants (clients, consultants and contractors). The ranking of categories of causes of delay, according to Table I, were: client-related causes (RII=0.716); labor and equipment category causes (RII=0.701); contractor-related causes (RII=0.698); material-related causes (RII=0.690); design-related causes (RII=0.666); external causes (RII=0.662); and consultant-related causes (RII=0.662). But according to the discussions and given that determining the contractual responsibility of delay is the most likely source of dispute in construction industry and many techniques have been used in the courts to demonstrate the criticalities of a delay event on the project schedule.

Originality/value

All process-based techniques of delay analysis have been present in this paper and categorized in 11 groups. In order to understand the advantages and disadvantages of them by clients, contractor and consultant, a thorough review conducted to reveal the nature of techniques. In the next step, given that selecting the most appropriate technique based on constraints and specific conditions of each project is one of the most important steps to carry out a successful delay analysis. The authors conformed, all process-based techniques of delay analysis, by SCL protocol and AACEI principles. Finally, the result of this match was brought in order to choose the best technique based on the specific circumstances of each project.

Details

Engineering, Construction and Architectural Management, vol. 25 no. 4
Type: Research Article
ISSN: 0969-9988

Keywords

Open Access
Article
Publication date: 31 May 2022

Kari-Pekka Tampio and Harri Haapasalo

The purpose of this paper is to identify the areas and logic of integration of different stakeholders using different methods and to analyse their applicability and challenges in…

1041

Abstract

Purpose

The purpose of this paper is to identify the areas and logic of integration of different stakeholders using different methods and to analyse their applicability and challenges in practical projects. The main aim is to describe how these different methods impact value creation.

Design/methodology/approach

Action design research was carried out in a large hospital construction project where the first author acted as an “involved researcher” and the second author acted as an “outside researcher”. Two workshops were organised to evaluate the direct and indirect challenges and benefits of the applied four methods and to explain how different methods enable value creation.

Findings

All the studied methods provide good results in terms of usability and commitment to the aims of the project, thus delivering the direct benefits expected. Process, people and tools logic works well in this case project when applying the methods properly. Significant evidence was provided on secondary deliverables of the methods, and all analysed methods had a significant impact in the area of leading people, clarifying what “focus on people” means and how it is enabled.

Practical implications

Focus on people can be achieved through different operative methods if applied in the right way. It is necessary to select the most suitable methods based on all the direct and indirect deliverables.

Originality/value

This case project offered a platform to analyse integration methods in a real-life project using the collaborative contract method. The authors were able to participate in the analysis by taking action from the very beginning of the project in terms of training, learning, continuous development and coaching of these methods and evaluating the applicability.

Details

Construction Innovation , vol. 24 no. 7
Type: Research Article
ISSN: 1471-4175

Keywords

Open Access
Book part
Publication date: 1 May 2019

Gunnar Lucko and Yi Su

Construction projects operate within a risky environment. It materialises as delays, which must be prevented or mitigated to avoid becoming amplified into late completion. But…

Abstract

Purpose

Construction projects operate within a risky environment. It materialises as delays, which must be prevented or mitigated to avoid becoming amplified into late completion. But previous research has largely ignored how structural complexity of the underlying network schedules shapes their resilience.

Design/Methodology/Approach

This research hypothesizes that schedule structure plays a vital role in its ability to absorb or propagate delays. The impact of activity-level local risk factors is represented via activity duration distributions, i.e. probability density functions. The impact of project-level global risk factors is more challenging because they arise via interactions between multiple activities.

Findings

Modelling resilience to local and global risk factors can employ a matrix approach. Simulation shows that delay amplification depends on local structure, not global complexity.

Research Limitations/Implications

Criticality had merely relied upon a single deterministic analysis of a network schedule to categorize activities as having zero or nonzero float from fixed relative duration a dependency structure. Repeated probabilistic analysis with sampled durations gives criticality indices of activities. This research limits itself to network schedules with point-wise relations between activities.

Practical Implications

Managers can use this knowledge to develop schedules that protect their expected project duration with a suitable structural complexity.

Originality/Value

Contributions to the body of knowledge are as follows: It converts the dependency structure into a reachability matrix and adds a correlation matrix to capture how the predecessor performance may impact its successors. It correlates criticality of activities with structural complexity indices. And it ranks activities objectively by their cruciality, i.e. potential delay propagation.

Details

10th Nordic Conference on Construction Economics and Organization
Type: Book
ISBN: 978-1-83867-051-1

Keywords

Open Access
Article
Publication date: 18 May 2022

Salman Ashkanani and Robert Franzoi

There is a large amount of published literature on project management. However, there exists a gap between the existing literature and current…

5220

Abstract

Purpose

There is a large amount of published literature on project management. However, there exists a gap between the existing literature and current practices in the industry for the development and execution of megaprojects. Existing literature generally focuses on individual elements applicable to project management in general. This article aims to provide an overview of the project management system components used in industrial megaprojects and identify the gaps between theory and practice, which can be used as input for further research on the topic.

Design/methodology/approach

The topic of megaproject management is reviewed based on available literature sources on megaproject management systems to identify the main gaps in the literature between theory and practice. Based on the findings, an analysis is provided to discuss the improvements required in distinct project management areas and phases.

Findings

There are multiple gaps associated with issues, failures, successes and challenges in industrial megaprojects. Improvements are needed in distinct management areas and over the entire project lifetime. Further guidelines are required for achieving improved megaproject management systems. Such concepts could benefit researchers and practitioners in streamlining their research toward the most relevant and critical areas of improvement of megaproject management systems.

Originality/value

This study addresses the literature gaps between theory and practices on megaproject management systems with an overview that provides helpful guidance for industrial applications and future research. A holistic analysis identifies gaps and critical drives in the body of knowledge, revealing avenues for future research focused on quality as the central pillar that affects the entire megaproject management system.

Details

Management Matters, vol. 19 no. 2
Type: Research Article
ISSN: 2752-8359

Keywords

Open Access
Article
Publication date: 28 June 2022

Sahar Jawad, Ann Ledwith and Rashid Khan

There is growing recognition that effective project control systems (PCS) are critical to the success of projects. The relationship between the individual elements of PCS and…

1571

Abstract

Purpose

There is growing recognition that effective project control systems (PCS) are critical to the success of projects. The relationship between the individual elements of PCS and successfully achieving project objectives has yet to be explored. This research investigates the enablers and barriers that influence the elements of PCS success and drive project objectives.

Design/methodology/approach

This study adopts a mixed approach of descriptive analysis and regression models to explore the impact of six PCS elements on project outcomes. Petroleum and chemical projects in Saudi Arabia were selected as a case study to validate the research model.

Findings

Data from a survey of 400 project managers in Saudi’s petroleum and chemical industry reveal that successful PCS are the key to achieving all project outcomes, but they are particularly critical for meeting project cost objectives. Project Governance was identified as the most important of the six PCS elements for meeting project objectives. A lack of standard processes emerged as the most significant barrier to achieving effective project governance, while having skilled and experienced project team members was the most significant enabler for implementing earned value.

Practical implications

The study offers a direction for implementing and developing PCS as a strategic tool and focuses on the PCS elements that can improve project outcomes.

Originality/value

This research contributes to project management knowledge and differs from previous attempts in two ways. Firstly, it investigates the elements of PCS that are critical to achieving project scope, schedule and cost objectives; secondly, enablers and barriers of PCS success are examined to see how they influence each element independently.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 13
Type: Research Article
ISSN: 0969-9988

Keywords

Open Access
Article
Publication date: 13 May 2022

Saleh Alsulamy

The purpose of this research is to identify the constraints and restrictions and their impact on the construction projects in Saudi Arabia from three key participants'…

2823

Abstract

Purpose

The purpose of this research is to identify the constraints and restrictions and their impact on the construction projects in Saudi Arabia from three key participants' perspectives for the planning stage.

Design/methodology/approach

Using a descriptive-analytical approach, this research described and analyzed the frequency and severity of failure factors in construction projects in the planning stage using a five-Likert scale questionnaire in Saudi Arabia construction between 2019 and 2020. A total of 100 experts from contractors, consultants and owners were included in the study.

Findings

The findings have shown that time dispute was the major factor affecting the projects to be failed. Similarly, cost overrun and total abandonment have an impact on project failures. The findings have indicated that government officials were involved in delaying the projects while contractors also failed in the project deliveries.

Research limitations/implications

Further research is needed to investigate the relationship between failure characteristics and project success measures in the same stage, in addition to, factors of failure for construction projects' life-cycle stages.

Originality/value

The findings have indicated that government officials were involved in delaying the projects while contractors also failed in the project deliveries.

Details

Frontiers in Engineering and Built Environment, vol. 2 no. 3
Type: Research Article
ISSN: 2634-2499

Keywords

Open Access
Article
Publication date: 12 May 2023

Olivia McDermott, Kevin ODwyer, John Noonan, Anna Trubetskaya and Angelo Rosa

This study aims to improve a construction company's overall project delivery by utilising lean six sigma (LSS) methods combined with building information modelling (BIM) to…

79278

Abstract

Purpose

This study aims to improve a construction company's overall project delivery by utilising lean six sigma (LSS) methods combined with building information modelling (BIM) to design, modularise and manufacture various building elements in a controlled factory environment off-site.

Design/methodology/approach

A case study in a construction company utilised lean six sigma (LSS) methodology and BIM to identify non-value add waste in the construction process and improve sustainability.

Findings

An Irish-based construction company manufacturing modular pipe racks for the pharmaceutical industry utilised LSS to optimise and standardise their off-site manufacturing (OSM) partners process and leverage BIM to design skids which could be manufactured offsite and transported easily with minimal on-site installation and rework required. Productivity was improved, waste was reduced, less energy was consumed, defects were reduced and the project schedule for completion was reduced.

Research limitations/implications

The case study was carried out on one construction company and one construction product type. Further case studies would ensure more generalisability. However, the implementation was tested on a modular construction company, and the methods used indicate that the generic framework could be applied and customized to any offsite company.

Originality/value

This is one of the few studies on implementing offsite manufacturing (OSM) utilising LSS and BIM in an Irish construction company. The detailed quantitative benefits and cost savings calculations presented as well as the use of the LSM methods and BIM in designing an OSM process can be leveraged by other construction organisations to understand the benefits of OSM. This study can help demonstrate how LSS and BIM can aid the construction industry to be more environmentally friendly.

Details

International Journal of Lean Six Sigma, vol. 15 no. 8
Type: Research Article
ISSN: 2040-4166