Search results

1 – 10 of over 27000
Open Access
Article
Publication date: 13 October 2022

Christian Nnaemeka Egwim, Hafiz Alaka, Eren Demir, Habeeb Balogun and Saheed Ajayi

This study aims to develop a comprehensive conceptual framework that serves as a foundation for identifying most critical delay risk drivers for Building Information Modelling…

1662

Abstract

Purpose

This study aims to develop a comprehensive conceptual framework that serves as a foundation for identifying most critical delay risk drivers for Building Information Modelling (BIM)-based construction projects.

Design/methodology/approach

A systematic review was conducted using Preferred Reporting Items for Systematic Reviews and Meta-Analyses (PRISMA) to identify key delay risk drivers in BIM-based construction projects that have significant impact on the performance of delay risk predictive modelling techniques.

Findings

The results show that contractor related driver and external related driver are the most important delay driver categories to be considered when developing delay risk predictive models for BIM-based construction projects.

Originality/value

This study contributes to the body of knowledge by filling the gap in lack of a conceptual framework for selecting key delay risk drivers for BIM-based construction projects, which has hampered scientific progress toward development of extremely effective delay risk predictive models for BIM-based construction projects. Furthermore, this study's analyses further confirmed a positive effect of BIM on construction project delay.

Details

Frontiers in Engineering and Built Environment, vol. 3 no. 1
Type: Research Article
ISSN: 2634-2499

Keywords

Article
Publication date: 3 October 2016

Suhaiza Zailani, Hazrina Aziz Md. Ariffin, Mohammad Iranmanesh, Soroush Moeinzadeh and Masoomeh Iranmanesh

This paper aims to explore the relationship between delay factors and construction project performance with respect to project risk mitigation strategies as moderators.

2004

Abstract

Purpose

This paper aims to explore the relationship between delay factors and construction project performance with respect to project risk mitigation strategies as moderators.

Design/methodology/approach

Random sampling was used to select the sample of the study. Data were gathered through a survey of 204 Malaysian construction companies. The data were analysed using the partial least squares technique.

Findings

The results indicate that environmental, resource and coordination issues negatively affect construction project performance. Project visibility and flexibility can mitigate the negative effects of both resource and coordination issues on project performance. Furthermore, supplier development can mitigate the negative effects of coordination issues.

Practical implications

The findings of the study will be useful for construction firms to complete construction projects timely, within a scheduled budget and with only minor defects if adopted.

Originality/value

This study is among the first to empirically test the moderating role of risk mitigation strategies on the relationship between delay factors and project performance in the construction industry.

Details

Journal of Science and Technology Policy Management, vol. 7 no. 3
Type: Research Article
ISSN: 2053-4620

Keywords

Article
Publication date: 5 February 2020

Hesham S. Ahmad, Maha D. Ayoush and Majed S. Al-Alwan

The purpose of this paper is to investigate the main causes of delay in public construction projects. This is motivated by feedback from public construction experts concerning…

Abstract

Purpose

The purpose of this paper is to investigate the main causes of delay in public construction projects. This is motivated by feedback from public construction experts concerning substantive delays during the last decade. The study thus seeks to help decision makers in Jordan and elsewhere identify problems and develop mitigating strategies.

Design/methodology/approach

Causes of delay were identified from previous related studies and then augmented after consultation with experts. This resulted in 56 delay factors classified into eight groups. The sampling frame for the study was defined in terms of public construction projects (mostly related to roads) owned by the Ministry of Public Works and Housing in Jordan. A survey was conducted with engineers working as representatives of the owner, contractors or consultants to elicit and evaluate the importance of the 56 delay factors.

Findings

Overall, 113 completed questionnaire responses were returned and analyzed to rank the causes of delay using the relative importance index method. Owners and consultants showed more interest in factors related to themselves, while contractors showed highest interest in an external factor related to the owner of services. Four recommendations are put forward for decision makers to mitigate against delays.

Originality/value

This research investigates a relatively large number of delay factors compared to other studies and these are categorized into groups to facilitate thematic understanding. Further, compared to previous related research, this research fills a gap by exploring the opinions of different contract parties.

Details

Built Environment Project and Asset Management, vol. 10 no. 1
Type: Research Article
ISSN: 2044-124X

Keywords

Open Access
Article
Publication date: 21 May 2018

Parvaneh Shahsavand, Akbar Marefat and Majid Parchamijalal

The purpose of this paper is to reveal the main causes of delays in the projects are from the client (relative importance index (RII)=0.716), labor and equipment (RII=0.701) and…

45448

Abstract

Purpose

The purpose of this paper is to reveal the main causes of delays in the projects are from the client (relative importance index (RII)=0.716), labor and equipment (RII=0.701) and contractor (RII=0.698). Hence determining the contractual responsibility of delay is the most likely source of dispute in construction projects and many techniques have been used in the courts to demonstrate the criticalities of a delay event on the project schedule. Therefore, authors try to investigate all process-based techniques of delay claims and evaluated and conformed them with principles by Society of Construction Law (SCL) protocol and Association for the Advancement of Cost Engineering International (AACEI) in order to choose the best techniques based on the specific circumstances of each project.

Design/methodology/approach

This section is divided into two distinct parts: refers to the methods used to assess the perceptions of clients, consultants, and contractors on the relative importance of causes of delay in construction industry; and refers to advantages and disadvantages of various techniques used to analyze delays and their conform with SCL protocol. A questionnaire was developed to assess the perceptions of clients, consultants, and contractors on the relative importance of causes of delay in Iranian construction industry. The respondents were asked to indicate their response category on 78 well-recognized construction delay factors identified by authors.

Findings

In total, 78 causes of delay were identified through research. The identified causes are combined into seven groups. The field survey included 58 contractors, 55 consultants, and 62 client. Data collected were analyzed by RII and Statistical Package for Social Sciences (SPSS). The authors identified main causes of delay and ten most important causes, according to Table AII, from the perspective of three major groups of participants (clients, consultants and contractors). The ranking of categories of causes of delay, according to Table I, were: client-related causes (RII=0.716); labor and equipment category causes (RII=0.701); contractor-related causes (RII=0.698); material-related causes (RII=0.690); design-related causes (RII=0.666); external causes (RII=0.662); and consultant-related causes (RII=0.662). But according to the discussions and given that determining the contractual responsibility of delay is the most likely source of dispute in construction industry and many techniques have been used in the courts to demonstrate the criticalities of a delay event on the project schedule.

Originality/value

All process-based techniques of delay analysis have been present in this paper and categorized in 11 groups. In order to understand the advantages and disadvantages of them by clients, contractor and consultant, a thorough review conducted to reveal the nature of techniques. In the next step, given that selecting the most appropriate technique based on constraints and specific conditions of each project is one of the most important steps to carry out a successful delay analysis. The authors conformed, all process-based techniques of delay analysis, by SCL protocol and AACEI principles. Finally, the result of this match was brought in order to choose the best technique based on the specific circumstances of each project.

Details

Engineering, Construction and Architectural Management, vol. 25 no. 4
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 13 April 2012

Gerard Hampton, Andrew N. Baldwin and Gary Holt

This paper aims to investigate the impacts on project delay from the perspective of construction stakeholders. Specifically, it aims to make a comparison between traditional…

3826

Abstract

Purpose

This paper aims to investigate the impacts on project delay from the perspective of construction stakeholders. Specifically, it aims to make a comparison between traditional procurement based on standard contract forms and private/public partnerships (PPPs), for the procurement of public sector projects in Scotland.

Design/methodology/approach

A structured questionnaire survey was used to elicit perceptions of seven delay impact groupings. Response data were analysed using hypothesis tests to observe perceived differences among these groupings, in respect of each procurement method. Follow‐up semi‐structured telephone interviews further explored stakeholders' views and broader issues.

Findings

Significant differences of perception were identified between the impacts of: client, contractor, designer, financial, labour and material related delay factors. These were felt to have greater “delay potential” under traditional vis‐à‐vis PPP procured projects. There was no significant difference among plant‐related factors. Preference for traditional procurement in achieving “project quality” and “value for money” was observed; but at the perceived risk of potentially encountering more delays. PPP was preferred for achieving best “time performance” and was the favoured procurement option “overall”.

Research limitations/implications

Findings add to the existing body of procurement‐choice knowledge generally and their relationship to project delays and associated costs, specifically.

Practical implications

Practitioners may wish to consider the perceived benefits of PPP procurement in better dealing with potential delay impacts.

Social implications

Reduction in delay and construction cost holds potential benefit to all who procure constructed facilities.

Originality/value

The work is novel in the specific contexts of public sector stakeholders surveyed and their geographical location.

Details

Journal of Financial Management of Property and Construction, vol. 17 no. 1
Type: Research Article
ISSN: 1366-4387

Keywords

Article
Publication date: 6 December 2021

Henry Duncan John Mwamvani, Christopher Amoah and Emma Ayesu-Koranteng

The study aims to find the causes of road projects implementation delays in Blantyre, one of the four city councils (CCs) in Malawi.

Abstract

Purpose

The study aims to find the causes of road projects implementation delays in Blantyre, one of the four city councils (CCs) in Malawi.

Design/methodology/approach

The study followed a qualitative research approach using a Blantyre City Council (BCC) as a case study. This study combined in-depth, face-to-face interviews with councillors, secretariat staff, consultants, and contractors who worked on the city's road projects. Data gathered were analysed using thematic content analysis. Also, some road project documents were examined.

Findings

The findings from the case study revealed the primary cause of road project construction delays as the shortage of engineers in conducting detailed proposed projects surveys resulting in incomplete project scope definition before contractor's procurement. Other identified factors were service providers delaying the removal of existing public utility infrastructure from project sites, client funding issues, scope changes, and client delays in issuing instructions to the contractors during project implementation. Another factor was the shortage of construction equipment and construction materials experienced by some appointed contractors.

Research limitations/implications

Only road construction projects and stakeholders operating from Blantyre city, Malawi, were contacted for the study; thus, the findings may not be generalizable.

Practical implications

There is an urgent need to increase technical employees, especially engineers and other critical technical staff such as quantity surveyors in Blantyre. Employees' conditions of service should be conducive to attract qualified people to undertake effective management and assessment of projects before commencement to identify the feasibility of proposed projects to decrease the rate of road construction project delays.

Originality/value

The study has established Blantyre city's core challenges in implementing its road projects seamlessly and has provided mitigation measures for dealing with the shortcomings.

Details

Built Environment Project and Asset Management, vol. 12 no. 2
Type: Research Article
ISSN: 2044-124X

Keywords

Article
Publication date: 22 January 2019

Prasad K.V., Vasugi V., Venkatesan R. and Nikhil Bhat

Construction projects in India continue to suffer excessive delays. This paper aims to investigate the delay causes in India by project sector (transport, power, buildings and…

1786

Abstract

Purpose

Construction projects in India continue to suffer excessive delays. This paper aims to investigate the delay causes in India by project sector (transport, power, buildings and water) and carry out a comparative study of delay causes in design build (DB) projects with that of design bid build (DBB) projects along with mitigation measures.

Design/methodology/approach

A questionnaire survey was conducted among major clients, contractors and consultants in India. Importance Index was used for ranking of the delay causes. Projects were categorized based on the type, and causes of delay in each project type were identified. Projects were also categorized based on type of contract, and delay causes in DB and DBB projects were compared. Statistical analysis of responses by Cronbach’s alpha, one-way analysis of variance, Kruskal–Wallis tests was carried out with Statistical Package for Social Sciences. Semi-structured in-depth interviews were conducted with senior industry professionals to develop exhaustive mitigation measures.

Findings

The research findings indicate finance-related causes as the most critical causes of delay in Indian projects. Delay in settlement of claims, contractor’s financial difficulties, delay in payment for extra work/variations by owner, late payment from contractor to subcontractor or suppliers, variation orders/changes of scope by owner during construction and changes in design by owner were the highly ranked delay causes. The research found no significant difference in the delay causes in DB and DBB projects.

Originality/value

This is the first study wherein delay causes for various project types within a single country are identified. In addition, the study has identified and compared the delay causes in DB projects and DBB projects. Mitigation measures developed in this study will help professionals and project managers not just in India but other developing countries as well to alleviate delay causes and in improvement of project timelines.

Details

Journal of Financial Management of Property and Construction, vol. 24 no. 1
Type: Research Article
ISSN: 1366-4387

Keywords

Article
Publication date: 30 September 2020

Hossein Derakhshanfar, J. Jorge Ochoa, Konstantinos Kirytopoulos, Wolfgang Mayer and Craig Langston

The purpose of this research is to identify the most impactful delay risks in Australian construction projects, including the associations amongst those risks as well as the…

1012

Abstract

Purpose

The purpose of this research is to identify the most impactful delay risks in Australian construction projects, including the associations amongst those risks as well as the project phases in which they are most likely present. The correlation between project and organisational characteristics with the impact of delay risks was also studied.

Design/methodology/approach

A questionnaire survey was used to collect data from 118 delayed construction projects in Australia. Data were analysed to rank the most impactful delay risks, their correlation to project and organisational characteristics and project phases where those risks are likely to emerge. Association rule learning was used to capture associations between the delay risks.

Findings

The top five most impactful delay risks in Australia were changes by the owner, slow decisions by the owner, preparation and approval of design drawings, underestimation of project complexity and unrealistic duration imposed to the project, respectively. There is a set of delay risks that are mutually associated with project complexity. In addition, while delay risks associated with resources most likely arise in the execution phase, stakeholder and process-related risks are more smoothly distributed along all the project phases.

Originality/value

This research for the first time investigated the impact of delay risks, associations amongst them and project phases in which they are likely to happen in the Australian context. Also, this research for the first time sheds light on the project phases for the individual project delay risks which aids the project managers to understand where to focus on during each phase of the project.

Details

Engineering, Construction and Architectural Management, vol. 28 no. 7
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 8 February 2022

Niyazi Alashwal and Ali Alashwal

Road projects are essential for poverty reduction and the socio-economic development of Yemeni people living in rural areas. Rural access programs, which are mainly sponsored by…

Abstract

Purpose

Road projects are essential for poverty reduction and the socio-economic development of Yemeni people living in rural areas. Rural access programs, which are mainly sponsored by foreign countries and international organisations, are often delayed. The purpose of this paper is to identify the delay factors of rural road projects with a focus on stakeholder-related factors.

Design/methodology/approach

The data was collected using a questionnaire survey from 164 participants representing 7 groups, namely, owner, government, donors, consultants, designers, contractors and beneficiaries. The data was analysed using the partial least squares path modelling (PLS-SEM).

Findings

The results show that the identified factors contribute to 16% of the variance of project delay. Donor and government-related factors have a significant relationship with delay. Further analysis of data using the IPMA procedure in PLS-SEM revealed the top factors contributing to delay, which are project selection criteria imposed by donors, government bureaucracy, decision-making process, weak laws and guidelines that regulate the work of project implementation units, procurement procedures, delay of payment to contractor and delay of transactions.

Originality/value

The timely completion of rural road projects can have a positive impact on the current and future rural access programs aiming to reduce poverty and increase access to health and education services of over 70% of Yemeni people living in rural areas. Such programs will reduce the misfortune of displaced people due to the ongoing war in the country.

Details

Engineering, Construction and Architectural Management, vol. 30 no. 4
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 25 February 2020

Amílcar Arantes and Luís Miguel D.F. Ferreira

The purpose of this study is to contribute to the theory and practice of project management in the construction industry by identifying the primary causes and extracting the…

1540

Abstract

Purpose

The purpose of this study is to contribute to the theory and practice of project management in the construction industry by identifying the primary causes and extracting the underlying causes of construction delays and providing recommendations on delay mitigation measures.

Design/methodology/approach

AA survey was used to identify the importance of 47 causes of delays. The relative importance index was used to rank them, factor analysis was applied to extract the underlying causes and focus group interviews were used for discussion and development of mitigation measures.

Findings

Six of the ten most important causes are in the top ten universal delays in construction projects. Factor analysis revealed six underlying causes: improper planning, poor consultant performance, inefficient site management, owner influence, bureaucracy and sub-standard contracts.

Practical implications

The owner/sponsor/client must have adequate engineering and project management skills to be able to evaluate proposals and contractors more accurately, economically and technically. The bidding and contract award process should focus on the most economically advantageous proposal and contracts should provide for mechanisms for managing risks while executing projects. Contractors should select reliable, high-quality subcontractors and suppliers and should have competent site managers.

Originality/value

This work expands and improves the understanding of the causes of delays in construction projects by providing an empirical study of the causes of delays and respective mitigation measures in Portugal.

Details

Journal of Financial Management of Property and Construction , vol. 25 no. 2
Type: Research Article
ISSN: 1366-4387

Keywords

1 – 10 of over 27000