Search results

1 – 10 of 12
Article
Publication date: 10 May 2022

Augustine Senanu Komla Kukah, De-Graft Owusu-Manu, Edward Badu and David John Edwards

This study aims to evaluate the key risk factors inherent in public–private partnership (PPP) power projects in Ghana and further determine the critical risk factors affecting…

Abstract

Purpose

This study aims to evaluate the key risk factors inherent in public–private partnership (PPP) power projects in Ghana and further determine the critical risk factors affecting both the public and private sectors in PPP power projects.

Design/methodology/approach

Ranking-type Delphi survey in two rounds was conducted to establish a comprehensive list of critical risk factors of PPP. Purposive and snowball sampling techniques helped obtain experts for the Delphi survey. Mean score ranking, factor analysis, Cronbach α coefficient and Kendall’s concordance were used for analysis. The probability of occurrence and severity of each risk factor were computed to obtain the risk impact.

Findings

From the list of 67 risks, 37 risk factors were deemed to be critical. The five topmost risk factors were: delay payment on contract, private investor change, political risks, fluctuating demand of power generated and public opposition. Principal component analysis grouped the risk factors into seven major themes.

Originality/value

This study develops an authoritative risk factor list for PPP power projects, which reflects both sector and country conditions for prioritizing and mitigating risk factors. Delphi approach adopted in this study can be used by future studies in similar environments where PPP is novel and expert respondents scarce.

Details

Journal of Facilities Management , vol. 22 no. 1
Type: Research Article
ISSN: 1472-5967

Keywords

Article
Publication date: 21 December 2021

Bamidele Temitope Arijeloye, Isaac Olaniyi Aje and Ayodeji Emmanuel Oke

The purpose of the study is to elicit risk factors that are peculiar to public-private partnership (PPP)-procured mass housing in Nigeria from the expert perspectives in ensuring…

Abstract

Purpose

The purpose of the study is to elicit risk factors that are peculiar to public-private partnership (PPP)-procured mass housing in Nigeria from the expert perspectives in ensuring the success of the scheme thereby reducing housing deficit in the country.

Design/methodology/approach

The risk inherent in construction projects had been established through literature in general. The risk in PPP projects is emerging because of the recent acceptance of the procurement option by governments all over the globe. The Nigerian Government has also adopted the procurement option in bridging the housing deficit in the country. This study, therefore, conducts a Delphi survey on the probability of risk occurrence peculiar to PPP mass housing projects (MHPs) in Nigeria. Pragmatic research approach through the mixed method of both quantitative and qualitative methods was adopted for this study. The quantitative method adopts the administration of questionnaires through the Delphi survey, whereas the qualitative method used interviews with the respondents. A two-stage Delphi questionnaire was administered to construction practitioners that cut across academics, the public and the private sectors by adopting convenient sampling techniques and following the Delphi principles and procedures. A total of 63 risk factors were submitted to the expert to rank on a Likert scale of 7 and any risk factors that the mean item score (MIS) falls below the grading scale of the five-point benchmark is deemed not necessary a risk factor associated with PPP MHPs and thereby expunged from the second round of the Delphi Survey. The interview was subsequently applied to the respondents to substantiate the risk factors that are peculiar to PPP-procured mass housing in the study area.

Findings

The findings show that risk factors such as maintenance frequent than expected, life of facility shorter than anticipated and maintenance cost higher than expected fall below 5.0 benchmark with MIS of 4.64 and 4.55 indicating that the risk factors are not peculiar to PPP mass housing in Nigeria.

Research limitations/implications

The implication for practise of this research is that these risk factors provide the PPP stakeholders with the comprehensive checklists that can aid in developing PPP risk assessment guidelines in the sector though both partners should be aware of the dynamic nature of risk because new ones might be emerging.

Originality/value

The authors hereby declare that the research findings are a product of a thorough research conducted in the study area and have not to be submitted or published by another person or publisher and due acknowledgement was made where necessary.

Details

Journal of Engineering, Design and Technology , vol. 22 no. 1
Type: Research Article
ISSN: 1726-0531

Keywords

Open Access
Article
Publication date: 13 June 2023

Gabriel Castelblanco, Jose Guevara and Alberto De Marco

Global crises have become increasingly recurrent events that jeopardize public-private partnerships (PPPs). In this context, the purpose of this paper is to expose the PPP-crisis…

1634

Abstract

Purpose

Global crises have become increasingly recurrent events that jeopardize public-private partnerships (PPPs). In this context, the purpose of this paper is to expose the PPP-crisis research agenda by combining bibliometric and network analyses.

Design/methodology/approach

The PPP literature associated with global crises between the 2008 global financial crisis and 2022 was analyzed in three stages: (1) paper selection and screening for the inclusion/exclusion of articles relevant to this research, (2) semantic network development for examining thematic relationships among selected papers by considering the co-occurrence of keywords within the chosen studies and (3) calculation of network metrics for analysis.

Findings

The paper identified six research avenues for the PPP-crisis agenda: public interest, relational governance, risk management, user-pay PPPs, crisis management and financial performance. The PPP-crisis literature has spread significantly in the last five years driven by the case study approaches on a national or regional basis. Conversely, non-crisis periods generate room to strengthen user-pay PPPs and relational governance. The pandemic and post-pandemic times shared the priorities of the 2008 financial crisis but also strengthened the management of the risks and the structural drivers of the global crisis.

Originality/value

This study demonstrates that during global crisis periods, the public interest and financial performance gain relevance in a detriment of structural solutions to social legitimacy erosion of PPPs because of the urgency of giving tools to the public and private sectors to tackle the financial issues, which steer future issues for PPPs.

Details

Built Environment Project and Asset Management, vol. 14 no. 1
Type: Research Article
ISSN: 2044-124X

Keywords

Article
Publication date: 17 October 2022

Jianbo Zhu, Qianqian Shi, Ce Zhang, Jingfeng Yuan, Qiming Li and Xiangyu Wang

Promoting low-carbon in the construction industry is important for achieving the overall low-carbon goals. Public–private partnership is very popular in public infrastructure…

Abstract

Purpose

Promoting low-carbon in the construction industry is important for achieving the overall low-carbon goals. Public–private partnership is very popular in public infrastructure projects. However, different perceptions of low-carbon and behaviors of public and private sectors can hinder the realization of low-carbon in these projects. In order to analyze the willingness of each stakeholder to cooperate towards low-carbon goals, an evolutionary game model is constructed.

Design/methodology/approach

An evolutionary game model that considers the opportunistic behavior of the participants is developed. The evolutionary stable strategies (ESSs) under different scenarios are examined, and the factors that influence the willingness to cooperate between the government and private investors are investigated.

Findings

The results illustrate that a well-designed system of profit distribution and subsidies can enhance collaboration. Excessive subsidies have negative impact on cooperation between the two sides, because these two sides can weaken income distribution and lead to the free-riding behavior of the government. Under the situation of two ESSs, there is also an optimal revenue distribution coefficient that maximizes the probability of cooperation. With the introduction of supervision and punishment mechanism, the opportunistic behavior of private investors is effectively constrained.

Originality/value

An evolutionary game model is developed to explore the cooperation between the public sector and the private sector in the field of low-carbon construction. Based on the analysis of the model, this paper summarizes the conditions and strategies that can enable the two sectors to cooperate.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 2
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 23 January 2024

Dilan Weerasooriya, K.A.T.O Ranadewa and B.A.K.S Perera

Cyber-physical systems (CPS) enable the synergistic integration of virtual models with the physical environment. This integration is gaining recognition for its potential to…

Abstract

Purpose

Cyber-physical systems (CPS) enable the synergistic integration of virtual models with the physical environment. This integration is gaining recognition for its potential to enhance construction project information management, thereby contributing to improved cost management in construction. Similarly, quantity surveyor (QS) plays a key role in construction projects by estimating and monitoring construction costs. Consequently, this research aims to explore redefining the role of QSs by integrating CPS.

Design/methodology/approach

The research adopted an interpretivism stance to collect and analyse data. Two rounds of 21 and 19 semi-structured interviews were conducted, with experts selected through heterogeneous purposive sampling. Code-based content analysis was used to analyse the data using NVivo12. MS Visio data visualisation tool was used to present the findings.

Findings

It is empirically proven the potential of CPS to facilitate nine key roles of QSs in all stages of the RIBA plan of work through the identification of 15 CPS applications and technologies. Nine key roles of QSs that CPS can facilitate were identified as preliminary estimation, measurement and quantification, contract administration, preparation of BOQ, interim valuation and payments, tender and contract documentation, cost planning, cost control and procurement advice. The study explored how adopting CPS technologies can transform traditional quantity surveying practices and enhance their value within the construction industry.

Originality/value

The findings add to the body of knowledge by redefining the role of QS through the integration of CPS for the first time and then by highlighting the usages of CPS in the construction industry rather than limiting it to a specific sector of the construction industry, as previous studies have done. This research uncovers several other research arenas on CPS as being the very first research to evaluate CPS to facilitate key roles of QSs. The findings can enhance the awareness and the practical implementation of CPS by intervening to form more partnerships among application developers and industry leaders.

Details

Journal of Engineering, Design and Technology , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1726-0531

Keywords

Book part
Publication date: 6 May 2024

Walid Simmou, Anas Hattabou and Samira Simmou

In Morocco, as in many developing countries, environmental responsibility is not well integrated into corporate management at the operational, tactical, and strategic levels…

Abstract

In Morocco, as in many developing countries, environmental responsibility is not well integrated into corporate management at the operational, tactical, and strategic levels. While the management literature offers a rich body of knowledge on Corporate Social Responsibility (CSR) strategies and practices, less attention has been paid to exploring the complexity of environmental responsibility through the lens of corporate culture. This research aims to address this gap by examining the influence of cultural factors on the deployment of environmental responsibility using Johnson's (2000) model of corporate culture. This model identifies seven components of corporate culture: stories or myths, symbols, power structures, organizational structures, control systems, rituals and routines, and paradigms. Through a Moroccan industrial group case study, this chapter presents the successful deployment of environmental responsibility and describes how managing cultural factors facilitated this transition. This chapter also identifies the unique aspects of the group's culture that allowed redesigning the company's management systems. These insights offer valuable implications for managers and policymakers seeking to improve the environmental performance of large enterprises in developing countries.

Details

The Emerald Handbook of Ethical Finance and Corporate Social Responsibility
Type: Book
ISBN: 978-1-80455-406-7

Keywords

Article
Publication date: 12 July 2023

Augustine Senanu Komla Kukah, De-Graft Owusu-Manu, Edward Badu, David J. Edwards and Eric Asamoah

Public-private partnership (PPP) power projects are associated with varying risk factors. This paper aims to develop a fuzzy quantitative risk allocation model (QRAM) to guide…

Abstract

Purpose

Public-private partnership (PPP) power projects are associated with varying risk factors. This paper aims to develop a fuzzy quantitative risk allocation model (QRAM) to guide decision-making on risk allocation in PPP power projects in Ghana.

Design/methodology/approach

A total of 67 risk factors and 9 risk allocation criteria were established from literature and ranked in a two-round Delphi survey using questionnaires. The fuzzy synthetic evaluation method was used in developing the risk allocation model.

Findings

The model’s output variable is the risk allocation proportions between the public body and private body based on their capability to manage the risk factors. Out of the 37 critical risk factors, the public sector was allocated 12 risk factors with proportions = 50%, while the private sector was allocated 25 risk factors with proportions = 50%.

Originality/value

To the best of the authors’ knowledge, this research presents the first attempt in Ghana at endeavouring to develop a QRAM for PPP power projects. There is confidence in the model to efficiently allocate risks emanating from PPP power projects.

Details

Journal of Financial Management of Property and Construction , vol. 29 no. 1
Type: Research Article
ISSN: 1366-4387

Keywords

Article
Publication date: 14 November 2023

Michał Kania and Marta Andhov

The purpose of this paper is to analyze the recently enacted Regulation (EU) 2022/2560 of the European Parliament and of the Council of December 14, 2022, on foreign subsidies…

Abstract

Purpose

The purpose of this paper is to analyze the recently enacted Regulation (EU) 2022/2560 of the European Parliament and of the Council of December 14, 2022, on foreign subsidies distorting the internal market (foreign subsidies regulation [FSR]) and its repercussions on the European Union (EU) public procurement marketplace and corporations from third countries. The purpose of this paper is to analyze the geopolitical and economic backgrounds for the Regulation and its efficiency.

Design/methodology/approach

In this study, the authors used doctrinal and analytical legal methodologies, meticulously examining pertinent EU law sources. The authors systematically collated and scrutinized applicable literature and legislative process materials to discern the essence and substance of the norms enshrined in the law. In this study, the authors also applied a socio-legal methodology when focusing on the economic and geopolitical context surrounding the adoption of the FSR. The contextual analysis traces the evolution of changes in international cooperation and recent political shifts.

Findings

Implementing the FSR should pave the way for a more equitable competitive landscape within the EU public procurement market, bolstering EU values. However, its potential to prolong public procurement procedures and create uncertainties regarding their outcomes could pose challenges, possibly affecting the effectiveness of public procurement regulations. Only time will reveal the extent of the EU’s interventionist approach and how necessary adjustments must be made to align with market demands.

Social implications

This study highlights socially relevant aspects of the implementation of EU policies – European New Green Deal and European Industrial Policy in the context of public procurement. The analysis contained in this study concerns issues directly related to meeting the collective needs of the citizens.

Originality/value

To the best of the authors’ knowledge, this study is the first in-depth analysis of the solutions contained in the FSR in terms of geopolitical and economic aspects. Furthermore, there have been no studies so far, which have analyzed the FSR in detail from the point of view of its effectiveness. The effectiveness concept contained in this study is the authors’ own solution.

Details

Journal of Public Procurement, vol. 24 no. 1
Type: Research Article
ISSN: 1535-0118

Keywords

Article
Publication date: 20 December 2023

Isaac Akomea-Frimpong, Xiaohua Jin, Robert Osei Kyei, Portia Atswei Tetteh, Roksana Jahan Tumpa, Joshua Nsiah Addo Ofori and Fatemeh Pariafsai

The application of circular economy (CE) has received wide coverage in the built environment, including public-private partnership (PPP) infrastructure projects, in recent times…

Abstract

Purpose

The application of circular economy (CE) has received wide coverage in the built environment, including public-private partnership (PPP) infrastructure projects, in recent times. However, current studies and practical implementation of CE are largely associated with construction demolition, waste and recycling management. Few studies exist on circular models and success factors of public infrastructures developed within the PPP contracts. Thus, the main objective of this article is to identify the models and key success factors associated with CE implementation in PPP infrastructure projects.

Design/methodology/approach

A systematic review of the literature was undertaken in this study using forty-two (42) peer-reviewed journal articles from Scopus, Web of Science, Google Scholar and PubMed.

Findings

The results show that environmental factors, sustainable economic growth, effective stakeholder management, sufficient funding, utilization of low-carbon materials, effective supply chain and procurement strategies facilitate the implementation of CE in PPP infrastructure projects. Key CE business models are centered around the extension of project life cycle value, circular inputs and recycling and reuse of projects.

Research limitations/implications

Although the study presents relevant findings and gaps for further investigations, it has a limited sample size of 42 papers, which is expected to increase as CE gain more prominence in PPP infrastructure management in future.

Practical implications

The findings are relevant for decision-making by PPP practitioners to attain the social, economic and environmental benefits of transitioning to circular infrastructure management.

Originality/value

This study contributes to articulating the key models and measures toward sustainable CE in public infrastructure development.

Details

Built Environment Project and Asset Management, vol. 14 no. 1
Type: Research Article
ISSN: 2044-124X

Keywords

Article
Publication date: 29 March 2024

Katarzyna Piwowar-Sulej and Qaisar Iqbal

Based on the social exchange theory, the aim of the present study is to examine the effects, both direct and indirect (through sustainability-oriented innovative behaviors…

Abstract

Purpose

Based on the social exchange theory, the aim of the present study is to examine the effects, both direct and indirect (through sustainability-oriented innovative behaviors [SIBs]), of sustainable project leadership (SPL) on sustainable project performance (SPP). Project management approaches (PMAs) (traditional, hybrid and agile) were examined as conditional factors in the “SPL–SIBs” relationship.

Design/methodology/approach

The study employs structural equation modeling based on data collected from 197 software engineering project team members working in the financial industry in Poland.

Findings

The study revealed that SPL significantly, positively affected SPP. It also provided evidence for the significant mediating impact of SIBs in the relationship between SPL and SPP and the conditional effect of agile and hybrid PMAs on the “SPL–SIBs” relationship.

Originality/value

The novelty of this work lies in introducing sustainable leadership into project management research, proposing and testing a unique and complex research framework, designing valid scales for measuring SPL and SPP, and suggesting many theoretical and empirical implications.

Details

International Journal of Managing Projects in Business, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1753-8378

Keywords

1 – 10 of 12