Search results

1 – 10 of over 1000
Article
Publication date: 27 October 2023

Muhammad Saiful Islam, Madhav Nepal and Martin Skitmore

Power plant projects are very complex and encounter serious cost overruns worldwide. Their cost overrun risks are not independent but interrelated in many cases, having structural…

Abstract

Purpose

Power plant projects are very complex and encounter serious cost overruns worldwide. Their cost overrun risks are not independent but interrelated in many cases, having structural relationships among each other. The purpose of this study is, therefore, to establish the complex structural relationships of risks involved.

Design/methodology/approach

In total, 76 published articles from the previous literature are reviewed using the content analysis method. Three risk networks in different phases of power plant projects are depicted based on literature review and case studies. The possible methods of solving these risk networks are also discussed.

Findings

The study finds critical cost overrun risks and develops risk networks for the procurement, civil and mechanical works of power plant projects. It identifies potential models to assess cost overrun risks based on the developed risk networks. The literature review also revealed some research gaps in the cost overrun risk management of power plants and similar infrastructure projects.

Practical implications

This study will assist project risk managers to understand the potential risks and their relationships to prevent and mitigate cost overruns for future power plant projects. It will also facilitate decision-makers developing a risk management framework and controlling projects’ cost overruns.

Originality/value

The study presents conceptual risk networks in different phases of power plant projects for comprehending the root causes of cost overruns. A comparative discussion of the relevant models available in the literature is presented, where their potential applications, limitations and further improvement areas are discussed to solve the developed risk networks for modeling cost overrun risks.

Details

Construction Innovation , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1471-4175

Keywords

Open Access
Article
Publication date: 13 February 2024

Daniel de Abreu Pereira Uhr, Mikael Jhordan Lacerda Cordeiro and Júlia Gallego Ziero Uhr

This research assesses the economic impact of biomass plant installations on Brazilian municipalities, focusing on (1) labor income, (2) sectoral labor income and (3) income…

Abstract

Purpose

This research assesses the economic impact of biomass plant installations on Brazilian municipalities, focusing on (1) labor income, (2) sectoral labor income and (3) income inequality.

Design/methodology/approach

Municipal data from the Annual Social Information Report, the National Electric Energy Agency and the National Institute of Meteorology spanning 2002 to 2020 are utilized. The Synthetic Difference-in-Differences methodology is employed for empirical analysis, and robustness checks are conducted using the Doubly Robust Difference in Differences and the Double/Debiased Machine Learning methods.

Findings

The findings reveal that biomass plant installations lead to an average annual increase of approximately R$688.00 in formal workers' wages and reduce formal income inequality, with notable benefits observed for workers in the industry and agriculture sectors. The robustness tests support and validate the primary results, highlighting the positive implications of renewable energy integration on economic development in the studied municipalities.

Originality/value

This article represents a groundbreaking contribution to the existing literature as it pioneers the identification of the impact of biomass plant installation on formal employment income and local economic development in Brazil. To the best of our knowledge, this study is the first to uncover such effects. Moreover, the authors comprehensively examine sectoral implications and formal income inequality.

Details

EconomiA, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1517-7580

Keywords

Article
Publication date: 12 July 2023

Augustine Senanu Komla Kukah, De-Graft Owusu-Manu, Edward Badu, David J. Edwards and Eric Asamoah

Public-private partnership (PPP) power projects are associated with varying risk factors. This paper aims to develop a fuzzy quantitative risk allocation model (QRAM) to guide…

Abstract

Purpose

Public-private partnership (PPP) power projects are associated with varying risk factors. This paper aims to develop a fuzzy quantitative risk allocation model (QRAM) to guide decision-making on risk allocation in PPP power projects in Ghana.

Design/methodology/approach

A total of 67 risk factors and 9 risk allocation criteria were established from literature and ranked in a two-round Delphi survey using questionnaires. The fuzzy synthetic evaluation method was used in developing the risk allocation model.

Findings

The model’s output variable is the risk allocation proportions between the public body and private body based on their capability to manage the risk factors. Out of the 37 critical risk factors, the public sector was allocated 12 risk factors with proportions = 50%, while the private sector was allocated 25 risk factors with proportions = 50%.

Originality/value

To the best of the authors’ knowledge, this research presents the first attempt in Ghana at endeavouring to develop a QRAM for PPP power projects. There is confidence in the model to efficiently allocate risks emanating from PPP power projects.

Details

Journal of Financial Management of Property and Construction , vol. 29 no. 1
Type: Research Article
ISSN: 1366-4387

Keywords

Article
Publication date: 14 December 2022

Bryan Pieterse, Kofi Agyekum, Patrick Manu, Saeed Reza Mohandes, Clara Cheung and Akilu Yunusa-Kaltungo

Major maintenance projects are often regarded as maintenance activities regardless of the projects' complexity and scale. Consequently, very scarce research attention has hitherto…

Abstract

Purpose

Major maintenance projects are often regarded as maintenance activities regardless of the projects' complexity and scale. Consequently, very scarce research attention has hitherto been paid to the critical skills required when undertaking these projects. More specifically, the body of relevant knowledge is deprived of a study focusing on maintenance projects within the energy sector. In view of this shortcoming, this research aims to examine the critical project management (PM) skills required to deliver major maintenance projects within the energy sector.

Design/methodology/approach

Based on a quantitative research strategy, this study addressed the knowledge gap through a cross-sectional survey of professionals involved in the delivery of major maintenance projects in the United Kingdom's (UK) energy sector. Data obtained were analyzed via descriptive (e.g. frequencies, mean and standard deviation [SD]) and inferential statistical analyses (One sample t-test and exploratory factor analysis (EFA)).

Findings

Out of the 45 PM skills identified in the literature and examined by the respondents, the results obtained from the One sample t-test (based on p (1-tailed) = 0.05) showed that 37 were considered to be at least “important,” accounting for 80.4% of all the skills identified. EFA revealed a clustering of the PM skills items into seven components: “skills related to work scheduling and coordination”; “communication, risk, safety and stakeholder management skills”; “quality assurance skills”; “people management skills”; “skills related to forecasting scope and duration of outage”; “implementation of processes and time management skills” and “technical/engineering skills and experience pertaining to the outage and local site knowledge.”

Originality/value

This study has identified and contributed to the limited state-of-the-art skills project managers must possess to manage major maintenance projects in the energy sector successfully. The findings would be useful to organizations within the energy sector in ensuring that the organizations have suitable personnel in place to deliver major maintenance projects on the organizations' assets.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 4
Type: Research Article
ISSN: 0969-9988

Keywords

Open Access
Article
Publication date: 28 February 2023

Mohammed Jawad Abed and Anis Mhalla

The paper aims to present a grid-connected multi-inverter for solar photovoltaic (PV) systems to enhance reliability indices after selected the placement and level of PV solar.

Abstract

Purpose

The paper aims to present a grid-connected multi-inverter for solar photovoltaic (PV) systems to enhance reliability indices after selected the placement and level of PV solar.

Design/methodology/approach

In this study, the associated probability is calculated based on the solar power generation capacity levels and outages conditions. Then, based on this probability, dependability indices like average energy not supplied (AENS), expected energy not supplied and loss of load expectations (LOLE) are computed, also, another indices have been computed such as (customer average interruption duration index (CAIDI), system average interruption frequency index (SAIFI) and system average interruption duration index (SAIDI)) addressing by affected customers with distribution networks reliability assessment, including PV. On the basis of their dependability indices and active power flow, several PV solar modules installed in several places are analyzed. A mechanism for assessing the performance of the grid's integration of renewable energy sources is also under investigation.

Findings

The findings of this study based on data extracted form a PV power plant connected to the power network system in Diyala, Iraq 132 kV, attempts to identify the system's weakest points in order to improve the system's overall dependability. In addition, enhanced reliability indices are given for measuring solar PV systems performance connected to the grid and reviewed for the benefit of the customers.

Originality/value

The main contributions of this study are two methods for determining the reliability of PV generators taking into consideration the system component failure rates and the power electronic component defect rates in a PV system which depend on the power input and the power loss using electrical transient analysis program (ETAP) program.

Details

Arab Gulf Journal of Scientific Research, vol. 42 no. 1
Type: Research Article
ISSN: 1985-9899

Keywords

Article
Publication date: 8 March 2024

Md. Mohaimenul Islam Sourav, Mohammed Russedul Islam, Sheikh Mohibur Rahman and Md. Istiak Jahan

In Bangladesh (BD), delays in infrastructure are common. Many previous studies have explored the causes of infrastructure delays. However, this study investigated the causes of…

Abstract

Purpose

In Bangladesh (BD), delays in infrastructure are common. Many previous studies have explored the causes of infrastructure delays. However, this study investigated the causes of delays by taking responses from the stakeholders who are responsible for planning, design, funding, approval and implementation. There are few studies that have related infrastructure project delays to heterogeneity in stakeholders’ perceptions.

Design/methodology/approach

A structural equation (SE) model is developed with 350 normally distributed data points to understand the heterogeneity in stakeholders’ perceptions regarding delays in infrastructure projects in BD. Additionally, the relative importance index (RII) approach is used to assess the responses, validating the SE model.

Findings

The study finds that among the three latent variables, “Project itself related delay” has more influence on delays in infrastructure projects. Among the observed variables under the “project itself related delay” latent variable, “DPP approval process” has the most significance. From the heterogeneity analysis, the study found differences in responses among the stakeholders from “the Engineering Department,” “the Planning Office” and “the Construction Firm/Industry.” An important class of stakeholders believes that their stage is not being delayed and that other stages require attention.

Research limitations/implications

The data sample is 350. More data can improve the accuracy of the findings. Most of the respondents are civil engineers (74%) and represent the owner of the project. Sample data from more stakeholders’ will enhance the accuracy of the result.

Practical implications

This study addresses the requirements of Bangladeshi project stakeholders and how their interactions cause delays in projects. Furthermore, the opinions of other stakeholders are taken into consideration when determining the specific factors of individual stakeholders that are causing delays. Practically, the distance between stakeholders should be reduced. A project manager can play a role in this regard. Initiatives should be taken on how to complete the project quickly by eliminating the requirements discussed among the stakeholders and bureaucratic complications. Instead of placing blame on one another, stakeholders should take the initiative to figure out how to work together to finish the project on schedule. The Planning Commission’s approval of the Development Project Proposal (DPP) and Revised Development Project Proposal (RDPP) should be obtained as soon as possible by owner stakeholders. In order to avoid frequently changing the DPP, owners should also exercise greater caution when choosing contractors. Contractor stakeholders should use efficient and proper manpower and equipment so that unexpected delays are not created during the execution of work. Since the role of the contractor stakeholder is the most important among the three types of stakeholders, the contractor should raise awareness and urge the owners to get the RDPP approved quickly.

Originality/value

The findings from the study can help mitigate delays in infrastructure projects in BD, taking into account the perceptions of various stakeholders.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 26 December 2022

Hafiz Muhammad Arshad, Muhammad Waheed Akhtar, Muhammad Imran, Irem Batool, Muhammad Asrar-ul-Haq and Minhas Akbar

China–Pakistan Economic Corridor (CPEC) is a framework of regional connectivity in which employees have to work in a cross-cultural environment. This study has extended the…

Abstract

Purpose

China–Pakistan Economic Corridor (CPEC) is a framework of regional connectivity in which employees have to work in a cross-cultural environment. This study has extended the leader-member exchange theory by investigating the mediating role of employee commitment (EC) between the relationship of leader-member exchange (LMX) and employee's work-related behaviors.

Design/methodology/approach

PLS-SEM technique was used to test the model by utilizing a multi-wave/two-source data collected from employees and their supervisors (n = 500) working in different energy projects of CPEC.

Findings

According to the results/findings, LMX has a significant positive impact on employee commitment, employee performance (EP) and open-minded discussions, but insignificant impact on innovative work behaviour (IWB). Mediating role of employee commitment was significant between the relationship of LMX with EP and open-minded discussions, but insignificant with the IWB.

Originality/value

The study contributes empirical evidence to understanding the leader-member exchange relationship among Chinese managers and Pakistani workers. It also contributes to the LMX theory literature by investigating the effect of LMX on followers' outcomes (employee performance, IWB, open-minded discussions) through employee commitment.

Details

Kybernetes, vol. 53 no. 4
Type: Research Article
ISSN: 0368-492X

Keywords

Article
Publication date: 6 September 2022

Namal Thilakarathne, Akila Pramodh Rathnasinghe, Udayangani Kulatunga, Niraj Thurairajah and Lichini Weerasinghe

Most developing countries, such as Sri Lanka (SL), are now looking for the support of foreign construction companies for large-scale infrastructure projects in return for…

Abstract

Purpose

Most developing countries, such as Sri Lanka (SL), are now looking for the support of foreign construction companies for large-scale infrastructure projects in return for expertise and resources. Thus, foreign companies may enter into agreements with local contractors through joint ventures (JVs). However, the priorities of construction project stakeholders may differ, which may ultimately end up in conflicts. Therefore, this research aims to investigate the most suitable conflict management strategies for international construction JVs (ICJVs) considering the SL context.

Design/methodology/approach

The mixed method was used for the research choice by selecting a questionnaire survey and expert interviews. Completed questionnaires (n = 78) were analysed using statistical techniques. The expert interviews with six industry practitioners were piloted to increase the validity and credibility of survey findings through a triangulation process where the collected data was analysed through content analysis.

Findings

The findings confirm that JV parties should first seek collaborative solutions in a conflict and seek legal redress only when those efforts are unsuccessful. Collaborating and compromising were recommended as the most appropriate tactics if an informal approach to conflict management was chosen. Alternative dispute resolution and litigation were identified as formal conflict management strategies.

Originality/value

This study, to the best of the authors’ knowledge, will be the first of its kind in SL, which will lead to a better understanding of conflict management in IJCVs and will encourage other researchers to extend this study through further work.

Details

Journal of Financial Management of Property and Construction , vol. 28 no. 3
Type: Research Article
ISSN: 1366-4387

Keywords

Open Access
Article
Publication date: 18 April 2023

Tommi Pauna, Jere Lehtinen, Jaakko Kujala and Kirsi Aaltonen

The aim of this research was to understand how governmental stakeholder engagement facilitates the sustainability of industrial engineering (IE) projects. A model for governmental…

2131

Abstract

Purpose

The aim of this research was to understand how governmental stakeholder engagement facilitates the sustainability of industrial engineering (IE) projects. A model for governmental stakeholder engagement activities is presented.

Design/methodology/approach

The authors relied on a single-case study of a mining project in Northern Europe, where a novel collaboration and engagement approach with governmental stakeholders was piloted in the project's front-end phase. The analysis focused on the collaborative practices through which the IE project investor engaged governmental stakeholders during the project's front-end phase and how the engagement contributed to solving challenges in the early planning and permitting process and achieving project plans that balanced economic, social and environmental aspects.

Findings

The findings show how four collaborative engagement practices reduced uncertainty and equivocality related to the legal sustainability requirements, enabled the development of sustainable design solutions and overall accelerated the permitting process without compromising the quality of final project plans.

Practical implications

The findings can be used to plan governmental stakeholder engagement and understand related challenges that need to be overcome. The study highlights the need to develop established practices and guidelines for governmental stakeholder engagement.

Originality/value

This study complements prior research on stakeholder engagement and project sustainability by developing an understanding of how governmental stakeholder engagement can be a key mechanism enabling the sustainability of IE project's end product. This research contributes to stakeholder theory by elaborating on a new stakeholder role, intermediary stakeholder.

Details

International Journal of Managing Projects in Business, vol. 16 no. 8
Type: Research Article
ISSN: 1753-8378

Keywords

Article
Publication date: 27 December 2022

Bright Awuku, Eric Asa, Edmund Baffoe-Twum and Adikie Essegbey

Challenges associated with ensuring the accuracy and reliability of cost estimation of highway construction bid items are of significant interest to state highway transportation…

Abstract

Purpose

Challenges associated with ensuring the accuracy and reliability of cost estimation of highway construction bid items are of significant interest to state highway transportation agencies. Even with the existing research undertaken on the subject, the problem of inaccurate estimation of highway bid items still exists. This paper aims to assess the accuracy of the cost estimation methods employed in the selected studies to provide insights into how well they perform empirically. Additionally, this research seeks to identify, synthesize and assess the impact of the factors affecting highway unit prices because they affect the total cost of highway construction costs.

Design/methodology/approach

This paper systematically searched, selected and reviewed 105 papers from Scopus, Google Scholar, American Society of Civil Engineers (ASCE), Transportation Research Board (TRB) and Science Direct (SD) on conceptual cost estimation of highway bid items. This study used content and nonparametric statistical analyses to determine research trends, identify, categorize the factors influencing highway unit prices and assess the combined performance of conceptual cost prediction models.

Findings

Findings from the trend analysis showed that between 1983 and 2019 North America, Asia, Europe and the Middle East contributed the most to improving highway cost estimation research. Aggregating the quantitative results and weighting the findings using each study's sample size revealed that the average error between the actual and the estimated project costs of Monte-Carlo simulation models (5.49%) performed better compared to the Bayesian model (5.95%), support vector machines (6.03%), case-based reasoning (11.69%), artificial neural networks (12.62%) and regression models (13.96%). This paper identified 41 factors and was grouped into three categories, namely: (1) factors relating to project characteristics; (2) organizational factors and (3) estimate factors based on the common classification used in the selected papers. The mean ranking analysis showed that most of the selected papers used project-specific factors more when estimating highway construction bid items than the other factors.

Originality/value

This paper contributes to the body of knowledge by analyzing and comparing the performance of highway cost estimation models, identifying and categorizing a comprehensive list of cost drivers to stimulate future studies in improving highway construction cost estimates.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 3
Type: Research Article
ISSN: 0969-9988

Keywords

1 – 10 of over 1000