Search results

1 – 10 of 83
Article
Publication date: 25 March 2024

Francis Nuako, Frank Ato Ghansah and Thomas Adusei

It is widely accepted that one criterion for determining if a construction project is successful is whether it is completed within the expected budget. There have been…

Abstract

Purpose

It is widely accepted that one criterion for determining if a construction project is successful is whether it is completed within the expected budget. There have been advancements in the management of building projects throughout time but cost overruns remain a key concern in the construction sector internationally, particularly in emerging economies such as Ghana. This study aims to answer the question, “What are the critical success factors (CSFs) that can assist reduce cost overruns in public sector infrastructure projects in the Ghanaian construction industry?”

Design/methodology/approach

This study used a quantitative survey method. The questionnaire was pre-tested by interviewing 15 contractors to ascertain the validity of the content. Factor analysis and multiple regression were adopted to analyze the data.

Findings

This study discovered that the critical factors that can reduce cost overruns in construction projects in Ghana are directly linked to five themes: early contractor involvement in the project planning stage, adequate funding, good project team relations, competent managers/supervisors and project participant incentives/bonuses. This study identifies indestructible, empirically measurable important success criteria for reducing cost overruns in public building projects in Ghana.

Practical implications

When well thought through from the project initiation stage to completion, these critical successes can also be used to deal with damaging economic effects such as allocative inefficiency of scarce resources, further delays, contractual disputes, claims and litigation, project failure and total abandonment.

Originality/value

The uniqueness of this research resides in the fact that it is, to the best of the authors’ knowledge, a first-of-its-kind investigation of the CSFs for reducing cost overruns in public building projects in developing countries.

Details

Construction Innovation , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 2 April 2024

Nikhitha Adepu, Sharareh Kermanshachi, Apurva Pamidimukkala and Emily Nwakpuda

The building sector is vital to a nation’s economy, as it has a major influence on economic activity and growth, job creations and the advancement of infrastructure. Intricate…

Abstract

Purpose

The building sector is vital to a nation’s economy, as it has a major influence on economic activity and growth, job creations and the advancement of infrastructure. Intricate challenges that are inherent in crises such as the COVID-19 outbreak lead to material scarcities, project delays, labor shortages, escalated expenses, funding challenges, regulatory obstacles and dwindling investment funds, all of which culminate in costs that are in excess of those budgeted. While numerous studies have explored the ramifications of COVID-19 on project budgets, there is little, if any, data available on forecasting the magnitude of this impact.

Design/methodology/approach

This investigation seeks to bridge this knowledge deficiency by devising a predictive tool grounded in an ordinal logistic regression method. An online survey was designed and disseminated to gauge the views of construction field experts about the diverse contributors to excessive costs during the viral outbreak, and a predictive tool, crafted from the survey participants’ feedback.

Findings

Findings showed that smaller-scale enterprises and contractor-centric establishments faced greater adversities than medium-to-large ones and consultancy-or-owner-type entities.

Originality/value

The insights from this research shed light on the amplified risk of higher project costs amid health crises or analogous events, underlining the imperative need for fortified risk management approaches to bolster project outcomes. By factoring in demographics, this research offers policymakers a refined lens through which to customize interventions and promote balanced and enduring advancement in the construction industry.

Details

Smart and Sustainable Built Environment, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 2046-6099

Keywords

Article
Publication date: 14 February 2024

Tiep Nguyen, Nicholas Chileshe, Duc Ty Ho, Viet Thanh Nguyen and Quang Phu Tran

Urban rail projects are typically large-scale transport infrastructure projects (megaprojects) which have many potential risks that can influence the strategic goals of owners…

Abstract

Purpose

Urban rail projects are typically large-scale transport infrastructure projects (megaprojects) which have many potential risks that can influence the strategic goals of owners. However, there is a paucity of studies which explore the impact of risks on both “urban rail” project time and cost together considering quantitative assessments. Therefore, this paper focuses on investigating critical risks and quantifying such risk impacts on urban railway project schedule and cost in practice.

Design/methodology/approach

A combination of qualitative and quantitative research methods comprising semi-interviews with five experts and a questionnaire survey of 132 professional respondents is used. The data were modeled using Monte Carlo Simulation to predict the probability of project schedule and cost.

Findings

The results show that 30 risk variables are categorized into seven main groups which have significant impacts on both project time and cost. Outstanding five risk variables were highlighted as follows: (1) project site clearance and land compensation; (2) design changes; (3) physical project resources; (4) contractors’ competencies and (5) project finance. Such findings were supported by Monte Carlo simulation which predicted in the worst case that the project may suffer 11.03 months’ delays and have cost overrun with a contingency of US$287.68 million.

Originality/value

This study expands our knowledge about time and cost contingency of urban metro railway implementation across developing economies and particularly within the context of Vietnam. Policymakers will not only gain an understanding about risk structure but will also recognize the significant impacts of critical risk through risk impact modeling and simulation. Such an approach provides insights into risk treatment priorities for planners so that they can proactively establish suitable strategies for risk mitigation in practice.

Details

Built Environment Project and Asset Management, vol. 14 no. 2
Type: Research Article
ISSN: 2044-124X

Keywords

Article
Publication date: 13 July 2023

Haitham Alajmani, Salma Ahmed and Sameh Monir El-Sayegh

This paper aims to measure the severity, frequency and importance of the factors causing delays in the United Arab Emirates (UAE) construction industry following the Covid-19…

Abstract

Purpose

This paper aims to measure the severity, frequency and importance of the factors causing delays in the United Arab Emirates (UAE) construction industry following the Covid-19 pandemic onset. The study also measures the likelihood of the effects caused by these delays.

Design/methodology/approach

A mixed approach of both qualitative and quantitative. Literature review was conducted to extract 40 factors of delays and 10 effects of delays. A survey was then administered to construction professionals in the UAE to collect the perceptions on the severity and frequency of factors of the causes of delays using a Likert Scale of 1–5 where 1 represented very low and 5 represented very high. Similarly, the respondents were also asked to rate the likelihood of the occurrence of the effects of the delays based on a Likert scale of 1–5 as well. Furthermore, Spearman’s rank correlation was also conducted to compute the level of agreement between the different parties; owner, consultants and contractors.

Findings

The results revealed that the top five factors of delays include: award the project for the lowest bidder, delay in progress payment, change orders by the owner, poor subcontractor performance and inadequate planning and scheduling by the contractor. The findings of this study emphasize the financial challenges and economic crisis brought upon the construction industry due to the pandemic. Furthermore, the pandemic also shifted the perceptions of construction professionals, who are now more aware of the delays caused by awarding the project to the lowest bidder who would not have the required qualifications to conduct efficient planning and scheduling that are relevant in the case of extraordinary events such as Covid-19. Moreover, a high level of agreement between the consultants and contractors was observed, with a Spearman’s rank correlation of 0.804. Additionally, the most likely effects of delays concluded from this study were time overrun/extension and poor quality of work.

Originality/value

Literature review is very rich in the field of construction projects delays. However, there is very limited research on the impact of Covid-19 in the context of construction projects delays, and insights from construction professionals regarding this matter are particularly lacking in literature. Therefore, this paper bridges the gap in literature by providing perceptions of construction professionals on the impact of Covid-19 on the factors causing delays in the UAE construction industry. The findings of this research are expected to be an invaluable resource for future to help the construction industry heal faster when encountering similar epidemics or extraordinary events.

Details

Journal of Financial Management of Property and Construction , vol. 29 no. 1
Type: Research Article
ISSN: 1366-4387

Keywords

Article
Publication date: 28 March 2024

Chinthaka Niroshan Atapattu, Niluka Domingo and Monty Sutrisna

The current estimation practice in construction projects greatly needs upgrading, as there has been no improvement in the cost overrun issue over the past 70 years. The purpose of…

Abstract

Purpose

The current estimation practice in construction projects greatly needs upgrading, as there has been no improvement in the cost overrun issue over the past 70 years. The purpose of this research was to develop a new multiple regression analysis (MRA)-based model to forecast the final cost of road projects at the pre-design stage using data from 43 projects in New Zealand (NZ).

Design/methodology/approach

The research used the case study of 43 completed road projects in NZ. Document analysis was conducted to collect data, and statistical tests were used for model development and analysis.

Findings

Eight models were developed, and all models achieved the required F statistics and met the regression assumptions. The models’ mean absolute percentage error (MAPE) was between 21.25% and 22.77%. The model with the lowest MAPE comprised the road length and width, number of bridges, pavement area, cut and fill area, preliminary cost and cost indices change.

Research limitations/implications

The model is based on road projects in NZ. However, it was designed to be able to adapt to other contexts. The findings suggest that the model can be used to improve traditional conceptual estimating methods. Past project data is often stored by the project team but rarely used for analysing and forecasting purposes. This research emphasises that past data can be effectively used to predict the project cost at the pre-design stage with limited information.

Originality/value

No research was conducted to adopt cost modelling techniques into the conceptual estimation practice in the NZ construction industry.

Details

Journal of Financial Management of Property and Construction , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1366-4387

Keywords

Open Access
Article
Publication date: 19 April 2024

Atupakisye Mwakolo, Meshack Siwandeti, Leticia Mahuwi and Baraka Israel

The study aims to explore the role of procurement of good governance (PGG) on value for money (VfM) achievement in public construction projects. By investigating various…

Abstract

Purpose

The study aims to explore the role of procurement of good governance (PGG) on value for money (VfM) achievement in public construction projects. By investigating various dimensions of PGG, including transparency, accountability, competition and integrity, this study provides insights into how these factors contribute to the successful achievement of VfM outcomes in public construction projects.

Design/methodology/approach

The data were sourced from 203 construction project practitioners from 24 selected procuring entities in Tanzania using a census approach and a cross-sectional questionnaire survey. Confirmatory factor analysis (CFA) and structural equation modelling (SEM) were used for data analysis.

Findings

The findings of the study revealed a positive and significant impact of various dimensions of PGG on VfM. Specifically, transparency, accountability, competition and integrity were positively and significantly related to VfM, with p-values <0.001. Based on the study findings, we conclude that PGG is an important predictor of VfM achievement in public construction projects.

Practical implications

The study offers policy implications for streamlined PGG and VfM achievement in public construction projects. It is suggested that procuring entities can enhance VfM by enforcing compliance with the principles of PGG throughout the entirety of construction projects. In this case, streamlined legislative frameworks and control mechanisms are crucial components that could enhance PGG and the achievement of VfM.

Originality/value

This study contributes to the academic literature on the strategic role of PGG in enhancing VfM achievement. This is one of the research domains, which has not been adequately researched, particularly in Tanzania’s context. In addition, the study provides valuable insights to policymakers, practitioners and stakeholders involved in public construction projects to improve project outcomes and resource allocation.

Details

LBS Journal of Management & Research, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0972-8031

Keywords

Article
Publication date: 18 April 2024

S. Sarkar

Globally, consumer’s inclination towards functional foods had noticed due to their greater health consciousness coupled with enhanced health-care cost. The fact that probiotics…

Abstract

Purpose

Globally, consumer’s inclination towards functional foods had noticed due to their greater health consciousness coupled with enhanced health-care cost. The fact that probiotics could promote a healthier gut microbiome led projection of probiotic foods as functional foods and had emerged as an important dietary strategy for improved human health. It had established that ice cream was a better carrier for probiotics than fermented milked due to greater stability of probiotics in ice cream matrix. Global demand for ice cream boomed and probiotic ice cream could have been one of the most demanded functional foods. The purpose of this paper was to review the technological aspects and factors affecting probiotic viability and to standardize methodology to produce functional probiotic ice cream.

Design/methodology/approach

Attempt was made to search the literature (review and researched papers) to identify diverse factors affecting the probiotic viability and major technological challenge faced during formulation of probiotic ice cream. Keywords used for data searched included dairy-based functional foods, ice cream variants, probiotic ice cream, factors affecting probiotic viability and health benefits of probiotic ice cream.

Findings

Retention of probiotic viability at a level of >106 cfu/ml is a prerequisite for functional probiotic ice creams. Functional probiotic ice cream could have been produced with the modification of basic mix and modulating technological parameters during processing and freezing. Functionality can be further enhanced with the inclusion of certain nutraceutical components such as prebiotics, antioxidant, phenolic compounds and dietary fibres. Based upon reviewed literature, suggested method for the manufacture of functional probiotic ice cream involved freezing of a probiotic ice cream mix obtained by blending 10% probiotic fermented milk with 90% non-fermented plain ice cream mix for higher probiotic viability. Probiotic ice cream with functional features, comparable with traditional ice cream in terms of technological and sensory properties could be produced and can crop up as a novel functional food.

Originality/value

Probiotic ice cream with functional features may attract food manufacturers to cater health-conscious consumers.

Details

Nutrition & Food Science , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0034-6659

Keywords

Article
Publication date: 28 November 2023

Shiqin Zeng, Frederick Chung and Baabak Ashuri

Completing Right-of-Way (ROW) acquisition process on schedule is critical to avoid delays and cost overruns on transportation projects. However, transportation agencies face…

Abstract

Purpose

Completing Right-of-Way (ROW) acquisition process on schedule is critical to avoid delays and cost overruns on transportation projects. However, transportation agencies face challenges in accurately forecasting ROW acquisition timelines in the early stage of projects due to complex nature of acquisition process and limited design information. There is a need of improving accuracy of estimating ROW acquisition duration during the early phase of project development and quantitatively identifying risk factors affecting the duration.

Design/methodology/approach

The quantitative research methodology used to develop the forecasting model includes an ensemble algorithm based on decision tree and adaptive boosting techniques. A dataset of Georgia Department of Transportation projects held from 2010 to 2019 is utilized to demonstrate building the forecasting model. Furthermore, sensitivity analysis is performed to identify critical drivers of ROW acquisition durations.

Findings

The forecasting model developed in this research achieves a high accuracy to predict ROW durations by explaining 74% of the variance in ROW acquisition durations using project features, which is outperforming single regression tree, multiple linear regression and support vector machine. Moreover, number of parcels, average cost estimation per parcel, length of projects, number of condemnations, number of relocations and type of work are found to be influential factors as drivers of ROW acquisition duration.

Originality/value

This research contributes to the state of knowledge in estimating ROW acquisition timeline through (1) developing a novel machine learning model to accurately estimate ROW acquisition timelines, and (2) identifying drivers (i.e. risk factors) of ROW acquisition durations. The findings of this research will provide transportation agencies with insights on how to improve practices in scheduling ROW acquisition process.

Details

Built Environment Project and Asset Management, vol. 14 no. 2
Type: Research Article
ISSN: 2044-124X

Keywords

Article
Publication date: 7 February 2022

Bankole Osita Awuzie, Zwelinzima P. Mcwari, Progress Shingai Chigangacha, Clinton Ohis Aigbavboa, Theo C. Haupt and Lovelin Obi

An increase in outsourcing of consultancy services has been observed during procurement and delivery of public-sector infrastructure projects. However, the incidence of project…

Abstract

Purpose

An increase in outsourcing of consultancy services has been observed during procurement and delivery of public-sector infrastructure projects. However, the incidence of project failure has continued unabated despite this shift by public-sector entities. Also, there appears to be limited literature focussed on seeking to provide the rationale governing the decision to outsource or insource consultancy services by public-sector organisations. The purpose of this study was to appraise the performance of public-sector projects in which consultancy services have been outsourced or insourced. These are the gaps which this study was undertaken to fill.

Design/methodology/approach

A grounded theory methodology (GTM) research design was adopted based on the nature of evidence sought and gathered from a Provincial Department of Public Works and Infrastructure (PDPWI) in South Africa. Data was obtained from a mixture of semi-structured interviews and project-specific documents spanning a five-year period and was analysed according to the procedures associated with GTM. Accordingly, open coding, axial coding and pattern matching were carried out at several intervals to develop categories and themes.

Findings

The findings of the study showed the absence of a structured approach within the PDPWI for facilitating decisions pertaining to outsourcing or insourcing consultancy services within construction projects. Furthermore, the study established that both approaches yielded similar results across all performance facets of cost, time and quality. In addition, a detailed insight into the steps required for the successful application of GTM in built environment research has been provided in the study.

Originality/value

Limited studies have been undertaken to compare the impact of either outsourced or insourced services on the organisational and project performance. This was the gap to which the study reported in this paper was undertaken to contribute.

Details

Journal of Engineering, Design and Technology , vol. 22 no. 2
Type: Research Article
ISSN: 1726-0531

Keywords

Open Access
Article
Publication date: 28 February 2024

Hassan Th. Alassafi, Khalid S. Al-Gahtani, Abdulmohsen S. Almohsen and Abdullah M. Alsugair

Heating, ventilating, air-conditioning and cooling (HVAC) systems are crucial in daily health-care facility services. Design-related defects can lead to maintenance issues…

Abstract

Purpose

Heating, ventilating, air-conditioning and cooling (HVAC) systems are crucial in daily health-care facility services. Design-related defects can lead to maintenance issues, causing service disruptions and cost overruns. These defects can be avoided if a link between the early design stages and maintenance feedback is established. This study aims to use experts’ experience in HVAC maintenance in health-care facilities to list and evaluate the risk of each maintenance issue caused by a design defect, supported by the literature.

Design/methodology/approach

Following semistructured interviews with experts, 41 maintenance issues were identified as the most encountered issues. Subsequently, a survey was conducted in which 44 participants evaluated the probability and impact of each design-caused issue.

Findings

Chillers were identified as the HVAC components most prone to design defects and cost impact. However, air distribution ducts and air handling units are the most critical HVAC components for maintaining healthy conditions inside health-care facilities.

Research limitations/implications

The unavailability of comprehensive data on the cost impacts of all design-related defects from multiple health-care facilities limits the ability of HVAC designers to furnish case studies and quantitative approaches.

Originality/value

This study helps HVAC designers acquire prior knowledge of decisions that may have led to unnecessary and avoidable maintenance. These design-related maintenance issues may cause unfavorable health and cost consequences.

1 – 10 of 83