Article
Publication date: 28 March 2024

Chinthaka Niroshan Atapattu, Niluka Domingo and Monty Sutrisna

The current estimation practice in construction projects greatly needs upgrading, as there has been no improvement in the cost overrun issue over the past 70 years. The purpose of…

Abstract

Purpose

The current estimation practice in construction projects greatly needs upgrading, as there has been no improvement in the cost overrun issue over the past 70 years. The purpose of this research was to develop a new multiple regression analysis (MRA)-based model to forecast the final cost of road projects at the pre-design stage using data from 43 projects in New Zealand (NZ).

Design/methodology/approach

The research used the case study of 43 completed road projects in NZ. Document analysis was conducted to collect data, and statistical tests were used for model development and analysis.

Findings

Eight models were developed, and all models achieved the required F statistics and met the regression assumptions. The models’ mean absolute percentage error (MAPE) was between 21.25% and 22.77%. The model with the lowest MAPE comprised the road length and width, number of bridges, pavement area, cut and fill area, preliminary cost and cost indices change.

Research limitations/implications

The model is based on road projects in NZ. However, it was designed to be able to adapt to other contexts. The findings suggest that the model can be used to improve traditional conceptual estimating methods. Past project data is often stored by the project team but rarely used for analysing and forecasting purposes. This research emphasises that past data can be effectively used to predict the project cost at the pre-design stage with limited information.

Originality/value

No research was conducted to adopt cost modelling techniques into the conceptual estimation practice in the NZ construction industry.

Details

Journal of Financial Management of Property and Construction , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1366-4387

Keywords

Article
Publication date: 12 September 2023

Pramod Malaka Silva, Niluka Domingo and Noushad Ali Naseem Ameer Ali

The construction industry is complex, human-intensive and driven by monetary values. Hence, disputes are widespread. Initial conflicts among parties may develop into a disastrous…

Abstract

Purpose

The construction industry is complex, human-intensive and driven by monetary values. Hence, disputes are widespread. Initial conflicts among parties may develop into a disastrous dispute that costs the project success and good relationships and affects stakeholders' expectations. There has been a focus on causes of construction-related disputes, and studies over the past three decades have attempted to identify a more comprehensive list of reasons for disputes. Some of these studies' limitations were geographical, project delivery methods and project types. The purpose of this study is to identify the most recent and conclusive list of causes of disputes based on current literature by undertaking a systematic literature review (SLR).

Design/methodology/approach

Considering the large number of studies that focused on causes of disputes, this study aims to develop a comprehensive list of causes, using a SLR, as it ensures that all previous articles in multiple databases are reviewed to produce a comprehensive outcome. A six-stage SLR was followed from background study to analysis and reporting.

Findings

Not surprisingly, the number of publications has increased over time, most from the Middle East region. The interconnected nature of the causes was widely emphasised. The SLR has produced eight common core causes of disputes. They are: poor contractual arrangements, employer-initiated scope changes, unforeseen site changes, poor contract understanding and administration, contractor’s quality of works, the inability of the contractor to achieve time targets, non- or delayed payments and poor quality of design. The majority of previous authors realised that disputes could be avoided by parties’ involvement during the early stages, avoiding being opportunistic and acting collaboratively.

Originality/value

Even though numerous studies have been carried out to identify the causes of disputes in the construction industry, none did a SLR. This study aggregates all the previous studies that focused on construction-related disputes systematically. Categorising causes based on the party primarily responsible help various stakeholders by providing a distinct list of factors to avoid that contribute to disputes.

Details

Journal of Financial Management of Property and Construction , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1366-4387

Keywords

Article
Publication date: 11 October 2023

Chinthaka Niroshan Atapattu, Niluka Domingo and Monty Sutrisna

Cost overrun in infrastructure projects is a constant concern, with a need for a proper solution. The current estimation practice needs improvement to reduce cost overruns. This…

Abstract

Purpose

Cost overrun in infrastructure projects is a constant concern, with a need for a proper solution. The current estimation practice needs improvement to reduce cost overruns. This study aimed to find possible statistical modelling techniques that could be used to develop cost models to produce more reliable cost estimates.

Design/methodology/approach

A bibliographic literature review was conducted using a two-stage selection method to compile the relevant publications from Scopus. Then, Visualisation of Similarities (VOS)-Viewer was used to develop the visualisation maps for co-occurrence keyword analysis and yearly trends in research topics.

Findings

The study found seven primary techniques used as cost models in construction projects: regression analysis (RA), artificial neural network (ANN), case-based reasoning (CBR), fuzzy logic, Monte-Carlo simulation (MCS), support vector machine (SVM) and reference class forecasting (RCF). RA, ANN and CBR were the most researched techniques. Furthermore, it was observed that the model's performance could be improved by combining two or more techniques into one model.

Research limitations/implications

The research was limited to the findings from the bibliometric literature review.

Practical implications

The findings provided an assessment of statistical techniques that the industry can adopt to improve the traditional estimation practice of infrastructure projects.

Originality/value

This study mapped the research carried out on cost-modelling techniques and analysed the trends. It also reviewed the performance of the models developed for infrastructure projects. The findings could be used to further research to develop more reliable cost models using statistical modelling techniques with better performance.

Details

Smart and Sustainable Built Environment, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 2046-6099

Keywords

Article
Publication date: 27 February 2023

Bindhu Kumari Sreekandan Nair Nidhin, Niluka Domingo, Thao Thi Phuong Bui and Suzanne Wilkinson

In light of climate change, the design and construction of buildings needs to shift from conventional to lower-carbon practices to maximise carbon reduction. Over the past few…

Abstract

Purpose

In light of climate change, the design and construction of buildings needs to shift from conventional to lower-carbon practices to maximise carbon reduction. Over the past few years, the zero carbon buildings (ZCBs) approach has been promoted worldwide as an effective way to reduce environmental impacts and mitigate climate change. Although zero-carbon policies, technologies, processes and products are widely available in the construction market, construction stakeholders play an important part in adopting relevant strategies to implement ZCBs successfully. This study investigates the knowledge of construction stakeholders involved in the design and construction of buildings regarding zero carbon initiatives in New Zealand.

Design/methodology/approach

The research was conducted using a literature review and an online questionnaire survey with various New Zealand's construction stakeholders.

Findings

The findings indicate a low level of knowledge regarding the design and construction of ZCBs. To successfully deliver ZCBs, the study suggests that construction stakeholders must have their self-awareness increased, especially in improving knowledge of whole-of-life embodied carbon reduction. The governments and construction sectors should devote more effort to establishing training programmes and knowledge-sharing platforms to improve stakeholder knowledge in carbon literacy, building assessment methods, energy modelling and life cycle assessment.

Originality/value

The research implications may assist the real-world uptake of the ZCBs approach by offering academics and practitioners an insight into the ZCBs knowledge gaps.

Details

International Journal of Building Pathology and Adaptation, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 2398-4708