1 – 10 of 11Shiba Hessami, Hamed Davari-Ardakani, Youness Javid and Mariam Ameli
This study aims to deal with the multi-mode resource-constrained project scheduling problem (MRCPSP) with the ability to transport resources among multiple sites, aiming to…
Abstract
Purpose
This study aims to deal with the multi-mode resource-constrained project scheduling problem (MRCPSP) with the ability to transport resources among multiple sites, aiming to minimize the total completion time and the total cost of the project simultaneously.
Design/methodology/approach
To deal with the problem under consideration, a bi-objective optimization model is developed. All activities are interconnected by finish-start precedence relations, and pre-emption is not allowed. Then, the ɛ-constraint optimization method is used to solve 24 different-sized instances, ranging from 5 to 120 activities, and report the makespan, total cost and CPU time. A set of Pareto-optimal solutions are determined for some instances, and sensitivity analyses are performed to find the impact of changing parameters on objective values.
Findings
Results highlight the importance of resource transportability assumption on project completion time and cost, providing useful insights for decision makers and practitioners.
Originality/value
A novel bi-objective optimization model is proposed to deal with the multi-site MRCPSP, considering both the cost and time of resource transportation between multiple sites. To the best of the authors’ knowledge, none of the studies in the project scheduling area has yet addressed this problem.
Details
Keywords
Ehsan Goudarzi, Hamid Esmaeeli, Kia Parsa and Shervin Asadzadeh
The target of this research is to develop a mathematical model which combines the Resource-Constrained Multi-Project Scheduling Problem (RCMPSP) and the Multi-Skilled…
Abstract
Purpose
The target of this research is to develop a mathematical model which combines the Resource-Constrained Multi-Project Scheduling Problem (RCMPSP) and the Multi-Skilled Resource-Constrained Project Scheduling Problem (MSRCPSP). Due to the importance of resource management, the proposed formulation comprises resource leveling considerations as well. The model aims to simultaneously optimize: (1) the total time to accomplish all projects and (2) the total deviation of resource consumptions from the uniform utilization levels.
Design/methodology/approach
The K-Means (KM) and Fuzzy C-Means (FCM) clustering methods have been separately applied to discover the clusters of activities which have the most similar resource demands. The discovered clusters are given to the scheduling process as priori knowledge. Consequently, the execution times of the activities with the most common resource requests will not overlap. The intricacy of the problem led us to incorporate the KM and FCM techniques into a meta-heuristic called the Bi-objective Symbiosis Organisms Search (BSOS) algorithm so that the real-life samples of this problem could be solved. Therefore, two clustering-based algorithms, namely, the BSOS-KM and BSOS-FCM have been developed.
Findings
Comparisons between the BSOS-KM, BSOS-FCM and the BSOS method without any clustering approach show that the clustering techniques could enhance the optimization process. Another hybrid clustering-based methodology called the NSGA-II-SPE has been added to the comparisons to evaluate the developed resource leveling framework.
Practical implications
The practical importance of the model and the clustering-based algorithms have been demonstrated in planning several construction projects, where multiple water supply systems are concurrently constructed.
Originality/value
Reviewing the literature revealed that there was a need for a hybrid formulation that embraces the characteristics of the RCMPSP and MSRCPSP with resource leveling considerations. Moreover, the application of clustering algorithms as resource leveling techniques was not studied sufficiently in the literature.
Details
Keywords
Xin Zou and Zhuang Rong
In repetitive projects, repetition offers more possibilities for activity scheduling at the sub-activity level. However, existing resource-constrained repetitive scheduling…
Abstract
Purpose
In repetitive projects, repetition offers more possibilities for activity scheduling at the sub-activity level. However, existing resource-constrained repetitive scheduling problem (RCRSP) models assume that there is only one sequence in performing the sub-activities of each activity, resulting in an inefficient resource allocation. This paper proposes a novel repetitive scheduling model for solving RCRSP with soft logic.
Design/methodology/approach
In this paper, a constraint programming model is developed to solve the RCRSP using soft logic, aiming at the possible relationship between parallel execution, orderly execution or partial parallel and partial orderly execution of different sub activities of the same activity in repetitive projects. The proposed model integrated crew assignment strategies and allowed continuous or fragmented execution.
Findings
When solving RCRSP, it is necessary to take soft logic into account. If managers only consider the fixed logic between sub-activities, they are likely to develop a delayed schedule. The practicality and effectiveness of the model were verified by a housing project based on eight different scenarios. The results showed that the constraint programming model outperformed its equivalent mathematical model in terms of solving speed and solution quality.
Originality/value
Available studies assume a fixed logic between sub-activities of the same activity in repetitive projects. However, there is no fixed construction sequence between sub-activities for some projects, e.g. hotel renovation projects. Therefore, this paper considers the soft logic relationship between sub-activities and investigates how to make the objective optimal without violating the resource availability constraint.
Details
Keywords
This study develops a model and algorithm to solve the decentralized resource-constrained multi-project scheduling problem (DRCMPSP) and provides a suitable priority rule (PR) for…
Abstract
Purpose
This study develops a model and algorithm to solve the decentralized resource-constrained multi-project scheduling problem (DRCMPSP) and provides a suitable priority rule (PR) for coordinating global resource conflicts among multiple projects.
Design/methodology/approach
This study addresses the DRCMPSP, which respects the information privacy requirements of project agents; that is, there is no single manager centrally in charge of generating multi-project scheduling. Accordingly, a three-stage model was proposed for the decentralized management of multiple projects. To solve this model, a three-stage solution approach with a repeated negotiation mechanism was proposed.
Findings
The experimental results obtained using the Multi-Project Scheduling Problem LIBrary confirm that our approach outperforms existing methods, regardless of the average utilization factor (AUF). Comparative analysis revealed that delaying activities in the lower project makespan produces a lower average project delay. Furthermore, the new PR LMS performed better in problem subsets with AUF < 1 and large-scale subsets with AUF > 1.
Originality/value
A solution approach with a repeated-negotiation mechanism suitable for the DRCMPSP and a new PR for coordinating global resource allocation are proposed.
Details
Keywords
Jing An, Suicheng Li and Xiao Ping Wu
Project managers bear the responsibility of selecting and developing resource scheduling methods that align with project requirements and organizational circumstances. This study…
Abstract
Purpose
Project managers bear the responsibility of selecting and developing resource scheduling methods that align with project requirements and organizational circumstances. This study focuses on resource-constrained project scheduling in multi-project environments. The research simplifies the problem by adopting a single-project perspective using gain coefficients.
Design/methodology/approach
It employs uncertainty theory and multi-objective programming to construct a model. The optimal solution is identified using Matlab, while LINGO determines satisfactory alternatives. By combining these methods and considering actual construction project situations, a compromise solution closely approximating the optimal one is derived.
Findings
The study provides fresh insights into modeling and resolving resource-constrained project scheduling issues, supported by real-world examples that effectively illustrate its practical significance.
Originality/value
The research highlights three main contributions: effective resource utilization, project prioritization and conflict management, and addressing uncertainty. It offers decision support for project managers to balance resource allocation, resolve conflicts, and adapt to changing project demands.
Details
Keywords
Mohamed Marzouk and Dina Hamdala
The aggressive competition in the real estate market forces real estate developers to tackle the challenge of selecting the best project construction phasing alternative. The real…
Abstract
Purpose
The aggressive competition in the real estate market forces real estate developers to tackle the challenge of selecting the best project construction phasing alternative. The real estate industry is characterized by high costs, high profit and high risks. The schedules of real estate projects are also characterized by having large number of repetitive activities that are executed over a long duration. The repetitiveness, long duration of execution, the high amounts of money involved and the high risk made it desirable to leverage the impact of changes in phasing plans on net present value of amounts incurred and received over the long execution and selling duration. This also changes the project progress, and delivery time as well as their respective impact on customer degree of satisfaction. This research addresses the problem of selecting the best phasing alternative for real estate development projects while maximizing customer satisfaction and project profit.
Design/methodology/approach
The research proposes a model that generates all construction phasing alternatives and performs decision-making to rank all possible phasing alternatives. The proposed model consists of five modules: (1) Phasing Sequencing module, (2) Customer Satisfaction module, (3) Cash-In calculation module, (4) Cost Estimation module and (5) Decision-making module. A case study was presented to demonstrate the practicality of the model.
Findings
The proposed model satisfies the real estate market's need for proper construction phasing plans evaluation and selection against the project's main success criteria, customer satisfaction and project profit. The proposed model generates all construction phasing alternatives and performs multi-criteria decision making to rank all possible phasing alternatives. It quantifies the score of the two previously mentioned criteria and ranks all solutions according to their overall score.
Research limitations/implications
The research proposes a model that assist real estate market's need for proper construction phasing plans evaluation and selection against the project's main success criteria, customer satisfaction and project profit. The proposed model can be used to conclude general guidelines and common successful practices to be used by real estate developers when deciding the construction phasing plan. In this study the model is based on business models where all the project units are sold, rental cases are not considered. Also, the budget limitations that might exist when phasing is not considered in the model computations.
Originality/value
The model can be used as a complete platform that can hold all real estate project data, process revenues and cost information for estimating profit, plotting cash flow profiles, quantifying the degree of customer satisfaction attributable to each phasing alternative and providing recommendation showing the best one. The model can be used to conclude general guidelines and common successful practices to be used by real estate developers when tackling the challenge of selecting construction phasing plans.
Details
Keywords
Masoud Parsi, Vahid Baradaran and Amir Hossein Hosseinian
The purpose of this study is to develop an integrated model for the stochastic multiproject scheduling and material ordering problems, where some of the prominent features of…
Abstract
Purpose
The purpose of this study is to develop an integrated model for the stochastic multiproject scheduling and material ordering problems, where some of the prominent features of offshore projects and their environmental-degrading effects have been embraced as well. The durations of activities are uncertain in this model. The developed formulation is tri-objective that seeks to minimize the expected time, total cost and CO2 emission of all projects.
Design/methodology/approach
A new version of the multiobjective multiagent optimization (MOMAO) algorithm has been proposed to solve the amalgamated model. To empower the MOMAO, various procedures of this algorithm have been modified based on the multiattribute utility theory (MAUT) technique. Along with the MOMAO, this study has employed four other meta-heuristic methodologies to solve the model as well.
Findings
The outputs of the MOMAO have been put to test against four other optimizers in terms of convergence, diversity, uniformity and computation times. The results of the Mean Ideal Distance (MID) metric have revealed that the MOMAO has strongly prevailed its rival optimizers. In terms of diversity of the acquired solutions, the MOMAO has ranked the first among all employed optimizers since this algorithm has offered the best solutions in 56.66 and 63.33% of the test problems regarding the diversification metric and hyper-volume metrics. Regarding the uniformity of results, which is measured through the spacing metric (SP), the MOMAO has presented the best SP values in more than 96% of the test problems. The MOMAO has needed more computation times in comparison to its rivals.
Practical implications
A real case study comprising two concurrent offshore projects has been offered. The proposed formulation and the MOMAO have been implemented for this case study, and their effectiveness has been appraised.
Originality/value
Very few studies have focused on presenting an integrated formulation for the stochastic multiproject scheduling and material ordering problems. The model embraces some of the characteristics of the offshore projects which have not been adequately studied in the literature. Limited capacities of the offshore platforms and cargo vessels have been embedded in the proposed model. The offshore platforms have spatial limitations in storing the required materials. The vessels are also capacitated and they also have limited shipment capacities. Some of the required materials need to be transported from the base to the offshore platform via a fleet of cargo vessels. The workforces and equipment can become idle on the offshore platform due to material shortage. Various offshore-related costs have been integrated as a minimization objective function in the model. The cargo vessels release CO2 detrimental emissions to the environment which are sought to be minimized in the developed formulation. To the best of the authors' knowledge, the MOMAO has not been sufficiently employed as a solution methodology for the stochastic multiproject scheduling and material ordering problems.
Details
Keywords
Junlong Peng and Xiang-Jun Liu
This research is aimed to mainly be applicable to expediting engineering projects, uses the method of inverse optimization and the double-layer nested genetic algorithm combined…
Abstract
Purpose
This research is aimed to mainly be applicable to expediting engineering projects, uses the method of inverse optimization and the double-layer nested genetic algorithm combined with nonlinear programming algorithm, study how to schedule the number of labor in each process at the minimum cost to achieve an extremely short construction period goal.
Design/methodology/approach
The method of inverse optimization is mainly used in this study. In the first phase, establish a positive optimization model, according to the existing labor constraints, aiming at the shortest construction period. In the second phase, under the condition that the expected shortest construction period is known, on the basis of the positive optimization model, the inverse optimization method is used to establish the inverse optimization model aiming at the minimum change of the number of workers, and finally the optimal labor allocation scheme that meets the conditions is obtained. Finally, use algorithm to solve and prove with a case.
Findings
The case study shows that this method can effectively achieve the extremely short duration goal of the engineering project at the minimum cost, and provide the basis for the decision-making of the engineering project.
Originality/value
The contribution of this paper to the existing knowledge is to carry out a preliminary study on the relatively blank field of the current engineering project with a very short construction period, and provide a path for the vast number of engineering projects with strict requirements on the construction period to achieve a very short construction period, and apply the inverse optimization method to the engineering field. Furthermore, a double-nested genetic algorithm and nonlinear programming algorithm are designed. It can effectively solve various optimization problems.
Details
Keywords
Libiao Bai, Mengqin Yang, Tong Pan and Yichen Sun
Selecting and scheduling optimal project portfolio simultaneously is a complex decision-making problem faced by organizations to realize the strategy. However, dynamic synergy…
Abstract
Purpose
Selecting and scheduling optimal project portfolio simultaneously is a complex decision-making problem faced by organizations to realize the strategy. However, dynamic synergy relationships among projects complicate this problem. This study aims at constructing a project portfolio selection and scheduling (PPSS) model while quantifying the dynamic synergetic effects to provide decision support for managing PPSS problems.
Design/methodology/approach
This study develops a mathematical model for PPSS with the objective of maximal project portfolio benefits (PPBs). To make the results align with the strategy, comprehensive PPBs are divided into financial and non-financial aspects based on the balanced scorecard. Then, synergy benefits evolve dynamically in the time horizon, and system dynamics is employed to quantify them. Lastly, a case example is conducted to verify the applicability of the proposed model.
Findings
The proposed model is an applicable model for PPSS while incorporating dynamic synergy. It can help project managers obtain the results that which project should be selected and when it should start while achieving optimal PPBs.
Originality/value
This study complements prior PPSS research in two aspects. First, financial and non-financial PPBs are designed as new criteria for PPSS, making the results follow the strategy. Second, this study illuminates the dynamic characteristic of synergy and quantifies the synergetic effect. The proposed model provides insights into managing a PPSS effectively.
Details
Keywords
The existing literature has been mainly focused on local problems but without an overall framework for studying the top-level planning of intelligent construction from a…
Abstract
Purpose
The existing literature has been mainly focused on local problems but without an overall framework for studying the top-level planning of intelligent construction from a systematic perspective. The purpose of this paper is to fill this gap.
Design/methodology/approach
This research adopts a deductive research approach.
Findings
This research proposes a reference architecture and related business scenario framework for intelligent construction based on the existing theory and industrial practice.
Originality/value
The main contribution of this research is to provide a useful reference to the Chinese government and industry for formulating digital transformation strategies, as well as suggests meaningful future research directions in the construction industry.