Deraniyagalage Chanaka Karunarathna, H.A.H.P. Perera, B.A.K.S. Perera and P.A.P.V.D.S. Disaratna

Delays in utility shifting during road construction have broad ramifications. These delays not only lengthen the project's timeline but also raise expenses and cause problems with…

Abstract

Purpose

Delays in utility shifting during road construction have broad ramifications. These delays not only lengthen the project's timeline but also raise expenses and cause problems with resource allocation. Thus, this study investigates the influence of delay in utility shifting for extension of time claims in road construction projects (RCPs) in Sri Lanka.

Design/methodology/approach

The study used a quantitative approach with three rounds of Delphi surveys to gather empirical data. Further, the probability impact assessment was used to carefully analyse the data and appraise the information gathered.

Findings

The findings initially revealed 33 causes of delays in utility shifting for extension of time claims in RCPs in Sri Lanka. Ultimately, 11 severe causes were identified based on their high probability and impact, concluding with 45 strategies that were assigned to overcoming those most severe causes of delay.

Originality/value

This study will contribute to the industry and theory by providing solutions to handle utility-shifting delays with the linkage of preventing time extension claims for RCPs in Sri Lanka. Further, there is a dearth of literature in the research area, both locally and globally. Thus, the findings of this research will provide a benchmark for further detailed studies in other countries as well.