Search results

1 – 10 of 555
Article
Publication date: 30 June 2023

Hana Begić, Mario Galić and Uroš Klanšek

Ready-mix concrete delivery problem (RMCDP), a specific version of the vehicle routing problem (VRP), is a relevant supply-chain engineering task for construction management with…

Abstract

Purpose

Ready-mix concrete delivery problem (RMCDP), a specific version of the vehicle routing problem (VRP), is a relevant supply-chain engineering task for construction management with various formulations and solving methods. This problem can range from a simple scenario involving one source, one material and one destination to a more challenging and complex case involving multiple sources, multiple materials and multiple destinations. This paper presents an Internet of Things (IoT)-supported active building information modeling (BIM) system for optimized multi-project ready-mix concrete (RMC) delivery.

Design/methodology/approach

The presented system is BIM-based, IoT supported, dynamic and automatic input/output exchange to provide an optimal delivery program for multi-project ready-mix-concrete problem. The input parameters are extracted as real-time map-supported IoT data and transferred to the system via an application programming interface (API) into a mixed-integer linear programming (MILP) optimization model developed to perform the optimization. The obtained optimization results are further integrated into BIM by conventional project management tools. To demonstrate the features of the suggested system, an RMCDP example was applied to solve that included four building sites, seven eligible concrete plants and three necessary RMC mixtures.

Findings

The system provides the optimum delivery schedule for multiple RMCs to multiple construction sites, as well as the optimum RMC quantities to be delivered, the quantities from each concrete plant that must be supplied, the best delivery routes, the optimum execution times for each construction site, and the total minimal costs, while also assuring the dynamic transfer of the optimized results back into the portfolio of multiple BIM projects. The system can generate as many solutions as needed by updating the real-time input parameters in terms of change of the routes, unit prices and availability of concrete plants.

Originality/value

The suggested system allows dynamic adjustments during the optimization process, andis adaptable to changes in input data also considering the real-time input data. The system is based on spreadsheets, which are widely used and common tool that most stakeholders already utilize daily, while also providing the possibility to apply a more specialized tool. Based on this, the RMCDP can be solved using both conventional and advanced optimization software, enabling the system to handle even large-scale tasks as necessary.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 16 November 2021

Saeid Jafarzadeh Ghoushchi, Iman Hushyar and Kamyar Sabri-Laghaie

A circular economy (CE) is an economic system that tries to eliminate waste and continually use resources. Due to growing environmental concerns, supply chain (SC) design should…

450

Abstract

Purpose

A circular economy (CE) is an economic system that tries to eliminate waste and continually use resources. Due to growing environmental concerns, supply chain (SC) design should be based on the CE considerations. In addition, responding and satisfying customers are the challenges managers constantly encounter. This study aims to improve the design of an agile closed-loop supply chain (CLSC) from the CE point of view.

Design/methodology/approach

In this research, a new multi-stage, multi-product and multi-period design of a CLSC network under uncertainty is proposed that aligns with the goals of CE and SC participants. Recycling of goods is an important part of the CLSC. Therefore, a multi-objective mixed-integer linear programming model (MILP) is proposed to formulate the problem. Besides, a robust counterpart of multi-objective MILP is offered based on robust optimization to cope with the uncertainty of parameters. Finally, the proposed model is solved using the e-constraint method.

Findings

The proposed model aims to provide the strategic choice of economic order to the suppliers and third-party logistic companies. The present study, which is carried out using a numerical example and sensitivity analysis, provides a robust model and solution methodology that are effective and applicable in CE-related problems.

Practical implications

This study shows how all upstream and downstream units of the SC network must work integrated to meet customer needs considering the CE context.

Originality/value

The main goal of the CE is to optimize resources, reduce the use of raw materials, and revitalize waste by recycling. In this study, a comprehensive model that can consider both SC design and CE necessities is developed that considers all SC participants.

Details

Journal of Enterprise Information Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1741-0398

Keywords

Article
Publication date: 26 January 2024

Mohsen Rajabzadeh, Seyed Meysam Mousavi and Farzad Azimi

This paper investigates a problem in a reverse logistics (RLs) network to decide whether to dispose of unsold goods in primary stores or re-commercialize them in outlet centers…

Abstract

Purpose

This paper investigates a problem in a reverse logistics (RLs) network to decide whether to dispose of unsold goods in primary stores or re-commercialize them in outlet centers. By deducting the costs associated with each policy from its revenue, this study aims to maximize the profit from managing unsold goods.

Design/methodology/approach

A new mixed-integer linear programming model has been developed to address the problem, which considers the selling prices of products in primary and secondary stores and the costs of transportation, cross-docking and returning unwanted items. As a result of uncertain nature of the cost and time parameters, gray numbers are used to deal with it. In addition, an innovative uncertain solution approach for gray programming problems is presented that considers objective function satisfaction level as an indicator of optimism.

Findings

According to the results, higher costs, including transportation, cross-docking and return costs, make sending goods to outlet centers unprofitable and more goods are disposed of in primary stores. Prices in primary and secondary stores heavily influence the number of discarded goods. Higher prices in primary stores result in more disposed of goods, while higher prices in secondary stores result in fewer. As a result of the proposed method, the objective function satisfaction level can be viewed as a measure of optimism.

Originality/value

An integral contribution of this study is developing a new mixed-integer linear programming model for selecting the appropriate goods for re-commercialization and choosing the best outlet center based on the products' price and total profit. Another novelty of the proposed model is considering the matching percentage of boxes with secondary stores’ desired product lists and the probability of returning goods due to non-compliance with delivery dates. Moreover, a new uncertain solution approach is developed to solve mathematical programming problems with gray parameters.

Details

Kybernetes, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0368-492X

Keywords

Article
Publication date: 26 September 2023

Yanhong Wu and Renlan Wang

From a supply chain perspective, logistics firms collaborate with other supply chain members to extend their business scope. Investment in circular economy projects in the supply…

Abstract

Purpose

From a supply chain perspective, logistics firms collaborate with other supply chain members to extend their business scope. Investment in circular economy projects in the supply chain can not only broaden the scope of business but also increase the value of the entire supply chain. Third-party logistics companies are gradually participating in the construction and operation of many circular economy projects. How to coordinate multiple circular economy supply chain projects is at the core of its operation.

Design/methodology/approach

This paper first analyzes some typical supply chain projects in China and summarizes the main features of these projects. Secondly, considering the benefits of the project and the stakes of each project, a multi-stage stochastic programming model is established. Finally, Cplex, nested decomposition, LocalSolver and other methods are adopted to simulate and analyze the model.

Findings

The final experimental results find that the importance of coordinating multiple circular economy supply chain projects to increase the value of the entire supply chain. The multi-stage stochastic programming model presented in this research can provide a useful tool for logistics enterprises and third-party logistics companies to optimize their investment decisions and maximize their profits in the context of a circular economy.

Research limitations/implications

There are still some limitations to this study; for example, it is limited to the analysis of circular economy supply chain projects in China. The study focused on third-party logistics companies, and other enterprises in the circular economy supply chain were not considered. The research also assumed that the benefits of each circular economy project and the stakes of each project were known, which may not always be the case in real-world scenarios.

Originality/value

This manuscript found that investing in other circular economy projects in the supply chain can broaden the scope of business and increase the value of the entire supply chain. Third-party logistics companies are gradually participating in the construction and operation of many circular economy projects, such as recycling and repurposing initiatives. It highlights the importance of coordinating multiple circular economy supply chain projects to increase the value of the entire supply chain. The multi-stage stochastic programming model presented in this research can provide a useful tool for logistics enterprises and third-party logistics companies to optimize their investment decisions and maximize their profits in the context of a circular economy.

Details

Management Decision, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0025-1747

Keywords

Article
Publication date: 13 July 2023

S.M. Taghavi, V. Ghezavati, H. Mohammadi Bidhandi and S.M.J. Mirzapour Al-e-Hashem

This paper proposes a two-level supply chain including suppliers and manufacturers. The purpose of this paper is to design a resilient fuzzy risk-averse supply portfolio selection…

Abstract

Purpose

This paper proposes a two-level supply chain including suppliers and manufacturers. The purpose of this paper is to design a resilient fuzzy risk-averse supply portfolio selection approach with lead-time sensitive manufacturers under partial and complete supply facility disruption in addition to the operational risk of imprecise demand to minimize the mean-risk costs. This problem is analyzed for a risk-averse decision maker, and the authors use the conditional value-at-risk (CVaR) as a risk measure, which has particular applications in financial engineering.

Design/methodology/approach

The methodology of the current research includes two phases of conceptual model and mathematical model. In the conceptual model phase, a new supply portfolio selection problem is presented under disruption and operational risks for lead-time sensitive manufacturers and considers resilience strategies for risk-averse decision makers. In the mathematical model phase, the stages of risk-averse two-stage fuzzy-stochastic programming model are formulated according to the above conceptual model, which minimizes the mean-CVaR costs.

Findings

In this paper, several computational experiments were conducted with sensitivity analysis by GAMS (General algebraic modeling system) software to determine the efficiency and significance of the developed model. Results show that the sensitivity of manufacturers to the lead time as well as the occurrence of disruption and operational risks, significantly affect the structure of the supply portfolio selection; hence, manufacturers should be taken into account in the design of this problem.

Originality/value

The study proposes a new two-stage fuzzy-stochastic scenario-based mathematical programming model for the resilient supply portfolio selection for risk-averse decision-makers under disruption and operational risks. This model assumes that the manufacturers are sensitive to lead time, so the demand of manufacturers depends on the suppliers who provide them with services. To manage risks, this model also considers proactive (supplier fortification, pre-positioned emergency inventory) and reactive (revision of allocation decisions) resilience strategies.

Article
Publication date: 26 March 2024

Jing An, Suicheng Li and Xiao Ping Wu

Project managers bear the responsibility of selecting and developing resource scheduling methods that align with project requirements and organizational circumstances. This study…

Abstract

Purpose

Project managers bear the responsibility of selecting and developing resource scheduling methods that align with project requirements and organizational circumstances. This study focuses on resource-constrained project scheduling in multi-project environments. The research simplifies the problem by adopting a single-project perspective using gain coefficients.

Design/methodology/approach

It employs uncertainty theory and multi-objective programming to construct a model. The optimal solution is identified using Matlab, while LINGO determines satisfactory alternatives. By combining these methods and considering actual construction project situations, a compromise solution closely approximating the optimal one is derived.

Findings

The study provides fresh insights into modeling and resolving resource-constrained project scheduling issues, supported by real-world examples that effectively illustrate its practical significance.

Originality/value

The research highlights three main contributions: effective resource utilization, project prioritization and conflict management, and addressing uncertainty. It offers decision support for project managers to balance resource allocation, resolve conflicts, and adapt to changing project demands.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 12 September 2023

Mohammad Hossein Dehghani Sadrabadi, Ahmad Makui, Rouzbeh Ghousi and Armin Jabbarzadeh

The adverse interactions between disruptions can increase the supply chain's vulnerability. Accordingly, establishing supply chain resilience to deal with disruptions and…

Abstract

Purpose

The adverse interactions between disruptions can increase the supply chain's vulnerability. Accordingly, establishing supply chain resilience to deal with disruptions and employing business continuity planning to preserve risk management achievements is of considerable importance. The aforementioned idea is discussed in this study.

Design/methodology/approach

This study proposes a multi-objective optimization model for employing business continuity management and organizational resilience in a supply chain for responding to multiple interrelated disruptions. The improved augmented e-constraint and the scenario-based robust optimization methods are adopted for multi-objective programming and dealing with uncertainty, respectively. A case study of the automotive battery manufacturing industry is also considered to ensure real-world conformity of the model.

Findings

The results indicate that interactions between disruptions remarkably increase the supply chain's vulnerability. Choosing a higher fortification level for the supply chain and foreign suppliers reduces disruption impacts on resources and improves the supply chain's resilience and business continuity. Facilities dispersion, fortification of facilities, lateral transshipment, order deferral policy, dynamic capacity planning and direct transportation of products to markets are the most efficient resilience strategies in the under-study industry.

Originality/value

Applying resource allocation planning and portfolio selection to adopt preventive and reactive resilience strategies simultaneously to manage multiple interrelated disruptions in a real-world automotive battery manufacturing industry, maintaining the long-term achievements of supply chain resilience using business continuity management and dynamic capacity planning are the main contributions of the presented paper.

Article
Publication date: 21 November 2023

Patrice Gaillardetz and Saeb Hachem

By using higher moments, this paper extends the quadratic local risk-minimizing approach in a general discrete incomplete financial market. The local optimization subproblems are…

Abstract

Purpose

By using higher moments, this paper extends the quadratic local risk-minimizing approach in a general discrete incomplete financial market. The local optimization subproblems are convex or nonconvex, depending on the moment variants used in the modeling. Inspired by Lai et al. (2006), the authors propose a new multiobjective approach for the combination of moments that is transformed into a multigoal programming problem.

Design/methodology/approach

The authors evaluate financial derivatives with American features using local risk-minimizing strategies. The financial structure is in line with Schweizer (1988): the market is discrete, self-financing is not guaranteed, but deviations are controlled and reduced by minimizing the second moment. As for the quadratic approach, the algorithm proceeds backwardly.

Findings

In the context of evaluating American option, a transposition of this multigoal programming leads not only to nonconvex optimization subproblems but also to the undesirable fact that local zero deviations from self-financing are penalized. The analysis shows that issuers should consider some higher moments when evaluating contingent claims because they help reshape the distribution of global cumulative deviations from self-financing.

Practical implications

A detailed numerical analysis that compares all the moments or some combinations of them is performed.

Originality/value

The quadratic approach is extended by exploring other higher moments, positive combinations of moments and variants to enforce asymmetry. This study also investigates the impact of two types of exercise decisions and multiple assets.

Details

Studies in Economics and Finance, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1086-7376

Keywords

Article
Publication date: 22 January 2024

Md. Tareq Hossain Khondoker, Md. Mehrab Hossain and Ayan Saha

Due to its longer length compared to other construction materials and distinctive stacking patterns, obtaining construction steel bars in congested construction sites with limited…

Abstract

Purpose

Due to its longer length compared to other construction materials and distinctive stacking patterns, obtaining construction steel bars in congested construction sites with limited storage capacity becomes challenging. Lack of storage space in crowded places prompts the need for building steel bar storage choice optimization. Therefore, this study aims to optimize the construction steel bar procurement plan by providing when and how much rebar to order and how to stack different sizes of rebar considering limited storage capacity.

Design/methodology/approach

A novel approach has been presented in this paper by integrating 4D building information modelling (BIM) and mixed-integer linear programming (MILP). This technique uses BIM to retrieve material quantities, including rebar, during the design phase. Following that, activities are scheduled depending on the duration determined by crew productivity data and material quantity. Then, based on the prior price, the price of each unit of rebar is projected for the duration of construction using the exponential smoothing method. After that, the MILP approach is used to generate an optimal steel bar procurement plan for limited storage space following the scheduled rebar-related operations.

Findings

The developed strategy minimizes overall procurement costs and ensures the storage of rebar as per standard guidelines. An optimal rebar procurement and storage plan to construct a six-storied RC frame has been presented in this paper as a demonstrative example to show the effectiveness of the proposed method.

Originality/value

This work partially satisfies a long-sought research need for establishing a comprehensive construction steel bar procurement system, making it a very useful source of information for practitioners and researchers. The proposed method can be used to minimize a key performance limitation that the conventional rebar procurement practice for crowded building sites may experience.

Details

Construction Innovation , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 2 January 2024

Xin Zou and Zhuang Rong

In repetitive projects, repetition offers more possibilities for activity scheduling at the sub-activity level. However, existing resource-constrained repetitive scheduling…

Abstract

Purpose

In repetitive projects, repetition offers more possibilities for activity scheduling at the sub-activity level. However, existing resource-constrained repetitive scheduling problem (RCRSP) models assume that there is only one sequence in performing the sub-activities of each activity, resulting in an inefficient resource allocation. This paper proposes a novel repetitive scheduling model for solving RCRSP with soft logic.

Design/methodology/approach

In this paper, a constraint programming model is developed to solve the RCRSP using soft logic, aiming at the possible relationship between parallel execution, orderly execution or partial parallel and partial orderly execution of different sub activities of the same activity in repetitive projects. The proposed model integrated crew assignment strategies and allowed continuous or fragmented execution.

Findings

When solving RCRSP, it is necessary to take soft logic into account. If managers only consider the fixed logic between sub-activities, they are likely to develop a delayed schedule. The practicality and effectiveness of the model were verified by a housing project based on eight different scenarios. The results showed that the constraint programming model outperformed its equivalent mathematical model in terms of solving speed and solution quality.

Originality/value

Available studies assume a fixed logic between sub-activities of the same activity in repetitive projects. However, there is no fixed construction sequence between sub-activities for some projects, e.g. hotel renovation projects. Therefore, this paper considers the soft logic relationship between sub-activities and investigates how to make the objective optimal without violating the resource availability constraint.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

1 – 10 of 555