Publication date: 26 June 2023

Petter Haglund and Mats Janné

The construction industry shows an increased interest in how to manage logistics within construction projects. Often construction logistics is outsourced to a logistics service…

1139

Abstract

Purpose

The construction industry shows an increased interest in how to manage logistics within construction projects. Often construction logistics is outsourced to a logistics service provider (LSP). However, construction logistics is normally approached either as a strategic decision or as an operational issue and rarely as a tactical concern. The purpose of this study is to explore how to organize the logistics outsourcing decision at strategic, tactical and operational levels.

Design/methodology/approach

This study is performed as a single-case study within a construction corporation, containing (amongst others) a building contractor (BC) and a construction equipment rental company (CERC) offering logistics services.

Findings

The study shows that to procure construction logistics service successfully, BCs need logistics capabilities at strategic and tactical levels to maintain an alignment between the use of logistics services and operational characteristics. Simultaneously, CERC’s need to design their service offerings to correspond to the needs of the BC.

Research limitations/implications

This study builds on a single-case study of a Swedish construction corporation. Further research is needed to better understand current logistics outsourcing and development practices and how these can be improved to foster better logistics management at the project level.

Practical implications

BCs find suggestions of different logistics organization structures and suitable outsourcing arrangements. CERCs and LSPs can use the findings to understand their customers’ needs and adapt service offerings.

Originality/value

To the best of the authors’ knowledge, this study is one of the first studies of how two companies within a corporation can work together to develop construction logistics service offerings.

Details

Construction Innovation , vol. 24 no. 7
Type: Research Article
ISSN: 1471-4175

Keywords

Open Access
Article
Publication date: 29 December 2022

Petter Haglund and Martin Rudberg

Contingency studies within logistics and supply chain management have shown a need for longitudinal studies on fit. The purpose of this paper is to investigate the logistics…

2964

Abstract

Purpose

Contingency studies within logistics and supply chain management have shown a need for longitudinal studies on fit. The purpose of this paper is to investigate the logistics strategy from a process of establishing fit perspective.

Design/methodology/approach

A large Swedish building contractor's logistics strategy process was analysed using a longitudinal single-case study for a period of 11 years (2008–2019).

Findings

The case study reveals three main constraints to logistics strategy implementation: a dominant purchasing organisation, a lack of incentives and diverging top-management priorities. This suggests that logistics strategy fit is not a conscious choice determined by contextual factors.

Research limitations/implications

Establishing fit is a continuous cycle of regaining fit between the logistics context and logistics strategy components. Fit can be achieved by a change to the logistics context or to logistics strategy components.

Practical implications

Logistics managers may need to opt for satisfactory fit in view of the costs incurred by changing strategy versus the benefits to be gained from a higher degree of fit.

Originality/value

This paper adopts a longitudinal case design to study the fit between the logistics context and strategy, adding to the body of knowledge on organisational design and strategy in logistics and supply chain management.

Details

The International Journal of Logistics Management, vol. 34 no. 7
Type: Research Article
ISSN: 0957-4093