Abstract

Subject area

Operations Research and Operation Management.

Study level/applicability

Undergraduate/MBA/Postgraduate.

Learning outcomes

The case depicts an opportunity for students to be exposed to optimization techniques using linear programming (LP). This case intends to: generate the LP model (identification of objective function and constraints); apply MS-Excel solver to arrive at an optimal solution; analyse manufacturing scenarios; and plan decision dependencies.

Case overview/synopsis

VBK Fibreo Tech Industries was a manufacturer of fibre reinforced plastic (FRP) products for industrial and domestic applications. Despite being a new entrant, it managed to exhibit great performance and attract a loyal base of customers. This case brings to light the problem that the company was facing that is demand exceeding capacity. The protagonist of the case Madhav, the Production Manager, was tasked to solve the problem of “product mix”. He was in a dilemma on how to fulfill customer orders while minimizing losses for his company. He knew that while losses were inevitable in the current scenario, they could be minimized with appropriate planning. Students are expected to use data and facts from the case and exhibit to formulate LP, by identifying the objective function and the constraints. They are also encouraged to use MS-Excel solver to find the optimal product mix and understand the decision dependencies.

Complexity academic level

This case can be used to teach LP in an undergraduate/postgraduate-level course on operations research. Students are exposed to the creation of a mathematical model for optimization and along with devising the implementation plan.

Supplementary materials

Teaching notes are available for educators only.

Subject code

CSS 9: Operations and logistics.

Details

Emerald Emerging Markets Case Studies, vol. 10 no. 3
Type: Case Study
ISSN: 2045-0621

Keywords

Case study
Publication date: 1 May 2013

Michael Phillips, David Watson, Bill Barnes and Howard Feldman

This case features a county planning director as he approves or turns down a permit application for the Harvest Wind Farm Project, located in Klickitat County on the Columbia…

Abstract

Case description

This case features a county planning director as he approves or turns down a permit application for the Harvest Wind Farm Project, located in Klickitat County on the Columbia Plateau in Washington State. The utilities involved and Klickitat County stood to benefit through new revenue generation and a favorable federal construction grant associated with the American Recovery and Reinvestment Act of 2009, and certain landowners stood to make substantial royalties. However, other landowners were also worried about declining property values, environmental groups had raised objections to the effect of turbines on the pristine Columbia River view, and uncertainty about health effects had recently become more of an issue. Nationally, “wind turbine syndrome” and “shadow-flicker” effects had been linked to wind farm operations. Given these concerns and the uncertainty, would the gains to stakeholders justify signing off on the project?

Details

The CASE Journal, vol. 9 no. 2
Type: Case Study
ISSN: 1544-9106

Keywords

Case study
Publication date: 19 March 2016

Biju Varkkey and Chetan Soman

Cummins Generator Technologies India Limited (CGTIL) was in the process of setting up a world-class factory at Ranjangaon based on “lean” production principles. The project team…

Abstract

Cummins Generator Technologies India Limited (CGTIL) was in the process of setting up a world-class factory at Ranjangaon based on “lean” production principles. The project team, however, went a step ahead and married “green” with “lean”. While lean is about taking the system inefficiencies out, the green is about harmony with nature. The case is about CGTIL's journey of deriving synergies between seemingly conflicting objectives of lean and green.

Details

Indian Institute of Management Ahmedabad, vol. no.
Type: Case Study
ISSN: 2633-3260
Published by: Indian Institute of Management Ahmedabad

Keywords

Case study
Publication date: 17 December 2019

Stuart Rosenberg

The following theoretical concepts are applicable to the case and its learning objectives: Stakeholder Power-Interest Matrix and Carroll’s Pyramid of Corporate Social…

Abstract

Theoretical basis

The following theoretical concepts are applicable to the case and its learning objectives: Stakeholder Power-Interest Matrix and Carroll’s Pyramid of Corporate Social Responsibility.

Research methodology

Information was obtained in three separate interviews with PSEG. In February 2018, an introductory phone conference was conducted with a number of senior managers within PSEG, including the Director of Development and Strategic Issues, Kate Gerlach. In April 2018, an onsite interview was conducted with Gerlach, who connected the author with Scott Jennings. A phone interview was conducted with Scott Jennings in May 2018 and follow-up communication with him was handled via e-mail. The information obtained from these interviews was supplemented by material obtained from secondary sources. None of the information in the case has been disguised.

Case overview/synopsis

Scott Jennings, a Vice President at PSEG, the diversified New Jersey-based energy company, was the project leader for a large commercial wind farm that was to be built off the coast. The project, Garden State Offshore Energy, a joint venture between PSEG and Deepwater Wind, an experienced developer of offshore wind projects, had been announced over six years earlier, in late 2008. In the time that had passed, the Garden State Offshore Energy project team had waited for the New Jersey Bureau of Public Utilities, which had been tasked by Governor Chris Christie to evaluate the project costs before it could authorize the actual construction of the wind turbines. Justifying the project on a cost basis proved to be difficult; despite the growing public sentiment in favor of projects that utilized renewable energy sources such as wind power, the Garden State Offshore Energy team was unable to move the project forward. Scott needed to decide whether it made sense to continue to hold regular meetings with the Garden State Offshore Energy team. Scott’s colleagues suggested that Scott speak with senior management at PSEG to find out if the resources that had been dedicated to the Garden State Offshore Energy project could be shifted to other projects that might be more feasible.

Complexity academic level

This case is suitable for courses in Sustainability. It is appropriate to use the case in undergraduate courses to illustrate decision making in a regulated industry. Sufficient information is presented in the case to debate both sides of the offshore wind authorization issue.

Details

The CASE Journal, vol. 16 no. 1
Type: Case Study
ISSN: 1544-9106

Keywords

Case study
Publication date: 26 February 2024

Arpita Amarnani, Umesh Mahtani and Vithal Sukhathankar

The learning outcomes of this study are to identify and discuss ways in which energy consumption in a residential educational institute can be reduced by improving demand-side…

Abstract

Learning outcomes

The learning outcomes of this study are to identify and discuss ways in which energy consumption in a residential educational institute can be reduced by improving demand-side energy management for sustainable development; summarise the challenges that an institute faces in transitioning to a more environmentally friendly mode of operations concerning energy management; illustrate the difference between operating expense and capital expenditure methods used for solar rooftop projects from the perspective of Goa Institute of Management (GIM); and analyse different project proposals for solar rooftop power generation energy using capital budgeting techniques.

Case overview/synopsis

Dr Ajit Parulekar, director at GIM, was evaluating the steps taken over the past few years for sustainable energy management to understand their impact and consider ways in which to take the environmental sustainability agenda forward. One of the projects that he was considering was the rooftop solar power plant. GIM had received proposals from several different vendors and evaluated three proposals out of these. He needed to decide on the capacity of the rooftop solar power generation and the type of contract that he should get into for the implementation of the project. This case study describes the differences and highlights the advantages and disadvantages of all the mentioned models with respect to GIM.

Complexity academic level

This case study is suitable for post-graduate level management students, as well as for undergraduate-level finance and management students.

Supplementary material

Teaching notes are available for educators only.

Subject code

CSS4: Environmental management.

Details

Emerald Emerging Markets Case Studies, vol. 14 no. 1
Type: Case Study
ISSN: 2045-0621

Keywords

Abstract

Subject area

Venture capital and private equity.

Study level/applicability

This case is suitable for II MBA/Executive MBA (venture capital and private equity/entrepreneurship/business models/managing family business) courses.

Case overview

Soliton is a technology and software services company with operations in India and the USA providing machine vision products and virtual instrumentation services. Soliton was started by Ganesh Devaraj in 1998 after his return from the United States after higher studies. Ganesh hails from a business family in Coimbatore that had interests in the textile spinning sector. The family had been in the textile business since the early 1940s and had revenues of Rs 400 million and employed about 700 people. Ganesh, not wanting to continue in the traditional family business, ventured into the technology sector using his academic and professional experience. His family was supportive of his venture and funded his company for the first two years of operation and for scaling up operations. Ganesh is now evaluating various sources of raising additional capital at a time when there was general slowdown in the automobile sector as a result of the global financial crisis.

Expected learning outcomes

The goal of this case study is to illustrate the complexities that exist in financing growth of companies in uncertain times. This following are the expected learning outcomes: discuss and understand the nuances between different sources of early stage funding: personal wealth, family, and angels; compare and contrast the differences between family funding and venture funding; and highlight the benefits and limitations of family funding.

Supplementary materials

Teaching notes are available.

Details

Emerald Emerging Markets Case Studies, vol. 2 no. 6
Type: Case Study
ISSN: 2045-0621

Keywords