1 – 10 of 11Bright Awuku, Eric Asa, Edmund Baffoe-Twum and Adikie Essegbey
Challenges associated with ensuring the accuracy and reliability of cost estimation of highway construction bid items are of significant interest to state highway transportation…
Abstract
Purpose
Challenges associated with ensuring the accuracy and reliability of cost estimation of highway construction bid items are of significant interest to state highway transportation agencies. Even with the existing research undertaken on the subject, the problem of inaccurate estimation of highway bid items still exists. This paper aims to assess the accuracy of the cost estimation methods employed in the selected studies to provide insights into how well they perform empirically. Additionally, this research seeks to identify, synthesize and assess the impact of the factors affecting highway unit prices because they affect the total cost of highway construction costs.
Design/methodology/approach
This paper systematically searched, selected and reviewed 105 papers from Scopus, Google Scholar, American Society of Civil Engineers (ASCE), Transportation Research Board (TRB) and Science Direct (SD) on conceptual cost estimation of highway bid items. This study used content and nonparametric statistical analyses to determine research trends, identify, categorize the factors influencing highway unit prices and assess the combined performance of conceptual cost prediction models.
Findings
Findings from the trend analysis showed that between 1983 and 2019 North America, Asia, Europe and the Middle East contributed the most to improving highway cost estimation research. Aggregating the quantitative results and weighting the findings using each study's sample size revealed that the average error between the actual and the estimated project costs of Monte-Carlo simulation models (5.49%) performed better compared to the Bayesian model (5.95%), support vector machines (6.03%), case-based reasoning (11.69%), artificial neural networks (12.62%) and regression models (13.96%). This paper identified 41 factors and was grouped into three categories, namely: (1) factors relating to project characteristics; (2) organizational factors and (3) estimate factors based on the common classification used in the selected papers. The mean ranking analysis showed that most of the selected papers used project-specific factors more when estimating highway construction bid items than the other factors.
Originality/value
This paper contributes to the body of knowledge by analyzing and comparing the performance of highway cost estimation models, identifying and categorizing a comprehensive list of cost drivers to stimulate future studies in improving highway construction cost estimates.
Details
Keywords
Indranil Ghosh, Rabin K. Jana and Dinesh K. Sharma
Owing to highly volatile and chaotic external events, predicting future movements of cryptocurrencies is a challenging task. This paper advances a granular hybrid predictive…
Abstract
Purpose
Owing to highly volatile and chaotic external events, predicting future movements of cryptocurrencies is a challenging task. This paper advances a granular hybrid predictive modeling framework for predicting the future figures of Bitcoin (BTC), Litecoin (LTC), Ethereum (ETH), Stellar (XLM) and Tether (USDT) during normal and pandemic regimes.
Design/methodology/approach
Initially, the major temporal characteristics of the price series are examined. In the second stage, ensemble empirical mode decomposition (EEMD) and maximal overlap discrete wavelet transformation (MODWT) are used to decompose the original time series into two distinct sets of granular subseries. In the third stage, long- and short-term memory network (LSTM) and extreme gradient boosting (XGB) are applied to the decomposed subseries to estimate the initial forecasts. Lastly, sequential quadratic programming (SQP) is used to fetch the forecast by combining the initial forecasts.
Findings
Rigorous performance assessment and the outcome of the Diebold-Mariano’s pairwise statistical test demonstrate the efficacy of the suggested predictive framework. The framework yields commendable predictive performance during the COVID-19 pandemic timeline explicitly as well. Future trends of BTC and ETH are found to be relatively easier to predict, while USDT is relatively difficult to predict.
Originality/value
The robustness of the proposed framework can be leveraged for practical trading and managing investment in crypto market. Empirical properties of the temporal dynamics of chosen cryptocurrencies provide deeper insights.
Details
Keywords
Hussein Y.H. Alnajjar and Osman Üçüncü
Artificial intelligence (AI) models are demonstrating day by day that they can find long-term solutions to improve wastewater treatment efficiency. Artificial neural networks…
Abstract
Purpose
Artificial intelligence (AI) models are demonstrating day by day that they can find long-term solutions to improve wastewater treatment efficiency. Artificial neural networks (ANNs) are one of the most important of these models, and they are increasingly being used to forecast water resource variables. The goal of this study was to create an ANN model to estimate the removal efficiency of biological oxygen demand (BOD), total nitrogen (TN), total phosphorus (TP) and total suspended solids (TSS) at the effluent of various primary and secondary treatment methods in a wastewater treatment plant (WWTP).
Design/methodology/approach
The MATLAB App Designer model was used to generate the data set. Various combinations of wastewater quality data, such as temperature(T), TN, TP and hydraulic retention time (HRT) are used as inputs into the ANN to assess the degree of effect of each of these variables on BOD, TN, TP and TSS removal efficiency. Two of the models reflect two different types of primary treatment, while the other nine models represent different types of subsequent treatment. The ANN model’s findings are compared to the MATLAB App Designer model. For evaluating model performance, mean square error (MSE) and coefficient of determination statistics (R2) are utilized as comparative metrics.
Findings
For both training and testing, the R values for the ANN models were greater than 0.99. Based on the comparisons, it was discovered that the ANN model can be used to estimate the removal efficiency of BOD, TN, TP and TSS in WWTP and that the ANN model produces very similar and satisfying results to the APPDESIGNER model. The R-value (Correlation coefficient) of 0.9909 and the MSE of 5.962 indicate that the model is accurate. Because of the many benefits of the ANN models used in this study, it has a lot of potential as a general modeling tool for a range of other complicated process systems that are difficult to solve using conventional modeling techniques.
Originality/value
The objective of this study was to develop an ANN model that could be used to estimate the removal efficiency of pollutants such as BOD, TN, TP and TSS at the effluent of various primary and secondary treatment methods in a WWTP. In the future, the ANN could be used to design a new WWTP and forecast the removal efficiency of pollutants.
Details
Keywords
Amin Mojoodi, Saeed Jalalian and Tafazal Kumail
This research aims to determine the ideal fare for various aircraft itineraries by modeling prices using a neural network method. Dynamic pricing has been studied from the…
Abstract
Purpose
This research aims to determine the ideal fare for various aircraft itineraries by modeling prices using a neural network method. Dynamic pricing has been studied from the airline’s point of view, with a focus on demand forecasting and price differentiation. Early demand forecasting on a specific route can assist an airline in strategically planning flights and determining optimal pricing strategies.
Design/methodology/approach
A feedforward neural network was employed in the current study. Two hidden layers, consisting of 18 and 12 neurons, were incorporated to enhance the network’s capabilities. The activation function employed for these layers was tanh. Additionally, it was considered that the output layer’s functions were linear. The neural network inputs considered in this study were flight path, month of flight, flight date (week/day), flight time, aircraft type (Boeing, Airbus, other), and flight class (economy, business). The neural network output, on the other hand, was the ticket price. The dataset comprises 16,585 records, specifically flight data for Iranian airlines for 2022.
Findings
The findings indicate that the model achieved a high level of accuracy in approximating the actual data. Additionally, it demonstrated the ability to predict the optimal ticket price for various flight routes with minimal error.
Practical implications
Based on the significant alignment observed between the actual data and the tested data utilizing the algorithmic model, airlines can proactively anticipate ticket prices across all routes, optimizing the revenue generated by each flight. The neural network algorithm utilized in this study offers a valuable opportunity for companies to enhance their decision-making processes. By leveraging the algorithm’s features, companies can analyze past data effectively and predict future prices. This enables them to make informed and timely decisions based on reliable information.
Originality/value
The present study represents a pioneering research endeavor that investigates using a neural network algorithm to predict the most suitable pricing for various flight routes. This study aims to provide valuable insights into dynamic pricing for marketing researchers and practitioners.
Details
Keywords
Aleena Swetapadma, Tishya Manna and Maryam Samami
A novel method has been proposed to reduce the false alarm rate of arrhythmia patients regarding life-threatening conditions in the intensive care unit. In this purpose, the…
Abstract
Purpose
A novel method has been proposed to reduce the false alarm rate of arrhythmia patients regarding life-threatening conditions in the intensive care unit. In this purpose, the atrial blood pressure, photoplethysmogram (PLETH), electrocardiogram (ECG) and respiratory (RESP) signals are considered as input signals.
Design/methodology/approach
Three machine learning approaches feed-forward artificial neural network (ANN), ensemble learning method and k-nearest neighbors searching methods are used to detect the false alarm. The proposed method has been implemented using Arduino and MATLAB/SIMULINK for real-time ICU-arrhythmia patients' monitoring data.
Findings
The proposed method detects the false alarm with an accuracy of 99.4 per cent during asystole, 100 per cent during ventricular flutter, 98.5 per cent during ventricular tachycardia, 99.6 per cent during bradycardia and 100 per cent during tachycardia. The proposed framework is adaptive in many scenarios, easy to implement, computationally friendly and highly accurate and robust with overfitting issue.
Originality/value
As ECG signals consisting with PQRST wave, any deviation from the normal pattern may signify some alarming conditions. These deviations can be utilized as input to classifiers for the detection of false alarms; hence, there is no need for other feature extraction techniques. Feed-forward ANN with the Lavenberg–Marquardt algorithm has shown higher rate of convergence than other neural network algorithms which helps provide better accuracy with no overfitting.
Details
Keywords
Farshad Peiman, Mohammad Khalilzadeh, Nasser Shahsavari-Pour and Mehdi Ravanshadnia
Earned value management (EVM)–based models for estimating project actual duration (AD) and cost at completion using various methods are continuously developed to improve the…
Abstract
Purpose
Earned value management (EVM)–based models for estimating project actual duration (AD) and cost at completion using various methods are continuously developed to improve the accuracy and actualization of predicted values. This study primarily aimed to examine natural gradient boosting (NGBoost-2020) with the classification and regression trees (CART) base model (base learner). To the best of the authors' knowledge, this concept has never been applied to EVM AD forecasting problem. Consequently, the authors compared this method to the single K-nearest neighbor (KNN) method, the ensemble method of extreme gradient boosting (XGBoost-2016) with the CART base model and the optimal equation of EVM, the earned schedule (ES) equation with the performance factor equal to 1 (ES1). The paper also sought to determine the extent to which the World Bank's two legal factors affect countries and how the two legal causes of delay (related to institutional flaws) influence AD prediction models.
Design/methodology/approach
In this paper, data from 30 construction projects of various building types in Iran, Pakistan, India, Turkey, Malaysia and Nigeria (due to the high number of delayed projects and the detrimental effects of these delays in these countries) were used to develop three models. The target variable of the models was a dimensionless output, the ratio of estimated duration to completion (ETC(t)) to planned duration (PD). Furthermore, 426 tracking periods were used to build the three models, with 353 samples and 23 projects in the training set, 73 patterns (17% of the total) and six projects (21% of the total) in the testing set. Furthermore, 17 dimensionless input variables were used, including ten variables based on the main variables and performance indices of EVM and several other variables detailed in the study. The three models were subsequently created using Python and several GitHub-hosted codes.
Findings
For the testing set of the optimal model (NGBoost), the better percentage mean (better%) of the prediction error (based on projects with a lower error percentage) of the NGBoost compared to two KNN and ES1 single models, as well as the total mean absolute percentage error (MAPE) and mean lags (MeLa) (indicating model stability) were 100, 83.33, 5.62 and 3.17%, respectively. Notably, the total MAPE and MeLa for the NGBoost model testing set, which had ten EVM-based input variables, were 6.74 and 5.20%, respectively. The ensemble artificial intelligence (AI) models exhibited a much lower MAPE than ES1. Additionally, ES1 was less stable in prediction than NGBoost. The possibility of excessive and unusual MAPE and MeLa values occurred only in the two single models. However, on some data sets, ES1 outperformed AI models. NGBoost also outperformed other models, especially single models for most developing countries, and was more accurate than previously presented optimized models. In addition, sensitivity analysis was conducted on the NGBoost predicted outputs of 30 projects using the SHapley Additive exPlanations (SHAP) method. All variables demonstrated an effect on ETC(t)/PD. The results revealed that the most influential input variables in order of importance were actual time (AT) to PD, regulatory quality (RQ), earned duration (ED) to PD, schedule cost index (SCI), planned complete percentage, rule of law (RL), actual complete percentage (ACP) and ETC(t) of the ES optimal equation to PD. The probabilistic hybrid model was selected based on the outputs predicted by the NGBoost and XGBoost models and the MAPE values from three AI models. The 95% prediction interval of the NGBoost–XGBoost model revealed that 96.10 and 98.60% of the actual output values of the testing and training sets are within this interval, respectively.
Research limitations/implications
Due to the use of projects performed in different countries, it was not possible to distribute the questionnaire to the managers and stakeholders of 30 projects in six developing countries. Due to the low number of EVM-based projects in various references, it was unfeasible to utilize other types of projects. Future prospects include evaluating the accuracy and stability of NGBoost for timely and non-fluctuating projects (mostly in developed countries), considering a greater number of legal/institutional variables as input, using legal/institutional/internal/inflation inputs for complex projects with extremely high uncertainty (such as bridge and road construction) and integrating these inputs and NGBoost with new technologies (such as blockchain, radio frequency identification (RFID) systems, building information modeling (BIM) and Internet of things (IoT)).
Practical implications
The legal/intuitive recommendations made to governments are strict control of prices, adequate supervision, removal of additional rules, removal of unfair regulations, clarification of the future trend of a law change, strict monitoring of property rights, simplification of the processes for obtaining permits and elimination of unnecessary changes particularly in developing countries and at the onset of irregular projects with limited information and numerous uncertainties. Furthermore, the managers and stakeholders of this group of projects were informed of the significance of seven construction variables (institutional/legal external risks, internal factors and inflation) at an early stage, using time series (dynamic) models to predict AD, accurate calculation of progress percentage variables, the effectiveness of building type in non-residential projects, regular updating inflation during implementation, effectiveness of employer type in the early stage of public projects in addition to the late stage of private projects, and allocating reserve duration (buffer) in order to respond to institutional/legal risks.
Originality/value
Ensemble methods were optimized in 70% of references. To the authors' knowledge, NGBoost from the set of ensemble methods was not used to estimate construction project duration and delays. NGBoost is an effective method for considering uncertainties in irregular projects and is often implemented in developing countries. Furthermore, AD estimation models do fail to incorporate RQ and RL from the World Bank's worldwide governance indicators (WGI) as risk-based inputs. In addition, the various WGI, EVM and inflation variables are not combined with substantial degrees of delay institutional risks as inputs. Consequently, due to the existence of critical and complex risks in different countries, it is vital to consider legal and institutional factors. This is especially recommended if an in-depth, accurate and reality-based method like SHAP is used for analysis.
Details
Keywords
Ismail Abiodun Sulaimon, Hafiz Alaka, Razak Olu-Ajayi, Mubashir Ahmad, Saheed Ajayi and Abdul Hye
Road traffic emissions are generally believed to contribute immensely to air pollution, but the effect of road traffic data sets on air quality (AQ) predictions has not been fully…
Abstract
Purpose
Road traffic emissions are generally believed to contribute immensely to air pollution, but the effect of road traffic data sets on air quality (AQ) predictions has not been fully investigated. This paper aims to investigate the effects traffic data set have on the performance of machine learning (ML) predictive models in AQ prediction.
Design/methodology/approach
To achieve this, the authors have set up an experiment with the control data set having only the AQ data set and meteorological (Met) data set, while the experimental data set is made up of the AQ data set, Met data set and traffic data set. Several ML models (such as extra trees regressor, eXtreme gradient boosting regressor, random forest regressor, K-neighbors regressor and two others) were trained, tested and compared on these individual combinations of data sets to predict the volume of PM2.5, PM10, NO2 and O3 in the atmosphere at various times of the day.
Findings
The result obtained showed that various ML algorithms react differently to the traffic data set despite generally contributing to the performance improvement of all the ML algorithms considered in this study by at least 20% and an error reduction of at least 18.97%.
Research limitations/implications
This research is limited in terms of the study area, and the result cannot be generalized outside of the UK as some of the inherent conditions may not be similar elsewhere. Additionally, only the ML algorithms commonly used in literature are considered in this research, therefore, leaving out a few other ML algorithms.
Practical implications
This study reinforces the belief that the traffic data set has a significant effect on improving the performance of air pollution ML prediction models. Hence, there is an indication that ML algorithms behave differently when trained with a form of traffic data set in the development of an AQ prediction model. This implies that developers and researchers in AQ prediction need to identify the ML algorithms that behave in their best interest before implementation.
Originality/value
The result of this study will enable researchers to focus more on algorithms of benefit when using traffic data sets in AQ prediction.
Details
Keywords
Li Chen, Dirk Ifenthaler, Jane Yin-Kim Yau and Wenting Sun
The study aims to identify the status quo of artificial intelligence in entrepreneurship education with a view to identifying potential research gaps, especially in the adoption…
Abstract
Purpose
The study aims to identify the status quo of artificial intelligence in entrepreneurship education with a view to identifying potential research gaps, especially in the adoption of certain intelligent technologies and pedagogical designs applied in this domain.
Design/methodology/approach
A scoping review was conducted using six inclusive and exclusive criteria agreed upon by the author team. The collected studies, which focused on the adoption of AI in entrepreneurship education, were analysed by the team with regards to various aspects including the definition of intelligent technology, research question, educational purpose, research method, sample size, research quality and publication. The results of this analysis were presented in tables and figures.
Findings
Educators introduced big data and algorithms of machine learning in entrepreneurship education. Big data analytics use multimodal data to improve the effectiveness of entrepreneurship education and spot entrepreneurial opportunities. Entrepreneurial analytics analysis entrepreneurial projects with low costs and high effectiveness. Machine learning releases educators’ burdens and improves the accuracy of the assessment. However, AI in entrepreneurship education needs more sophisticated pedagogical designs in diagnosis, prediction, intervention, prevention and recommendation, combined with specific entrepreneurial learning content and entrepreneurial procedure, obeying entrepreneurial pedagogy.
Originality/value
This study holds significant implications as it can shift the focus of entrepreneurs and educators towards the educational potential of artificial intelligence, prompting them to consider the ways in which it can be used effectively. By providing valuable insights, the study can stimulate further research and exploration, potentially opening up new avenues for the application of artificial intelligence in entrepreneurship education.
Details
Keywords
This research study aims to delve into the enduring relationship between housing property prices and economic policy uncertainty across eight major Indian cities.
Abstract
Purpose
This research study aims to delve into the enduring relationship between housing property prices and economic policy uncertainty across eight major Indian cities.
Design/methodology/approach
Using the panel non-linear autoregressive distributed lag model, this study meticulously investigates the asymmetric impact of economic policy uncertainty on apartment and house (unit) prices in India during the period from 2000 to 2022.
Findings
The findings of this study indicate that economic policy uncertainty exerts a negative influence on property prices, but noteworthy asymmetry is observed, with positive changes in effect having a more pronounced impact than negative changes. This asymmetrical effect is particularly prominent in the case of unit prices.
Originality/value
This research reveals that long-run price trends are also influenced by factors such as interest rates, building costs and housing loans. Through a comprehensive analysis of these factors and their interplay with property prices, this research paper contributes valuable insights to the understanding of the real estate market dynamics in Indian cities.
Details
Keywords
Nirodha Fernando, Kasun Dilshan T.A. and Hexin (Johnson) Zhang
The Government’s investment in infrastructure projects is considerably high, especially in bridge construction projects. Government authorities must establish an initial…
Abstract
Purpose
The Government’s investment in infrastructure projects is considerably high, especially in bridge construction projects. Government authorities must establish an initial forecasted budget to have transparency in transactions. Early cost estimating is challenging for Quantity Surveyors due to incomplete project details at the initial stage and the unavailability of standard cost estimating techniques for bridge projects. To mitigate the difficulties in the traditional preliminary cost estimating methods, there is a requirement to develop a new initial cost estimating model which is accurate, user friendly and straightforward. The research was carried out in Sri Lanka, and this paper aims to develop the artificial neural network (ANN) model for an early cost estimate of concrete bridge systems.
Design/methodology/approach
The construction cost data of 30 concrete bridge projects which are in Sri Lanka constructed within the past ten years were trained and tested to develop an ANN cost model. Backpropagation technique was used to identify the number of hidden layers, iteration and momentum for optimum neural network architectures.
Findings
An ANN cost model was developed, furnishing the best result since it succeeded with around 90% validation accuracy. It created a cost estimation model for the public sector as an accurate, heuristic, flexible and efficient technique.
Originality/value
The research contributes to the current body of knowledge by providing the most accurate early-stage cost estimate for the concrete bridge systems in Sri Lanka. In addition, the research findings would be helpful for stakeholders and policymakers to propose policy recommendations that positively influence the prediction of the most accurate cost estimate for concrete bridge construction projects in Sri Lanka and other developing countries.