1 – 10 of 20The delay in real estate projects in India is pervasive. Organization and management (O&M) and project management (PM)-related challenges are argued to contribute to project…
Abstract
Purpose
The delay in real estate projects in India is pervasive. Organization and management (O&M) and project management (PM)-related challenges are argued to contribute to project delays. This study examined the O&M and PM factors that cause delays, the level of implementation of various O&M and PM aspects in real estate projects and how the challenges can be alleviated.
Design/methodology/approach
Perception surveys among the consumers and relevant stakeholders engaged in real estate projects in the Bhubaneswar and Cuttack regions of India were conducted to collect data on the factors of delay and implementation of the O&M and PM aspects. Relevant statistical methods and structural equation modeling (SEM) were used for data analysis.
Findings
Findings suggest that from the O&M point of view, poor decision-making, mishandling of finance, concurrent execution of many projects, diversion and misuse of finance for unrelated activities, lack of PM personnel and poor management contribute to the delay. Further, although the project initiation is satisfactorily done, most of the PM principles are not largely used, thus leading to delay.
Research limitations/implications
The study does have limitations, including its reliance on a perception survey of consumers and stakeholders, a limited sample size and a restricted number of projects. Nevertheless, the study highlights the need to address poor O&M and the insufficient application of PM principles to combat project delays in the Indian real estate sector.
Practical implications
Proper O&M and adequate application of PM will enable professional management of the projects and avoid delay.
Social implications
Proper O&M and the application of adequate PM would reduce delays in real estate projects. Consequently, conflicts between the companies and consumers might be reduced and housing and infrastructure demands might be met.
Originality/value
The study manifested that the lack of adequate implementation of O&M and PM aspects leads to delays. So, it is theorized that O&M and PM play critical roles in the success of real estate projects. Appropriate implementation of the principles and best practices linked to these aspects might alleviate the challenges of delay in real estate projects in India.
Details
Keywords
Najimu Saka, Abdullahi Babatunde Saka, Opeoluwa Akinradewo and Clinton O. Aigbavboa
The complex interaction of politics and the economy is a critical factor for the sustainable growth and development of the construction sector (CNS). This study aims to…
Abstract
Purpose
The complex interaction of politics and the economy is a critical factor for the sustainable growth and development of the construction sector (CNS). This study aims to investigate the effects of type of political administration including democracy and military on the performance of CNS using the Nigerian Construction Sector (NCS) as a case study.
Design/methodology/approach
A 48 year (1970–2017) time series data (TSD) on the NCS and the gross domestic product (GDP) based on 2010 constant USD were extracted from the United Nations Statistical Department database. Analysis of variance (ANOVA) and analysis of covariance (ANCOVA) models were used to analyze the TSD. The ANCOVA model includes the GDP as correlational variable or covariate.
Findings
The estimates of the ANOVA model indicate that democratic administration is significantly better than military administration in construction performance. However, the ANCOVA model indicates that the GDP is more important than political administration in the performance of the CNS. The study recommends for a new national construction policy, favourable fiscal and monetary policy, local content development policy and construction credit guaranty scheme for the rapid growth and development of the NCS.
Originality/value
Hitherto, little is known about the influence of political administration on the performance of the CNS. This study provides empirical evidence from a developing economy perspective. It presents the relationships and highlights recommendations for driving growth in the construction industry.
Details
Keywords
Lekan Damilola Ojo, Deji Rufus Ogunsemi, Ahmed Elyamany and Ayodeji Emmanuel Oke
The adoption of value management (VM) has been on the rise in the construction industry, especially in the past decade. Identifying the main barriers to VM application for…
Abstract
Purpose
The adoption of value management (VM) has been on the rise in the construction industry, especially in the past decade. Identifying the main barriers to VM application for ameliorating poor project outcomes in the construction industry is a critical step to overcoming its implementation. Therefore, this study aims to examine the barriers to the adoption of VM in the Nigerian construction industry (NCI) and identify the critical ones for action by construction stakeholders.
Design/methodology/approach
This study used two rounds of Delphi surveys with 15 VM experts to identify the challenges to VM adoption. The Delphi team’s data from the two surveys were analysed using descriptive statistics. The mean-mode approach was used to identify ten major barriers to VM adoption based on the consensus reached during the second round of the Delphi poll. Following that, an interrater agreement analysis and a significant level analysis were performed.
Findings
Of the 17 identified barriers hindering VM adoption on construction projects in the NCI, 10 were found to be profound after statistical analyses of the data. The significant barriers include communication gap between the client and other consultants; delay in design preparation because of VM services; the pretext that VM is being practiced in the construction industry; and the wrong perception of VM by construction professionals, among others. The findings of the analysis suggested that the lack of VM adoption in the NCI was because of inadequate knowledge of VM techniques among construction professionals. Therefore, it is advised that VM training be provided for concerned stakeholders to address the lack of VM expertise among Nigerian construction professionals.
Practical implications
This study investigated the barriers to VM adoption on construction projects in the NCI with the opinions of a few construction professionals who can be regarded as VM experts. As against obtaining large survey responses from construction professionals who may not be knowledgeable in the VM process, the limited VM experts’ responses provide a valid basis for drawing inferences and making recommendations to address the paucity of VM applications in the NCI.
Originality/value
Through a Delphi survey, the critical barriers to the adoption of VM were identified, along with recommendations to help construction stakeholders overcome the challenges and enjoy the benefits of VM.
Details
Keywords
Andrew Ebekozien and Clinton Ohis Aigbavboa
The dynamic nature of the built environment and trending smart construction project complexities demand proactive needs tailored towards architecture, engineering and construction…
Abstract
Purpose
The dynamic nature of the built environment and trending smart construction project complexities demand proactive needs tailored towards architecture, engineering and construction (AEC) education. It is a task for the built environment professionals (BEP) to prepare for the future, including the quantity surveying (QS) profession. Studies are scarce in preparing QS education from Nigeria’s stakeholders’ perspective regarding digital technology. Therefore, this paper aims to investigate how to improve QS education by continually updating curriculum digitalisation to meet the construction industry requirements.
Design/methodology/approach
Data were sourced from elite virtual interviews across Nigeria. A total of 40 key stakeholders knowledgeable in QS education, advocating a future template for the advancement of QS education in higher institutions, were engaged, and saturation was achieved.
Findings
Findings show that improving QS education through continually updating curriculum digitalisation to meet industry requirements cannot be over-emphasised in the 21st-century-built environment industry. The outcomes of the results led to the conclusion that the current QS education curriculum was not meeting the expectations of other BEP stakeholders. Thus, for competitiveness in the future, the QS education curriculum needs to infuse more related-digital technology modules/courses to assist in the sustainability and relevance of the profession within the BEP.
Research limitations/implications
This paper focussed on improving Nigeria’s QS education using digital technologies via a qualitative approach. Future study is needed via a quantitative approach for broader coverage and validation.
Practical implications
The research revealed the need for designing QS programmes to provide for industry demands with emphasis on digital technologies modules/courses. Nigeria’s QS education stakeholders have been stirred up to embrace the curriculum review and make the profession digitalised and relevant within the BEP. The built environment sector is trending towards digitalisation, and the QS programmes cannot afford to be behind.
Originality/value
This research identified the current gap regarding digitalisation of the curriculum. This study will stir QS educational providers and regulators to improve future programmes via digital technologies. It would encourage the use of digital technologies with the right enabling environment. The outcome would mitigate the gap and improve Nigeria’s QS education in the future.
Details
Keywords
Hasith Chathuranga Victar, B.A.K.S. Perera, Asha Dulanjalie Palihakkara and Kaveesha Gihani Dewagod
The construction industry is shifting towards becoming more circular by reducing waste, reusing building materials and embracing regenerative solutions for energy generation and…
Abstract
Purpose
The construction industry is shifting towards becoming more circular by reducing waste, reusing building materials and embracing regenerative solutions for energy generation and biodiversity conservation. Thus, construction professionals must perform diversified services to achieve a circular built environment (CBE). Implementing resource planning and waste management in CBE has already posed challenges to the quantity surveying profession; thus, quantity surveyors (QSs) should be equipped with new roles and competencies to tackle challenges in achieving a CBE. Hence, this study aimed to investigate the functions and competencies of QSs at the design and building material sourcing stages in achieving a CBE according to 3R principles.
Design/methodology/approach
The research apprehended a qualitative approach, including two expert interview rounds adhering to the Delphi technique with 14 and 11 experts per each round. Manual content analysis was incorporated to analyse the collected data.
Findings
The research findings revealed the important roles and competencies of QSs in achieving a CBE. In addition, essential functions and competencies were categorised according to the 3R principles (reduce, reuse, recycle) to successfully implement CBE during the Design and Building Material Sourcing stages. According to the 3R principles of CBE, cost control, cost planning, feasibility studies, measurement and quantification, risk management, value engineering and innovations and technologies were well-received by most interviewees as essential roles of QSs during the Design and Building Material Sourcing stages. Further, basic/mandatory competencies (personal, interpersonal, professional practice and business skills), economic analysis, BIM management, cost management and risk management are highly regarded by experts for QS as important competencies to achieve CBE.
Originality/value
With new construction trends, QSs must enhance their conventional roles and competencies and search for new skills and competencies. Those skills and competencies could be linked to the CE concept, either directly or indirectly. Since QS holds a prominent place in sustainable construction in CBE, adapting to changes in the construction industry such as CBE is timely for QSs. Further, there is a shortage of literature regarding QSs' roles and competencies in achieving a CBE; thus, this study will contribute by identifying new avenues for QSs in achieving a CBE in the practice and the research.
Details
Keywords
Haruna Sa'idu Lawal, Hassan Adaviriku Ahmadu, Muhammad Abdullahi, Muhammad Aliyu Yamusa and Mustapha Abdulrazaq
This study aims to develop a building renovation duration prediction model incorporating both scope and non-scope factors.
Abstract
Purpose
This study aims to develop a building renovation duration prediction model incorporating both scope and non-scope factors.
Design/methodology/approach
The study used a questionnaire to obtain basic information relating to identified project scope factors as well as information relating to the impact of the non-scope factors on the duration of building renovation projects. The study retrieved 121 completed questionnaires from construction firms on tertiary education trust fund (TETFund) building renovation projects. Artificial neural network was then used to develop the model using 90% of the data, while mean absolute percentage error was used to validate the model using the remaining 10% of the data.
Findings
Two artificial neural network models were developed – a multilayer perceptron (MLP) and a radial basis function (RBF) model. The accuracy of the models was 86% and 80%, respectively. The developed models’ predictions were not statistically different from those of actual duration estimates with less than 20% error margin. Also, the study found that MLP models are more accurate than RBF models.
Research limitations/implications
The developed models are only applicable to projects that suit the characteristics and nature of the data used to develop the models. Hence, models can only predict the duration of building renovation projects.
Practical implications
The developed models are expected to serve as a tool for realistic estimation of the duration of building renovation projects and thus, help construction project managers to effectively plan and manage it.
Social implications
The developed models are expected to serve as a tool for realistic estimation of the duration of building renovation projects and thus, help construction project managers to effectively plan and manage it; it also helps clients to effectively benchmark projects duration and contractors to accurately estimate duration at tendering stage.
Originality/value
The study presents models that combine both scope and non-scope factors in predicting the duration of building renovation projects so as to ensure more realistic predictions.
Details
Keywords
Luqman Toriola-Coker, Hakeem Owolabi, Hafiz Alaka, Wasiu Adeniran Bello and Chaminda Pathirage
This study aims to investigate two public private partnership (PPP) road projects in Nigeria for exploring factors that can motivate end-user stakeholders for contributing towards…
Abstract
Purpose
This study aims to investigate two public private partnership (PPP) road projects in Nigeria for exploring factors that can motivate end-user stakeholders for contributing towards sustaining a PPP project in the long-term.
Design/methodology/approach
Using a case study methodology approach, this study adopts two-way data collection strategies via in-depth interviews with PPP experts and end-user stakeholders in Nigeria host communities and a questionnaire survey to relevant stakeholders.
Findings
The study identifies an eight-factor structure indicating critical success factors for ensuring end-user stakeholders support PPP projects on a long-term basis in their host communities.
Originality/value
Results of the study have huge implications for policymakers and project companies by encouraging the early integration of far-sighted measures that will promote long-term support and sustainability for PPP projects amongst the end-user stakeholders.
Details
Keywords
Sanjay Bhattacharya and Gautam Pant
The Fourth Industrial Revolution (4IR) holds the potential to significantly improve capabilities and performances for architectural, engineering, construction and operation and…
Abstract
Purpose
The Fourth Industrial Revolution (4IR) holds the potential to significantly improve capabilities and performances for architectural, engineering, construction and operation and maintenance (AECO) companies in India. The top management of such companies seems unsure and reluctant to implementation of the 4IR applications. The objective of this research is to identify the 4IR technology applications, which would have a significant impact on the operation of the AECO companies in India. Moreover, the paper further attempts to give a conceptual roadmap for the implementation of these 4IR technologies in the AECO value chain.
Design/methodology/approach
The nascent level of research in 4IR in construction necessitated the adoption of mixed methodologies in research. Hypothesis testing has been carried out on the quantitative data to ascertain the potential of 4IR technologies, which could significantly impact the AECO companies. Subsequently, qualitative research has been used to explore the reasons impacting the technology adoption and generate a possible road map for the implementation of the significant 4IR technology applications.
Findings
The AECO value chain is challenged due to its complexity, uncertainty, fragmented supply chains, myopic thinking and a culture reluctant to change. The study provides insights into the dilemmas of practitioners in the Indian context while exploring possible approaches to carry out the transformation in AECO.
Research limitations/implications
The study validation relied on the opinions, perspectives and recollections of respondents. The opinion of practicing professionals was limited to the Indian context.
Originality/value
The article may help leaders of AECO firms, industry associations, policymakers and academia to take steps in relevant directions to enable digital transformation.
Details
Keywords
Olufisayo Adewumi Adedokun, Temitope Egbelakin, Deborah Oluwafunke Adedokun and Johnson Adafin
Despite the huge capital outlay in tertiary education building projects (TEBP), these projects undoubtedly failed in meeting the set objectives of cost, time and quality, among…
Abstract
Purpose
Despite the huge capital outlay in tertiary education building projects (TEBP), these projects undoubtedly failed in meeting the set objectives of cost, time and quality, among others. Therefore, rather than the impacts of risks on the overall project performance, which is common in the construction management literature, the purpose of this study is to assess the impacts of risk factors on the criteria for measuring the success of public TEBP.
Design/methodology/approach
The paper adopted a quantitative research method where the data collection was via a questionnaire survey. The researcher administered 452 questionnaires to the client representatives, consultants and contractors involved in building projects across five public tertiary education institutions in Ondo State, Nigeria. Of 452 questionnaires, 279 were retrieved and suitable for the analysis, translating to a 61.73% response rate. The reliability analysis of the research instrument showed 0.965 and 0.807, via Cronbach’s alpha test, indicating high reliability of the instrument used for data collection.
Findings
The study found different risk factors affecting the criteria for measuring the success of TEBP. For instance, the environmental risk factor significantly impacted completion to cost, while financial and political risk factors significantly impacted completion to time. In addition, while environmental, legal and management risks significantly impacted end-user satisfaction, safety performance was significantly impacted by logistic, legal, design, construction, political and management risks. Besides, the logistic, legal, design, construction, financial, political and management risk factors impacted profit. However, despite profit being one of the criteria for measuring the success of building projects, it recorded the highest risk impacts amounting to 41% variance.
Research limitations/implications
The findings are limited to the public tertiary education building projects procured via competitive tendering; therefore, the results might differ when considering other procurement methods.
Practical implications
The practical implication is that rather than focusing on all risk factors, the project stakeholders could give adequate attention to the significant risk factors impacting each of the parameters for measuring the success of education building projects.
Originality/value
The study revealed specific risk factors impacting the criteria for measuring the success of TEBP, which extend beyond the use of the overall project performance approach.
Details
Keywords
Kai Hänninen, Jouni Juntunen and Harri Haapasalo
The purpose of this study is to describe latent classes explaining the innovation logic in the Finnish construction companies. Innovativeness is a driver of competitive…
Abstract
Purpose
The purpose of this study is to describe latent classes explaining the innovation logic in the Finnish construction companies. Innovativeness is a driver of competitive performance and vital to the long-term success of any organisation and company.
Design/methodology/approach
Using finite mixture structural equation modelling (FMSEM), the authors have classified innovation logic into latent classes. The method analyses and recognises classes for companies that have similar logic in innovation activities based on the collected data.
Findings
Through FMSEM analysis, the authors have identified three latent classes that explain the innovation logic in the Finnish construction companies – LC1: the internal innovators; LC2: the non-innovation-oriented introverts; and LC3: the innovation-oriented extroverts. These three latent classes clearly capture the perceptions within the industry as well as the different characteristics and variables.
Research limitations/implications
The presented latent classes explain innovation logic but is limited to analysing Finnish companies. Also, the research is quantitative by nature and does not increase the understanding in the same manner as qualitative research might capture on more specific aspects.
Practical implications
This paper presents starting points for construction industry companies to intensify innovation activities. It may also indicate more fundamental changes for the structure of construction industry organisations, especially by enabling innovation friendly culture.
Originality/value
This study describes innovation logic in Finnish construction companies through three models (LC1–LC3) by using quantitative data analysed with the FMSEM method. The fundamental innovation challenges in the Finnish construction companies are clarified via the identified latent classes.
Details