1 – 10 of over 1000Chinthaka Niroshan Atapattu, Niluka Domingo and Monty Sutrisna
The current estimation practice in construction projects greatly needs upgrading, as there has been no improvement in the cost overrun issue over the past 70 years. The purpose of…
Abstract
Purpose
The current estimation practice in construction projects greatly needs upgrading, as there has been no improvement in the cost overrun issue over the past 70 years. The purpose of this research was to develop a new multiple regression analysis (MRA)-based model to forecast the final cost of road projects at the pre-design stage using data from 43 projects in New Zealand (NZ).
Design/methodology/approach
The research used the case study of 43 completed road projects in NZ. Document analysis was conducted to collect data, and statistical tests were used for model development and analysis.
Findings
Eight models were developed, and all models achieved the required F statistics and met the regression assumptions. The models’ mean absolute percentage error (MAPE) was between 21.25% and 22.77%. The model with the lowest MAPE comprised the road length and width, number of bridges, pavement area, cut and fill area, preliminary cost and cost indices change.
Research limitations/implications
The model is based on road projects in NZ. However, it was designed to be able to adapt to other contexts. The findings suggest that the model can be used to improve traditional conceptual estimating methods. Past project data is often stored by the project team but rarely used for analysing and forecasting purposes. This research emphasises that past data can be effectively used to predict the project cost at the pre-design stage with limited information.
Originality/value
No research was conducted to adopt cost modelling techniques into the conceptual estimation practice in the NZ construction industry.
Details
Keywords
Lisa Bosman, Esteban Soto, Jason Ostanek, Jose Garcia-Bravo, Sunghwan Lee and Walter Leon-Salas
The National Science Foundation (NSF) Research Experience for Undergraduates (REU) programs are traditionally delivered in-person and full-time (40 h per week) for 10 weeks during…
Abstract
Purpose
The National Science Foundation (NSF) Research Experience for Undergraduates (REU) programs are traditionally delivered in-person and full-time (40 h per week) for 10 weeks during the summer. However, this type of format has the potential to limit broader student participation. This study aims to compare learning assessment data between a traditional NSF REU (10 weeks of summer, full-time, in-person) to an alternative NSF REU delivered virtually, part-time and over 10 months as a result of the coronavirus disease 2019 (COVID-19) pandemic.
Design/methodology/approach
A retrospective pre-then-post survey was completed to assess perceived learning gains for each REU program. Three learning gains categories were assessed: entrepreneurial competencies, career goals and research skill development. T-tests were used to evaluate a difference in means between pre and post.
Findings
Findings show the greatest quantity of learning gains within the alternative program delivery. Moreover, a larger quantity of learning gains was perceived within the first semester of the alternative program delivery compared to the second semester.
Practical implications
The authors propose the NSF should be intentional about trying new approaches to REU programs delivery, including duration and format, as a way to broaden participation in engineering.
Originality/value
This study is original in that it is the first of its kind to assess an alternative REU program delivery (allowed only because of the COVID-19 pandemic) in comparison to traditional REU program delivery.
Details
Keywords
Lina Gharaibeh, Kristina Eriksson and Björn Lantz
Perceived benefits of building information modelling (BIM) have been discussed for some time, but cost–benefit benchmarking has been inconsistent. The purpose of this paper is to…
Abstract
Purpose
Perceived benefits of building information modelling (BIM) have been discussed for some time, but cost–benefit benchmarking has been inconsistent. The purpose of this paper is to investigate BIM feasibility and evaluate investment worth to elucidate and develop the current understanding of BIM merit. The aim of the study is to propose a research agenda towards a more holistic perspective of BIM use incorporating quantifying investment return.
Design/methodology/approach
An in-depth examination of research patterns has been conducted to identify challenges in the assessment of the investment value and return on investment (ROI) for BIM in the construction industry. A total of 75 research articles were considered for the final literature review. An evaluation of the literature is conducted using a combination of bibliometric analysis and systematic reviews.
Findings
This study, which analysed 75 articles, unveils key findings in quantifying BIM benefits, primarily through ROI calculation. Two major research gaps are identified: the absence of a standardized BIM ROI method and insufficient exploration of intangible benefits. Research focus varies across phases, emphasizing design and construction integration and exploring post-construction phases. The study categorizes quantifiable factors, including productivity, changes and rework reduction, requests for information reduction, schedule efficiency, safety, environmental sustainability and operations and facility management. These findings offer vital insights for researchers and practitioners, enhancing understanding of ’BIM’s financial benefits and signalling areas for further exploration in construction.
Originality/value
The ’study’s outcomes offer the latest insights for researchers and practitioners to create effective approaches for quantifying ’BIM’s financial benefits. Additionally, the proposed research agenda aims to improve the current limited understanding of BIM feasibility and investment worth evaluation. Results of the study could assist practitioners in overcoming limitations associated with BIM investment and economic evaluations in the construction industry.
Details
Keywords
James Prater and Konstantinos Kirytopoulos
This research aspires to contribute in the area of exploration of the psychological traits evolving by practitioners within the project management profession. Specifically, it…
Abstract
Purpose
This research aspires to contribute in the area of exploration of the psychological traits evolving by practitioners within the project management profession. Specifically, it investigates whether there is any difference in optimism levels among experienced project management practitioners and newcomers in the profession.
Design/methodology/approach
The research used the life orientation test-revised (LOTR) (Scheier et al., 1994) to calculate respondents’ optimism scores. With these scores at hand, the researchers could then apply inferential statistics in order to deduce any differences observed among optimism score and the respondents’ characteristics (age, years of experience etc.).
Findings
Based on the results of this research, several demographic variables were shown to be statistically significant with optimism. These were (1) the number of years of experience the respondent had in managing projects, (2) working in a government organisation and (3) possessing specific project management certifications, all of which were found to adversely affect the respondent’s optimism score.
Originality/value
This research was unique in applying a well-known psychological test instrument (LOTR) to provide insight into the psychological impacts of a career as an information technology (IT) project manager. It is also highly likely that this correlation between the length of time working as a project manager and the adverse impact on their optimism would also apply to not just IT project managers but all experienced project managers.
Details
Keywords
Ahmed O. El-Kholei, Ahmed S. Amer and Ghada A. Yassein
Sustainable design is a new paradigm to localize sustainable development. The Union Internationale des Architectes (UIA) prepared guidelines for architectural projects to…
Abstract
Purpose
Sustainable design is a new paradigm to localize sustainable development. The Union Internationale des Architectes (UIA) prepared guidelines for architectural projects to contribute to the Sustainable Development Goals (SDGs). Using the theory of change, the Department of Architecture at Menofia University set the 2023 graduation project to explore the possibility of adopting sustainable design principles and integrating SDGs into architectural education. The paper documents and evaluates the experiment to drive best practices and lessons learned.
Design/methodology/approach
The paper utilized a mixed design strategy utilizing qualitative and quantitative techniques. It gathered data from various sources, including a student questionnaire and unstructured interviews with external examiners. Data analysis included frequency distribution and sentiment, content and thematic analyses. Triangulation is applied, combining data, investigator and methodological triangulation to enhance the paper’s validity.
Findings
Integrating SDGs into the 2023 graduation project contributed to students’ understanding of sustainable urban development. Students demonstrated varying receptiveness to guidelines, focusing mainly on the SDGs (1-5, 7, 8, 10 and 11). Gender equality and economic empowerment struck a chord with the mostly female students, acknowledging that securing well-paying jobs is a way to escape the cycle of poverty. Challenges included limited resources and time constraints, a scarcity of Arabic reading materials and misunderstandings among students and staff, thus prompting collaborative efforts beyond standard studio hours. Despite challenges, the initiative contributes to sustainable urban development, providing valuable lessons learned and insights.
Originality/value
Integrating sustainable design principles into architectural education is doable but involves a complex process requiring careful preparation. The value lies in the tangible impact on sustainable urban development, emphasizing the importance of incorporating sustainable development concepts throughout the architectural curriculum. The authors advocate for increased awareness and education among stakeholders and suggest areas for future research by exploring a broader implementation and assessing the long-term effects on students’ mindsets and practices. Sustainable development is a means toward community prosperity, and the inquiry highlights the collective responsibility of scholars, practitioners and students in shaping a better future.
Details
Keywords
Asli Pelin Gurgun, Kerim Koc and Handan Kunkcu
Completing construction projects within the planned schedule has widely been considered as one of the major project success factors. This study investigates the use of…
Abstract
Purpose
Completing construction projects within the planned schedule has widely been considered as one of the major project success factors. This study investigates the use of technologies to address delays in construction projects and aims to address three research questions (1) to identify the adopted technologies and proposed solutions in the literature, (2) to explore the reasons why the delays cannot be prevented despite disruptive technologies and (3) to determine the major strategies to prevent delays in construction projects.
Design/methodology/approach
In total, 208 research articles that used innovative technologies, methods, or tools to avoid delays in construction projects were investigated by conducting a comprehensive literature review. An elaborative content analysis was performed to cover the implemented technologies and their transformation, highlighted research fields in relation to selected technologies, focused delay causes and corresponding delay mitigation strategies and emphasized project types with specific delay causes. According to the analysis results, a typological framework with appropriate technological means was proposed.
Findings
The findings revealed that several tools such as planning, imaging, geo-spatial data collection, machine learning and optimization have widely been adopted to address specific delay causes. It was also observed that strategies to address various delay causes throughout the life cycle of construction projects have been overlooked in the literature. The findings of the present research underpin the trends and technological advances to address significant delay causes.
Originality/value
Despite the technological advancements in the digitalization era of Industry 4.0, many construction projects still suffer from poor schedule performance. However, the reason of this is questionable and has not been investigated thoroughly.
Details
Keywords
John Thomas Flynn and Lloyd Levine
A quick search of the headlines of major newspapers reveals a treasure trove of technology procurement gone wrong. While the private sector seems to adopt and implement new…
Abstract
A quick search of the headlines of major newspapers reveals a treasure trove of technology procurement gone wrong. While the private sector seems to adopt and implement new technology seamlessly and quickly to deliver for customers, the government struggles to accomplish technology purchases and integrations with the same ease. As governments in the United States are looking to retain their current workforce and attract the next generation of workers, the technological capabilities and ethos of governments will be paramount. With nearly every industry being transformed by technology and Generation T being the first generation to have an ingrained “technology first” mindset, the ability of governments to attract these workers depends, in large part, on the ability to transform their government technology culture, policies, and practices.
In this chapter, the authors examine the administrative branch and observe two key components at the root of most technology failures: poor organizational structure in the bureaucracy and the lack of an empowered Chief Information/Technology Officer. Building upon case studies from Massachusetts and California, this chapter looks at the factors related to failure or success to understand the technology procurement culture. The chapter concludes by presenting four key “best practice” principles of public policy and administration that can be implemented by almost any governmental entity to improve their acquisition and implementation of technology.
Details
Keywords
Giovanni Cláudio Pinto Condé, José Carlos Toledo and Mauro Luiz Martens
The purpose of this paper is to test and develop a method for generation and selection of six sigma projects. This is done by testing the use of the generation and selection…
Abstract
Purpose
The purpose of this paper is to test and develop a method for generation and selection of six sigma projects. This is done by testing the use of the generation and selection method for six sigma projects (GSM_SSP) in a Brazilian manufacturing industry with the participation of managers, aiming to gather the user’s perspective and improvement opportunities for the approach itself.
Design/methodology/approach
The work adopts the action research (AR) approach once the researchers were busily involved in the training, implementation and use of the GSM_SSP. The intervention was performed in on a series of 15 workshops, with a group of managers, during six months.
Findings
The application of the eight steps of the GSM_SSP approach assisted the company’s management team to generate nine project candidates and also to select three six sigma projects. This study also finds and discusses barriers and lessons learned used to improve the GSM_SSP.
Research limitations/implications
This study presents an example of how six sigma project generation and selection has been applied to a manufacturing industry by adapting AR to the process using the eight steps of GSM_SSP, demonstrating how the management team was involved. This study should be replicated in different companies because AR is limited in its generalization.
Originality/value
To the best of the authors’ knowledge, this study represents the first use of AR methodology in six sigma project selection. This study contributes a method that can generate and select six sigma projects. In doing so, the research offers a simple approach that can be used by managers. In addition, the steps of the approach before selection were explored.
Details
Keywords
Nirodha Fernando, Kasun Dilshan T.A. and Hexin (Johnson) Zhang
The Government’s investment in infrastructure projects is considerably high, especially in bridge construction projects. Government authorities must establish an initial…
Abstract
Purpose
The Government’s investment in infrastructure projects is considerably high, especially in bridge construction projects. Government authorities must establish an initial forecasted budget to have transparency in transactions. Early cost estimating is challenging for Quantity Surveyors due to incomplete project details at the initial stage and the unavailability of standard cost estimating techniques for bridge projects. To mitigate the difficulties in the traditional preliminary cost estimating methods, there is a requirement to develop a new initial cost estimating model which is accurate, user friendly and straightforward. The research was carried out in Sri Lanka, and this paper aims to develop the artificial neural network (ANN) model for an early cost estimate of concrete bridge systems.
Design/methodology/approach
The construction cost data of 30 concrete bridge projects which are in Sri Lanka constructed within the past ten years were trained and tested to develop an ANN cost model. Backpropagation technique was used to identify the number of hidden layers, iteration and momentum for optimum neural network architectures.
Findings
An ANN cost model was developed, furnishing the best result since it succeeded with around 90% validation accuracy. It created a cost estimation model for the public sector as an accurate, heuristic, flexible and efficient technique.
Originality/value
The research contributes to the current body of knowledge by providing the most accurate early-stage cost estimate for the concrete bridge systems in Sri Lanka. In addition, the research findings would be helpful for stakeholders and policymakers to propose policy recommendations that positively influence the prediction of the most accurate cost estimate for concrete bridge construction projects in Sri Lanka and other developing countries.