Article
Publication date: 14 October 2022

Sakibu Seidu, De-Graft Owusu-Manu, Augustine Senanu Komla Kukah, Michael Adesi, Eric Oduro-Ofori and David John Edwards

The demand for energy infrastructure projects has increased steadily over the last few decades and has come at a high cost. Disruptive technologies (DTs) have the inherent…

Abstract

Purpose

The demand for energy infrastructure projects has increased steadily over the last few decades and has come at a high cost. Disruptive technologies (DTs) have the inherent capability to affect the performance of energy infrastructure projects. Therefore, this research aims to explore the implications of DTs on the performance of energy infrastructure projects.

Design/methodology/approach

This research adopts a positivist philosophical position. A quantitative strategy and deductive approach (based on a survey design) guided this study. Sixty-six respondents participated in the study. The study’s population comprised of experts in energy infrastructure projects who possessed a high level of industrial experience including top- and middle-level management of power generation companies. Cochran’s formula was used to select a sufficient sample for the study. Linear regression, one sample test and Cronbach’s alpha were the analytical tools adopted.

Findings

This study established that there is an 18.4% increase in the performance of energy infrastructure projects in Ghana when DTs are applied. In order of importance, DTs improve speed of operations in energy projects; reduce operating cost and enhance efficiency of energy projects; drive sustainable economic development; enhance security in energy projects; and improve environmental sustainability of projects. The study also revealed that e-commerce technologies, renewable energy technologies, three-dimensional printing, bar code technology, photogrammetry, global positioning systems, geographic information systems and nanotechnologies were the topmost ranked DTs with the most impact on the performance of energy infrastructure projects.

Originality/value

This is a novel investigation on the implications of DTs on the performance of Ghanaian energy infrastructure projects. This study’s practical implication is evident in both policy and practice. Energy sector policymakers should endeavour to adopt DTs in their operations to enhance sustainability and performance.

Details

International Journal of Energy Sector Management, vol. 17 no. 5
Type: Research Article
ISSN: 1750-6220

Keywords

Article
Publication date: 12 July 2023

Augustine Senanu Komla Kukah, De-Graft Owusu-Manu, Edward Badu, David J. Edwards and Eric Asamoah

Public-private partnership (PPP) power projects are associated with varying risk factors. This paper aims to develop a fuzzy quantitative risk allocation model (QRAM) to guide…

Abstract

Purpose

Public-private partnership (PPP) power projects are associated with varying risk factors. This paper aims to develop a fuzzy quantitative risk allocation model (QRAM) to guide decision-making on risk allocation in PPP power projects in Ghana.

Design/methodology/approach

A total of 67 risk factors and 9 risk allocation criteria were established from literature and ranked in a two-round Delphi survey using questionnaires. The fuzzy synthetic evaluation method was used in developing the risk allocation model.

Findings

The model’s output variable is the risk allocation proportions between the public body and private body based on their capability to manage the risk factors. Out of the 37 critical risk factors, the public sector was allocated 12 risk factors with proportions = 50%, while the private sector was allocated 25 risk factors with proportions = 50%.

Originality/value

To the best of the authors’ knowledge, this research presents the first attempt in Ghana at endeavouring to develop a QRAM for PPP power projects. There is confidence in the model to efficiently allocate risks emanating from PPP power projects.

Details

Journal of Financial Management of Property and Construction , vol. 29 no. 1
Type: Research Article
ISSN: 1366-4387

Keywords

Article
Publication date: 10 July 2023

Augustine Senanu Komla Kukah, De-Graft Owusu-Manu, Edward Badu, David John Edwards and Eric Asamoah

The purpose of this paper was to first identify and then model the impact of critical success factors (CSFs) of public–private partnership (PPP) power projects.

Abstract

Purpose

The purpose of this paper was to first identify and then model the impact of critical success factors (CSFs) of public–private partnership (PPP) power projects.

Design/methodology/approach

Review of empirical literature came out with 20 CSFs which were ranked by experts and industry practitioners through a two-round Delphi questionnaire survey.

Findings

These CSFs were grouped into CSF groups (CSFGs) using component analysis, and they served as the input variables for fuzzy analysis. The six components were collaboration and transparency, guarantee and permits, socio-political support, expected profitability, technical feasibility and risk allocation (RA). Overall success index of PPP power projects in Ghana was 5.966 and showed there is high impact of CSFGs on project success. Fuzzy analysis also confirmed RA as the most significant CSFG.

Originality/value

The model developed can serve as a multi-dimension CSF framework that can be used as a success attainment tool for PPP power projects. For policy developers and stakeholders, the model serves as a pointer to issues which the government/public sector must focus on to attract huge investments from the private sector in the power sector.

Details

Journal of Facilities Management , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1472-5967

Keywords

Article
Publication date: 12 May 2023

Augustine Senanu Komla Kukah, De-Graft Owusu-Manu, Edward Badu, David John Edwards, Eric Asamoah, Andrew Anafo, Dominic Kuutiero and Richmond Makafui Kofi Kukah

In comparison to other countries, power generation in Sub-Sahara Africa is poor. Public–private partnership (PPP) model has become increasingly popular for addressing…

Abstract

Purpose

In comparison to other countries, power generation in Sub-Sahara Africa is poor. Public–private partnership (PPP) model has become increasingly popular for addressing infrastructural challenges, especially in the power sector. The purpose of this study is to evaluate and classify the factors that influence public sector involvement in Ghanaian PPP power projects.

Design/methodology/approach

Using purposive and snowball sampling techniques, questionnaires were used to gather responses from experts in the PPP power sector in a two round Delphi survey. Analytical tools adopted were descriptive statistics, mean score ranking, Cronbach’s alpha and factor analysis.

Findings

The most significant factors that influence public sector involvement in PPP power projects were: achieving improved value for money; access to additional capital; increased certainty of projects; greater efficiency of project delivery services; and improved ability to deliver new infrastructure. From factor analysis, the four components were: value for money and efficiency; capital and skills; innovation and technology; and project delivery.

Originality/value

Government bodies in the power sector will benefit from the findings, as it would aid them develop policies that would strengthen regulatory structures as well as institutions.

Details

Journal of Facilities Management , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1472-5967

Keywords

Article
Publication date: 14 February 2023

Alice Stewardson, David J. Edwards, Eric Asamoah, Clinton Ohis Aigbavboa, Joseph H.K. Lai and Hatem El-Gohary

The UK government has elaborated the effect of late payment on the economy, with its impact on the construction sector being particularly pronounced. This paper aims to evaluate…

Abstract

Purpose

The UK government has elaborated the effect of late payment on the economy, with its impact on the construction sector being particularly pronounced. This paper aims to evaluate the late payment epidemic that persists within the construction industry, specifically analysing the effectiveness of government-led voluntary payment initiatives.

Design/methodology/approach

A mixed philosophical lens is adopted that incorporates both pragmatism and post-positivism to examine the late payment phenomena. Couched within deductive reasoning and a case study strategy, a questionnaire survey was conducted to elicit responses from one-hundred construction professionals. Elucidating upon respondents’ perceptions of the UK’s late payment epidemic, a comparative analysis was undertaken of upstream (main contractor) and downstream (subcontractors/suppliers) contractors through Cronbach’s alpha, descriptive statistics, independence chi-square test, Kruskal–Wallis test and Mann–Whitney U test.

Findings

Emergent findings reveal that in practice, the monitoring and enforcement of government-led voluntary payment initiatives has been unprosperous with numerous contractors being forced to adopt indefensibly poor and punitive payment practices. Survey responses and extant literature substantiate and underscore the industry’s need to strengthen voluntary government-led payment initiatives. To create a responsible payment culture, any future code created should be mandatory and enforceable as a self-regulating approach has failed dismally. The work concludes with practical additional measures that could be introduced to create a responsible payment culture and promote ethical trading within the UK construction industry.

Originality/value

This paper constitutes a novel vignette of, and reflection upon, contemporary practice in this area of construction finance and serves to emphasise that very little has changes in the sector despite numerous UK government led reports and interventions.

Details

Journal of Financial Management of Property and Construction , vol. 28 no. 3
Type: Research Article
ISSN: 1366-4387