Article
Publication date: 21 December 2021

Bamidele Temitope Arijeloye, Isaac Olaniyi Aje and Ayodeji Emmanuel Oke

The purpose of the study is to elicit risk factors that are peculiar to public-private partnership (PPP)-procured mass housing in Nigeria from the expert perspectives in ensuring…

Abstract

Purpose

The purpose of the study is to elicit risk factors that are peculiar to public-private partnership (PPP)-procured mass housing in Nigeria from the expert perspectives in ensuring the success of the scheme thereby reducing housing deficit in the country.

Design/methodology/approach

The risk inherent in construction projects had been established through literature in general. The risk in PPP projects is emerging because of the recent acceptance of the procurement option by governments all over the globe. The Nigerian Government has also adopted the procurement option in bridging the housing deficit in the country. This study, therefore, conducts a Delphi survey on the probability of risk occurrence peculiar to PPP mass housing projects (MHPs) in Nigeria. Pragmatic research approach through the mixed method of both quantitative and qualitative methods was adopted for this study. The quantitative method adopts the administration of questionnaires through the Delphi survey, whereas the qualitative method used interviews with the respondents. A two-stage Delphi questionnaire was administered to construction practitioners that cut across academics, the public and the private sectors by adopting convenient sampling techniques and following the Delphi principles and procedures. A total of 63 risk factors were submitted to the expert to rank on a Likert scale of 7 and any risk factors that the mean item score (MIS) falls below the grading scale of the five-point benchmark is deemed not necessary a risk factor associated with PPP MHPs and thereby expunged from the second round of the Delphi Survey. The interview was subsequently applied to the respondents to substantiate the risk factors that are peculiar to PPP-procured mass housing in the study area.

Findings

The findings show that risk factors such as maintenance frequent than expected, life of facility shorter than anticipated and maintenance cost higher than expected fall below 5.0 benchmark with MIS of 4.64 and 4.55 indicating that the risk factors are not peculiar to PPP mass housing in Nigeria.

Research limitations/implications

The implication for practise of this research is that these risk factors provide the PPP stakeholders with the comprehensive checklists that can aid in developing PPP risk assessment guidelines in the sector though both partners should be aware of the dynamic nature of risk because new ones might be emerging.

Originality/value

The authors hereby declare that the research findings are a product of a thorough research conducted in the study area and have not to be submitted or published by another person or publisher and due acknowledgement was made where necessary.

Details

Journal of Engineering, Design and Technology , vol. 22 no. 1
Type: Research Article
ISSN: 1726-0531

Keywords

Abstract

Details

A Neoliberal Framework for Urban Housing Development in the Global South
Type: Book
ISBN: 978-1-83797-034-6

Article
Publication date: 1 December 2023

Xufan Zhang, Xue Fan and Mingke He

The challenges faced by China's high-end equipment manufacturing (HEEM) industry are becoming clearer in the process of global supply chain (GSC) reconfiguration. The purpose of…

Abstract

Purpose

The challenges faced by China's high-end equipment manufacturing (HEEM) industry are becoming clearer in the process of global supply chain (GSC) reconfiguration. The purpose of this study is to investigate how China's HEEM industry has been affected by the GSC reconfiguration, as well as its short- and long-term strategies.

Design/methodology/approach

The authors adopted a multi-method approach. Interviews were conducted in Phase 1, while a three-round Delphi survey was conducted in Phase 2 to reach consensus at the industry level.

Findings

The GSC reconfiguration affected China's HEEM supply chain (SC). Its direct effects include longer lead times, higher purchasing prices and inconsistent supply and inventory levels of key imported components and materials. Its indirect effects include inconsistent product quality and cash flows. In the short term, China's HEEM enterprises have sought to employ localized substitutes, while long-term strategies include continuous technological innovation, industry upgrades and developing SC resilience.

Originality/value

This study not only encourages Chinese HEEM enterprises to undertake a comprehensive examination of their respective industries but also provides practical insights for SC scholars, policymakers and international stakeholders interested in how China's HEEM industry adapts to the GSC reconfiguration and gains global market share.

Details

International Journal of Physical Distribution & Logistics Management, vol. 54 no. 1
Type: Research Article
ISSN: 0960-0035

Keywords

Article
Publication date: 14 February 2024

Ahmed Ashraf Zaidi and Rahul Chandra

In recent years, researchers and practitioners have paid a great deal of attention to the circular economy (CE) due to its potential social and environmental benefits. However…

Abstract

Purpose

In recent years, researchers and practitioners have paid a great deal of attention to the circular economy (CE) due to its potential social and environmental benefits. However, limited attention has been devoted in the literature to studying the barriers to CE implementation in the apparel retail industry in emerging and developing nations besides China. Consequently, the purpose of this paper is to analyse the barriers to implementing CE in the Indian garment retail market.

Design/methodology/approach

This exploratory study uses a comprehensive literature analysis to identify the micro-level impediments to CE adoption in India's garment retail industry. The study aims to identify these barriers using a Delphi process, consisting of three stages. The first stage involves literature reviews and expert opinions, while the second and third stages involve survey methods with 14 industry professionals and academics. The use of the two primary data sources allows for triangulation of the data, which improves the validity of the findings and enables broader conclusions to be drawn from the results.

Findings

This study indicates that the top three challenges to implementing CE principles in the Indian apparel retail industry are “standards and regulation barriers” (84%), “strategic barriers” (82%) and “supply chain management and technology barriers” (79%). Strategies for overcoming these obstacles include gaining top management support, coordinating supply chain components, training and employee motivation.

Research limitations/implications

This study considers only Indian apparel retail industry, and the practical implications could potentially limit the study to emerging Asian economies.

Originality/value

To the best of the authors’ knowledge, this is the first research of its type to explore CE obstacles at the organizational level in the Indian garment retail business. Thus, it contributes to a greater understanding of the topic and enables practitioners to develop effective policies and business strategies for CE and sustainability.

Details

Research Journal of Textile and Apparel, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1560-6074

Keywords

Article
Publication date: 3 April 2024

Deraniyagalage Chanaka Karunarathna, H.A.H.P. Perera, B.A.K.S. Perera and P.A.P.V.D.S. Disaratna

Delays in utility shifting during road construction have broad ramifications. These delays not only lengthen the project's timeline but also raise expenses and cause problems with…

Abstract

Purpose

Delays in utility shifting during road construction have broad ramifications. These delays not only lengthen the project's timeline but also raise expenses and cause problems with resource allocation. Thus, this study investigates the influence of delay in utility shifting for extension of time claims in road construction projects (RCPs) in Sri Lanka.

Design/methodology/approach

The study used a quantitative approach with three rounds of Delphi surveys to gather empirical data. Further, the probability impact assessment was used to carefully analyse the data and appraise the information gathered.

Findings

The findings initially revealed 33 causes of delays in utility shifting for extension of time claims in RCPs in Sri Lanka. Ultimately, 11 severe causes were identified based on their high probability and impact, concluding with 45 strategies that were assigned to overcoming those most severe causes of delay.

Originality/value

This study will contribute to the industry and theory by providing solutions to handle utility-shifting delays with the linkage of preventing time extension claims for RCPs in Sri Lanka. Further, there is a dearth of literature in the research area, both locally and globally. Thus, the findings of this research will provide a benchmark for further detailed studies in other countries as well.

Details

Smart and Sustainable Built Environment, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 2046-6099

Keywords

Article
Publication date: 12 July 2023

Augustine Senanu Komla Kukah, De-Graft Owusu-Manu, Edward Badu, David J. Edwards and Eric Asamoah

Public-private partnership (PPP) power projects are associated with varying risk factors. This paper aims to develop a fuzzy quantitative risk allocation model (QRAM) to guide…

Abstract

Purpose

Public-private partnership (PPP) power projects are associated with varying risk factors. This paper aims to develop a fuzzy quantitative risk allocation model (QRAM) to guide decision-making on risk allocation in PPP power projects in Ghana.

Design/methodology/approach

A total of 67 risk factors and 9 risk allocation criteria were established from literature and ranked in a two-round Delphi survey using questionnaires. The fuzzy synthetic evaluation method was used in developing the risk allocation model.

Findings

The model’s output variable is the risk allocation proportions between the public body and private body based on their capability to manage the risk factors. Out of the 37 critical risk factors, the public sector was allocated 12 risk factors with proportions = 50%, while the private sector was allocated 25 risk factors with proportions = 50%.

Originality/value

To the best of the authors’ knowledge, this research presents the first attempt in Ghana at endeavouring to develop a QRAM for PPP power projects. There is confidence in the model to efficiently allocate risks emanating from PPP power projects.

Details

Journal of Financial Management of Property and Construction , vol. 29 no. 1
Type: Research Article
ISSN: 1366-4387

Keywords

Article
Publication date: 15 February 2023

Ismail Badraoui, Ivo A.M.C. van der Lans, Youssef Boulaksil and Jack G.A.J. van der Vorst

This study aims to compare the expectations of non-collaborating professionals and the actual opinions of collaborating professionals regarding success factors of horizontal…

Abstract

Purpose

This study aims to compare the expectations of non-collaborating professionals and the actual opinions of collaborating professionals regarding success factors of horizontal logistics collaboration (HLC) and investigates the reasons behind the observed differences.

Design/methodology/approach

This study employs a mixed-method approach. First, a survey is conducted to collect data from two samples representing collaborating and non-collaborating industry professionals. Second, confirmatory factor analysis (CFA) is used to compare the measurement models from the two samples and identify their similarities and differences. Third, a Delphi study is conducted to identify factors limiting collaborative behavior.

Findings

The results show that collaborating professionals exhibit lower levels of joint relationship efforts and trust than expected. This is primarily due to inadequate information sharing, poor collaboration formalization and the absence of a clear costs and benefits allocation mechanism.

Practical implications

The findings indicate that, in HLC, managers should give high importance to facilitating timely and complete information exchange, putting in place an acceptable costs/benefits allocation mechanism, formalizing the collaboration and prioritizing integrity over competency when selecting partners.

Originality/value

To the best of the authors’ knowledge, this is the first study that shows the existence of differences between industry professionals' pre-collaboration expectations and the actual experiences in HLC. This is also the first study that points to the exact HLC enablers that fail in practice and the barriers responsible for it.

Details

Benchmarking: An International Journal, vol. 31 no. 1
Type: Research Article
ISSN: 1463-5771

Keywords

Article
Publication date: 16 February 2024

M.K.S. Al-Mhdawi, Alan O'connor, Abroon Qazi, Farzad Rahimian and Nicholas Dacre

This research aims to systematically review studies on significant risks for Critical Infrastructure Projects (CIPs) from selected top-tier academic journals from 2011 to 2023.

Abstract

Purpose

This research aims to systematically review studies on significant risks for Critical Infrastructure Projects (CIPs) from selected top-tier academic journals from 2011 to 2023.

Design/methodology/approach

In this research, a three-step systematic literature review methodology was employed to analyse 55 selected articles on Critical Infrastructure Risks (CIRs) from well-regarded and relevant academic journals published from 2011 to 2023.

Findings

The findings highlight a growing research focus on CIRs from 2011 to 2023. A total of 128 risks were identified and grouped into ten distinct categories: construction, cultural, environmental, financial, legal, management, market, political, safety and technical risks. In addition, literature reviews combined with questionnaire surveys were more frequently used to identify CIRs than any other method. Moreover, oil and gas projects were the subjects most often explored in the reviewed papers. Furthermore, it was observed that publications from Iran, the USA and China dominated CIRs research, making significant contributions, accounting for 49.65% of the analysed articles.

Research limitations/implications

This research specifically focuses on five types of CIPs (i.e. roadways, bridges, water supply systems, dams and oil and gas projects). Other CIPs like cyber-physical systems or electric power systems, were not considered in this research.

Practical implications

Governments and contracting firms can benefit from the findings of this study by understanding the significant risks associated with the execution of CIPs, irrespective of the nation, industry or type of project. The results of this investigation can offer construction professionals valuable insights to formulate and implement risk response plans in the early stages of a project.

Originality/value

As a novel literature review related to CIRs, it lays the groundwork for future research and deepens the understanding of the multi-faceted effects of these risks, as well as sets practical response strategies.

Details

Smart and Sustainable Built Environment, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 2046-6099

Keywords

Article
Publication date: 10 May 2022

Augustine Senanu Komla Kukah, De-Graft Owusu-Manu, Edward Badu and David John Edwards

This study aims to evaluate the key risk factors inherent in public–private partnership (PPP) power projects in Ghana and further determine the critical risk factors affecting…

Abstract

Purpose

This study aims to evaluate the key risk factors inherent in public–private partnership (PPP) power projects in Ghana and further determine the critical risk factors affecting both the public and private sectors in PPP power projects.

Design/methodology/approach

Ranking-type Delphi survey in two rounds was conducted to establish a comprehensive list of critical risk factors of PPP. Purposive and snowball sampling techniques helped obtain experts for the Delphi survey. Mean score ranking, factor analysis, Cronbach α coefficient and Kendall’s concordance were used for analysis. The probability of occurrence and severity of each risk factor were computed to obtain the risk impact.

Findings

From the list of 67 risks, 37 risk factors were deemed to be critical. The five topmost risk factors were: delay payment on contract, private investor change, political risks, fluctuating demand of power generated and public opposition. Principal component analysis grouped the risk factors into seven major themes.

Originality/value

This study develops an authoritative risk factor list for PPP power projects, which reflects both sector and country conditions for prioritizing and mitigating risk factors. Delphi approach adopted in this study can be used by future studies in similar environments where PPP is novel and expert respondents scarce.

Details

Journal of Facilities Management , vol. 22 no. 1
Type: Research Article
ISSN: 1472-5967

Keywords

Article
Publication date: 12 July 2023

A.M.D.S. Atapattu, Chandanie Hadiwattage, B.A.K.S. Perera and Dilakshan Rajaratnam

The circular economy concept emerged as the resolution to the destructive linear economy practices. Nevertheless, the transition to a circular built environment is hindered due to…

Abstract

Purpose

The circular economy concept emerged as the resolution to the destructive linear economy practices. Nevertheless, the transition to a circular built environment is hindered due to the ambiguities of the economic value of the concept. Conversely, numerous decision-making tools are applied in the construction industry in assessing economic alternatives, even if there is a gap in utilising these tools in appraising circular economic practices. Hence, this study investigates the potential benefits of applying proven decision-making practices, particularly criteria scoring matrices, in developing circular built environments.

Design/methodology/approach

A qualitative approach was followed to achieve the aim of the study. A conceptual design of a criteria scoring matrix was developed with a comprehensive literature survey. Semi-structured interviews of a three-round Delphi expert survey were employed to assess the matrix qualitatively and develop the matrix further. Data were analysed using the content analysis method.

Findings

The lack of a value assessment tool in economically assessing the circular economy principles is a key barrier to transcending to a circular built environment. In addressing this issue, this study develops a criteria scoring matrix for circularity value assessment during the design stage of a construction project.

Originality/value

This research contributes to the theory by developing a criteria scoring matrix to measure the economic contribution of circular economy principles. Further, this research contributes to the practice by allowing construction alternatives to be selected, balancing the potential economic return options of a project with the project's contribution to a circular economy.