Search results

1 – 10 of over 42000
Article
Publication date: 5 September 2018

Octaviano Rojas Luiz, Fernando Bernardi de Souza, João Victor Rojas Luiz and Daniel Jugend

The purpose of this paper is to analyze the state of the art in Critical Chain Project Management (CCPM), outlining the CCPM literature to date, in an effort to guide future…

1361

Abstract

Purpose

The purpose of this paper is to analyze the state of the art in Critical Chain Project Management (CCPM), outlining the CCPM literature to date, in an effort to guide future studies.

Design/methodology/approach

The paper is based on a bibliometric analysis using Scopus and Web of Science databases. The authors identified the principal journals, articles and authors regarding the research theme, as well as the authors elaborated co-citation and co-occurrence network maps to support the analysis.

Findings

The authors described five co-citation clusters: Fundamentals of Critical Chain, Scheduling, Operations Research, Multi-project and Network, and General Project Management. The most frequently occurring keywords were: “project management,” “critical chain,” “scheduling” and “theory of constraints.” Observing the distribution, the expression “project management” occupied a central position, connecting two other clusters, represented by the keywords “scheduling” and “critical chain.” The authors proposed an evolutive framework for the CCPM state of the art in three stages, according to the most frequent topics identified: Conceptual, Deepening of Applications and Methodological Maturity.

Originality/value

This research adopts a systematic approach based on bibliometric tools, which allows a more rigorous organization of the literature. Co-citation and keyword co-occurrence maps provide evidence of how the main themes in CCPM relate. Besides, the presented historical framework allows new research in CCPM to be directed to the most recent topics of interest that have gaps to be explored.

Details

International Journal of Managing Projects in Business, vol. 12 no. 2
Type: Research Article
ISSN: 1753-8378

Keywords

Article
Publication date: 17 March 2021

Shakib Zohrehvandi, Mohammad Khalilzadeh, Maghsoud Amiri and Shahram Shadrokh

The aim of this research is to propose a buffer sizing and buffer controlling algorithm (BSCA) as a heuristic algorithm for calculating project buffer and feeding buffers as well…

Abstract

Purpose

The aim of this research is to propose a buffer sizing and buffer controlling algorithm (BSCA) as a heuristic algorithm for calculating project buffer and feeding buffers as well as dynamic controlling of buffer consumption in different phases of a wind power plant project in order to achieve a more realistic project duration.

Design/methodology/approach

The BSCA algorithm has two main phases of planning and buffer sizing and construction and buffer consumption. Project buffer and feeding buffers are determined in the planning and buffer sizing phase, and their consumption is controlled in the construction and buffer consumption phase. The heuristic algorithm was coded and run in MATLAB software. The sensitivity analysis was conducted to show the BSCA influence on project implementation. Then, to evaluate the BSCA algorithm, inputs from this project were run through several algorithms recently presented by researchers. Finally, the data of 20 projects previously accomplished by the company were applied to compare the proposed algorithm.

Findings

The results show that BSCA heuristic algorithm outperformed the other algorithms as it shortened the projects' durations. The average project completion time using the BSCA algorithm was reduced by about 15% compared to the previous average project completion time.

Originality/value

The proposed BSCA algorithm determines both the project buffer and feeding buffers and simultaneously controls their consumption in a dynamic way.

Details

Engineering, Construction and Architectural Management, vol. 29 no. 2
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 2 October 2017

Anand Kulkarni, Devinder Kumar Yadav and Hamid Nikraz

Aircraft operators incur significant costs when an aircraft is taken out of service for maintenance. The purpose of this paper is to present a method for reducing time duration of…

1133

Abstract

Purpose

Aircraft operators incur significant costs when an aircraft is taken out of service for maintenance. The purpose of this paper is to present a method for reducing time duration of aircraft maintenance checks using critical chain project management (CCPM) principle.

Design/methodology/approach

A case study of a typical heavy maintenance check performed on an Airbus 320 aircraft is undertaken for the analysis. The critical chain method is applied to develop a plan with a reduced duration and a survey and field observations to validate the findings have also been carried out as a part of this paper.

Findings

The paper compares the traditional project management method with CCPM in view of reducing the aircraft down time duration for maintenance. This paper repositions buffers and other techniques to shorten the chain path and a reduction in the total duration of the project by five days is achieved.

Research limitations/implications

It is argued that the application of CCPM principle can reduce the duration of an aircraft maintenance check, but this paper is done in a single project situation focusing on project planning and execution. Therefore, additional study may be required to examine other issues.

Originality/value

Cost of the maintenance is second highest expenditure factor for an airline operator. Therefore, it is necessary to drive the maintenance cost down. The paper demonstrates that the duration of a maintenance check can be reduced by 8.9 per cent using the method suggested in this paper.

Details

Aircraft Engineering and Aerospace Technology, vol. 89 no. 6
Type: Research Article
ISSN: 1748-8842

Keywords

Article
Publication date: 29 April 2020

Shakib Zohrehvandi, Mario Vanhoucke and Mohammad Khalilzadeh

This study aims to introduce an efficient project buffer and resource management (PBRM) model for project resource leveling and project buffer sizing and controlling of project

Abstract

Purpose

This study aims to introduce an efficient project buffer and resource management (PBRM) model for project resource leveling and project buffer sizing and controlling of project buffer consumption of a wind power plant project to achieve a more realistic project duration.

Design/methodology/approach

The methodology of this research consists of three main phases. In the first phase of the research methodology, resource leveling is done in the project and resource conflicts of activities are identified. In the second phase, the project critical chain is determined, and the appropriate size of the project buffer is specified. In the third phase of the methodology, buffer consumption is controlled and monitored during the project implementation. After using the PBRM method, the results of this project were compared with those of the previous projects.

Findings

According to the obtained results, it can be concluded that using PBRM model in this wind turbine project construction, the project duration became 25 per cent shorter than the scheduled duration and also 29 per cent shorter than average duration of previous similar projects.

Research limitations/implications

One of the major problems with projects is that they are not completed according to schedule, and this creates time delays and losses in the implementation of projects. Today, as projects in the energy sector, especially renewable projects, are on the increase and also we are facing resource constraint in the implementation of projects, using scheduling techniques to minimize delays and obtain more realistic project duration is necessary.

Practical implications

This research was carried out in a wind farm project. In spite of the initial plan duration of 142 days and average duration of previous similar projects of 146 days, the project was completed in 113 days.

Originality/value

This paper introduces a practical project buffer and resource management model for project resource leveling, project buffer sizing and buffer consumption monitoring to reach a more realistic schedule in energy sector. This study adds to the literature by proposing the PBRM model in renewable energy sector.

Details

International Journal of Energy Sector Management, vol. 14 no. 6
Type: Research Article
ISSN: 1750-6220

Keywords

Open Access
Article
Publication date: 9 November 2018

Viviane Souza Vilela Junqueira, Marcelo Seido Nagano and Hugo Hissashi Miyata

This paper aims to exemplify the use of project management tools in the scheduling of aircraft maintenance activities. This process is known as maintenance, repair and overhaul…

6644

Abstract

Purpose

This paper aims to exemplify the use of project management tools in the scheduling of aircraft maintenance activities. This process is known as maintenance, repair and overhaul and it has gained importance within the aeronautical sector due to its expected growth in the coming years; however, it also faces increasing competitiveness in its market. This fact gives rise to the need of acting in maintenance management and seeking lower costs while maintaining the quality of the service provided. The purpose of this paper is to propose the structuring of a procedure that aims to reduce the total maintenance time (downtime) and guarantee the delivery of the aircraft on time.

Design/methodology/approach

The paper, through a case study at a Brazilian aircraft maintenance center, used critical path method and critical chain project management, the latter being derived from the theory of constraints, with the purpose of analyzing resources systematically and synchronizing the activities in the precedence network.

Findings

As a result, it is shown that downtime can be reduced from 11 to 5 days and improvements are proposed to achieve greater market competitiveness.

Originality/value

This paper demonstrates the competitive advantage that resulted from the application of project management tools in the aircraft maintenance planning and execution.

Details

Revista de Gestão, vol. 27 no. 1
Type: Research Article
ISSN: 2177-8736

Keywords

Article
Publication date: 10 May 2019

Shakib Zohrehvandi and Mohammad Khalilzadeh

The purpose of this paper is to present an efficient model for project buffer sizing by taking failure mode and effects analysis (FMEA) into account to reach a more realistic…

Abstract

Purpose

The purpose of this paper is to present an efficient model for project buffer sizing by taking failure mode and effects analysis (FMEA) into account to reach a more realistic schedule.

Design/methodology/approach

In the first phase of the project, several turbines were installed according to the primary schedule with an average duration of 142 days. Then, some of critical chain project management algorithms were separately applied in the implementation and installation of the other wind turbines. The adaptive procedure with resource tightness (APRT) method turned out to be the best method in terms of obtaining a more realistic schedule in this case study. Finally, FMEA was simultaneously applied with APRT.

Findings

Applying the hybrid method to the scheduling of the wind turbines, yielded the more realistic schedule than traditional.

Research limitations/implications

The proposed hybrid APRT-FMEA algorithm was implemented on a real wind farm construction project which was completed with 37 percent shorter duration than the initial estimation; in spite of the initial estimation of 142 days, the project completed in 103 days.

Practical implications

Introducing and implementing a new algorithm which is a combination of buffer sizing algorithms and one of the well-known and mostly used risk assessment methods in order to provide the more realistic project schedule in the construction of wind turbines.

Originality/value

Introducing and implementing a novel algorithm which is a combination of conventional buffer sizing method and one of the efficient risk assessment methods in order to make the schedule more realistic.

Details

Engineering, Construction and Architectural Management, vol. 26 no. 6
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 23 August 2019

Octaviano Rojas Luiz, Fernando Bernardi de Souza, João Victor Rojas Luiz, Daniel Jugend, Manoel Henrique Salgado and Sergio Luis da Silva

This study aims to analyze the relationship between the adherence to critical chain project management (CCPM) practices and the new product development performance, in terms of…

1313

Abstract

Purpose

This study aims to analyze the relationship between the adherence to critical chain project management (CCPM) practices and the new product development performance, in terms of the results of product development programs and product portfolio management (PPM).

Design/methodology/approach

A survey was conducted with 79 innovative companies operating in Brazil. Data were analyzed using correlation analysis and non-parametric tests.

Findings

Significant and positive correlations were found between CCPM adoption and the performance factors proposed. The adoption of CCPM offered stronger correlation with PPM performance than with the adoption of traditional methods. The results further indicate a possible indirect contribution of CCPM practices to the product development program by means of PPM improvement.

Originality/value

This study deepens the knowledge of the joint study between project management and new product development, by bringing empirical evidence that the adoption of specific practices suggested by CCPM is used by organizations with superior performance. Moreover, the results broaden CCPM literature by attesting that companies do not necessarily have to apply the CCPM approach in a formal and explicit way to obtain the performance results given. The analyses still have practical value when indicating which CCPM practices should be prioritized by managers seeking high performance in PPM.

Details

Journal of Business & Industrial Marketing, vol. 34 no. 8
Type: Research Article
ISSN: 0885-8624

Keywords

Article
Publication date: 3 August 2021

Tarek Salama, Ahmad Salah and Osama Moselhi

The purpose of this paper is to present a new method for project tracking and control of integrated offsite and onsite activities in modular construction considering practical…

Abstract

Purpose

The purpose of this paper is to present a new method for project tracking and control of integrated offsite and onsite activities in modular construction considering practical characteristics associated with this type of construction.

Design/methodology/approach

The design embraces building information modelling and integrates last planner system (LPS), linear scheduling method (LSM) and critical chain project management (CCPM) to develop tracking and control procedures for modular construction projects. The developed method accounts for constraints of resources continuity and uncertainties associated with activity duration. Features of proposed method are illustrated in a case example for tracking and control of modular projects.

Findings

Comparison between developed schedule and Monte Carlo simulation showed that baseline duration generated from simulation exceeds that produced by developed method by 12% and 10% for schedules with 50% and 90% confidence level, respectively. These percentages decrease based on interventions of members of project team in the LPS sessions. The case example results indicate that project is delayed 5% and experienced cost overrun of 2.5%.

Originality/value

Developed method integrated LPS, LSM and CCPM while using metrics for reliability assessment of linear schedules, namely, critical percent plan complete (PPCcr) and buffer index (BI). PPCcr and BI measure percentage of plan completion for critical activities and buffer consumption, respectively. The developed method provides a systematic procedure for forecasting look-ahead schedules using forecasting correction factor Δt and a newly developed tracking and control procedure that uses PPCcr and BI. Quantitative cost analysis is also provided to forecast and monitor project costs to prove the robustness of proposed framework.

Details

Construction Innovation , vol. 21 no. 4
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 10 May 2019

Tarek Salama and Osama Moselhi

The purpose of this paper is to present a newly developed multi-objective optimization method for the time, cost and work interruptions for repetitive scheduling while considering…

Abstract

Purpose

The purpose of this paper is to present a newly developed multi-objective optimization method for the time, cost and work interruptions for repetitive scheduling while considering uncertainties associated with different input parameters.

Design/methodology/approach

The design of the developed method is based on integrating six modules: uncertainty and defuzzification module using fuzzy set theory, schedule calculations module using the integration of linear scheduling method (LSM) and critical chain project management (CCPM), cost calculations module that considers direct and indirect costs, delay penalty, and work interruptions cost, multi-objective optimization module using Evolver © 7.5.2 as a genetic algorithm (GA) software, module for identifying multiple critical sequences and schedule buffers, and reporting module.

Findings

For duration optimization that utilizes fuzzy inputs without interruptions or adding buffers, duration and cost generated by the developed method are found to be 90 and 99 percent of those reported in the literature, respectively. For cost optimization that utilizes fuzzy inputs without interruptions, project duration generated by the developed method is found to be 93 percent of that reported in the literature after adding buffers. The developed method accelerates the generation of optimum schedules.

Originality/value

Unlike methods reported in the literature, the proposed method is the first multi-objective optimization method that integrates LSM and the CCPM. This method considers uncertainties of productivity rates, quantities and availability of resources while utilizing multi-objective GA function to minimize project duration, cost and work interruptions simultaneously. Schedule buffers are assigned whether optimized schedule allows for interruptions or not. This method considers delay and work interruption penalties, and bonus payments.

Details

Engineering, Construction and Architectural Management, vol. 26 no. 7
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 8 June 2015

Karessa Cullen and David W. Parker

The purpose of this paper is to explore benefits and issues of integrating the theory of constraints (TOC), resource-based view (RBV) and resource-dependence theory (RDT) with…

4235

Abstract

Purpose

The purpose of this paper is to explore benefits and issues of integrating the theory of constraints (TOC), resource-based view (RBV) and resource-dependence theory (RDT) with conventional project-based management frameworks.

Design/methodology/approach

Extant literature is used to develop a conceptual framework of an integrated model that will be tested for applied robustness. The model has been applied to published projects to identify its strengths and weaknesses.

Findings

The work shows important implications for improved success of projects from the use of TOC, RBV and RDT.

Research limitations/implications

While TOC, RBV and RDT are well established in the context of organization theory, there is limited application in project management. Moreover, the model has yet to be applied in the field. The hypotheses identified in this research are currently being tested using empirical investigation.

Practical implications

The research falls short in addressing some resources, e.g. innovation, tacit knowledge and decision-making methods in traditional project management context. Therefore, identifying these critical resources in future work and exploiting them as the means of improving project performance would enhance the success of project-based management.

Social implications

Project management is an emergent discipline and a project is temporary in nature. Therefore, new ideas and development of theories for project management practices are required. This innovative research, for example, may change the way projects are executed in future.

Originality/value

This paper examines the components of a successful project according to the iron triangle, i.e. scope, quality, time and cost. However, through the application of TOC, RBV and RDT into an integrated project-based management framework gives new insights to resources management.

Details

International Journal of Productivity and Performance Management, vol. 64 no. 5
Type: Research Article
ISSN: 1741-0401

Keywords

1 – 10 of over 42000