Article
Publication date: 6 September 2022

Murat Cevikbas, Ozan Okudan and Zeynep Işık

The purpose of this paper is to propose a disruption claim management (DCM) life cycle and a risk management framework to provide comprehensive guidance to construction…

Abstract

Purpose

The purpose of this paper is to propose a disruption claim management (DCM) life cycle and a risk management framework to provide comprehensive guidance to construction practitioners for facilitating effective and efficient DCM.

Design/methodology/approach

DCM life cycle was initially developed through a focus group discussion (FGD) with the participation of the construction practitioners who have diverse experiences about DCM. The life cycle is comprised of 6 phases and also includes proper reactions of the owners and contractors. Then, 42 risk factors that can impact the deliverables of DCM were identified through a literature review and an additional FGD session. This was then followed by a Fuzzy Analytical Hierarchy Process (FAHP) which was performed to evaluate the importance of each risk factor in terms of the factor's impact on the success of DCM. Additionally, consistency analysis was performed to further maximize the reliability of the results.

Findings

Findings revealed that a proactive and systematic approach should be adopted and DCM practices should be initiated before any disruption event is triggered. Accordingly, the proposed framework recommends DCM practices to be initiated early in the contract development phase since compensation for the disruption might be recovered only to the extent that the contract permits. The contract-related risks were given top priority by the experts so that the results of the fuzzy AHP analysis also verified the significance of the contract development phase. Besides contract-related risks, risks related to insufficient site observation, ignorance of the project team, cognitive bias and conflict of interest were determined as the most significant DCM risks, needing an urgent and sophisticated risk response plan. Lastly, results suggested that “Site observation and record-keeping” is the most formidable phase since the phase's implementation on a continuous basis could create unforeseen organizational challenges such as mismanagement of project records, especially in the dynamic and turbulent environment of the construction projects.

Originality/value

Disruption – which is caused mostly by change – is inevitable in construction projects due to their sophisticated nature. DCM, therefore, becomes crucial to compensate losses of contractors and eliminate or diminish the prolonged dispute resolution process. Existing studies, however, do not provide a comprehensive theoretical basis for the DCM life cycle and DCM life cycle's potential risks so that DCM life cycle's promising benefits can hardly be materialized. Thus, developing a DCM life cycle and associating DCM life cycle with risk management, this study is highly believed to make a promising theoretical contribution to the DCM domain since this is one of the earliest attempts in the literature. Additionally, this research provides construction practitioners with an insight into the effective implementation of DCM practices in construction projects.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 1
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 12 January 2023

Jia Jia Chang, Zhi Jun Hu and Changxiu Liu

In this study, a dynamic contracting model is developed between a venture capitalist (VC) and an entrepreneur (EN) to explore the influence of asymmetric beliefs regarding…

Abstract

Purpose

In this study, a dynamic contracting model is developed between a venture capitalist (VC) and an entrepreneur (EN) to explore the influence of asymmetric beliefs regarding output-relevant parameters, agency conflicts and complementarity on the VC's posterior beliefs through the EN's unobservable effort choices to influence the optimal dynamic contract.

Design/methodology/approach

The authors construct the contracting model by incorporating the VC's effort, which is ignored in most studies. Using backward induction and a discrete-time approximation approach, the authors solve the continuous-time contract design problem, which evolves into a nonlinear ordinary differential equation (ODE).

Findings

The optimal equity share that the VC provides to the EN decreases over time. In accordance with the empirical evidence, the EN's optimistic beliefs regarding the project's profitability positively affect its equity share. However, the interactions between the optimal equity share, project risk and both partners' degrees of risk aversion are not monotonic. Moreover, the authors find that the optimal equity share increases with the degree of complementarity, which indicates that the EN is willing to cooperate with the VC. This study’s results also show that the optimal equity shares at each time are interdependent if the VC is risk-averse and independent if the VC is risk-neutral.

Research limitations/implications

In conclusion, the authors highlight two potential directions for future research. First, the authors only considered a single VC, whereas in practice, a risk project may be carried out by multiple VCs, and it is interesting to discuss how the degree of complementarity affects the number of VCs that ENs contract. Second, the authors may introduce jumps and consider more general multivariate stochastic volatility models for output dynamics and analyze the characteristics of the optimal contracts. Third, further research can deal with other forms of discretionary output functions concerning complementarity, such as Cobb–Douglas and constant elasticity of substitution (See Varian, 1992).

Social implications

The results of this study have several implications. First, it offers a novel approach to designing dynamic contracts that are specific and easy to operate. To improve the complicated venture investment situation and abate conflict between contractual parties, this study plays a good reference role. Second, the synergy effect proposed in this study provides a theoretical explanation for the executive compensation puzzle in economics, in which managers are often “rewarded for luck” (Bertrand and Mullainathan, 2001; Wu et al., 2018). This result indicates a realistic perspective on financing and establishing cooperative relationships, which enhances the efficiency of venture investment. Third, from an empirical standpoint, one can apply this framework to study research and development (R&D) problems.

Originality/value

First, the authors introduce asymmetric beliefs and Bayesian learning to study the dynamic contract design problem and discuss their effects on equity share. Second, the authors incorporate the VC's effort into the contracting problem, and analyze the synergistic effect of effort complementarity on the optimal dynamic contract.

Details

Kybernetes, vol. 53 no. 4
Type: Research Article
ISSN: 0368-492X

Keywords

Article
Publication date: 3 May 2022

Olufisayo Adedokun and Temitope Egbelakin

Despite several research efforts tackling construction project risks globally, tertiary education building projects are not devoid of experiencing risks with cascading effects on…

Abstract

Purpose

Despite several research efforts tackling construction project risks globally, tertiary education building projects are not devoid of experiencing risks with cascading effects on projects. In the past decades, there has been increasing application of linear assessments of risks in construction risk management practices. However, this study aims to assess the influence of risk factors on the success of tertiary education building projects using a structural equation modelling approach. This study will further reinforce the risk factors that require attention because risk factors are not linear but interdependent.

Design/methodology/approach

A quantitative research method was undertaken in this study, where data collection was achieved via a structured questionnaire survey. In total, 452 questionnaires were administered to client representatives, consultants and contractors involved in executing tertiary education building projects across five public tertiary education institutions in Ondo State, Nigeria. Of 452 questionnaires, 279 were found usable for the analysis, implying a response rate of 61.73%. The Cronbach α test, average variances extracted and composite reliabilities values show high reliability and internal consistency of the instrument used for data gathering. Furthermore, the study adopted percentile, mean, correlation, regression analysis and structural equation modelling for analyzing the data collected upon which the study’s inferences were based.

Findings

The study found that three out of six criteria for measuring the success of tertiary education building projects were significantly affected by risk factors while using the structural equation modelling technique. With this non-linear method of assessment, completion to time was significantly impacted by environmental risk factors. In addition, safety performance was also significantly influenced by logistic, environmental and legal risk factors; furthermore, logistics, design and environmental risks significantly affected profit. However, completion to cost, standard/quality and end-user satisfaction was not significantly affected by the risk factors in tertiary education building projects.

Research limitations/implications

The quantitative data used for the analysis are limited to the tertiary education building projects from selected five tertiary education institutions in Ondo State; therefore, the results do not indicate all tertiary institutions in Nigeria. In addition, the findings are based on building projects that were procured through a competitive tendering arrangement only and thus considered a limitation for this study.

Practical implications

Not all the risks significantly influence the tertiary education building projects. Therefore, risk factors with a significant effect on the success indicators of tertiary education building projects should be prioritized for a successful project. While risk factors have not affected the completion to cost per se, the study implies that the resultant effect of risks on other success indicators could have a cascading effect on these projects in terms of cost and time overruns. These results may assist during the project risk management while also addressing complexity and uncertainty to avoid chaos in a tertiary education building projects.

Originality/value

The study found significant construction risk factors impacting the success of tertiary education building projects using a non-linear methodology, an extension beyond the usual linear method of assessment of risk impacts on the project performance.

Details

Journal of Facilities Management , vol. 22 no. 1
Type: Research Article
ISSN: 1472-5967

Keywords

Article
Publication date: 21 February 2024

Hassan Mohamed

The purpose of this paper is to examine the supervening loss of inter-organisational trust in long-term commercial contracts. The underlying research question is whether contract…

Abstract

Purpose

The purpose of this paper is to examine the supervening loss of inter-organisational trust in long-term commercial contracts. The underlying research question is whether contract law – the legal institution regulating economic exchanges – should intervene and enable a party to a long-term commercial contract to extricate itself from a situation where a relationship of trust has broken down irretrievably.

Design/methodology/approach

This paper uses doctrinal methodology and theoretical conceptualisation to answer the underlying research question. The legal instrument chosen for analysis purposes is the UNIDROIT Principles of International Commercial Contracts. This paper also draws on extant literature on inter-organisational trust (including conceptual and empirical studies) to support the arguments and propositions. Furthermore, this study proceeds to assess the substantive justifiability of the proposed remedial measure using four normative values: legal certainty and predictability, protection of the performance interest, economic efficiency and the preservation of the relation.

Findings

The central argument put forward in this paper is the reformulation of draft Article 6.3.1 proposed by the UNIDROIT Working Group on Long-Term Contracts, which confers a novel right to terminate for a compelling reason. This paper presents a multidimensional model of inter-organisational trust that would serve as the conceptual framework for the proposed reformulation of the provision and establishes a coherent juridical basis for the legal solution that would accord with the Principles of International Commercial Contracts’ general remedial scheme. As for the normative assessment, this paper demonstrates that the proposed remedial measure would significantly promote efficient outcomes and positively serve the norms of legal certainty, protection of the performance interest and the preservation of the relation.

Originality/value

This paper addresses the lacuna in current legal scholarship in relation to the adverse socio-economic effects following trust violation and deterioration in inter-organisational relationships. Additionally, the propositions and findings should contribute to the workings of the UNIDROIT in adopting new rules and principles that would serve the special requirements of cross-border trade.

Details

International Journal of Law and Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1754-243X

Keywords

Article
Publication date: 31 October 2023

Hong Zhou, Binwei Gao, Shilong Tang, Bing Li and Shuyu Wang

The number of construction dispute cases has maintained a high growth trend in recent years. The effective exploration and management of construction contract risk can directly…

Abstract

Purpose

The number of construction dispute cases has maintained a high growth trend in recent years. The effective exploration and management of construction contract risk can directly promote the overall performance of the project life cycle. The miss of clauses may result in a failure to match with standard contracts. If the contract, modified by the owner, omits key clauses, potential disputes may lead to contractors paying substantial compensation. Therefore, the identification of construction project contract missing clauses has heavily relied on the manual review technique, which is inefficient and highly restricted by personnel experience. The existing intelligent means only work for the contract query and storage. It is urgent to raise the level of intelligence for contract clause management. Therefore, this paper aims to propose an intelligent method to detect construction project contract missing clauses based on Natural Language Processing (NLP) and deep learning technology.

Design/methodology/approach

A complete classification scheme of contract clauses is designed based on NLP. First, construction contract texts are pre-processed and converted from unstructured natural language into structured digital vector form. Following the initial categorization, a multi-label classification of long text construction contract clauses is designed to preliminary identify whether the clause labels are missing. After the multi-label clause missing detection, the authors implement a clause similarity algorithm by creatively integrating the image detection thought, MatchPyramid model, with BERT to identify missing substantial content in the contract clauses.

Findings

1,322 construction project contracts were tested. Results showed that the accuracy of multi-label classification could reach 93%, the accuracy of similarity matching can reach 83%, and the recall rate and F1 mean of both can reach more than 0.7. The experimental results verify the feasibility of intelligently detecting contract risk through the NLP-based method to some extent.

Originality/value

NLP is adept at recognizing textual content and has shown promising results in some contract processing applications. However, the mostly used approaches of its utilization for risk detection in construction contract clauses predominantly are rule-based, which encounter challenges when handling intricate and lengthy engineering contracts. This paper introduces an NLP technique based on deep learning which reduces manual intervention and can autonomously identify and tag types of contractual deficiencies, aligning with the evolving complexities anticipated in future construction contracts. Moreover, this method achieves the recognition of extended contract clause texts. Ultimately, this approach boasts versatility; users simply need to adjust parameters such as segmentation based on language categories to detect omissions in contract clauses of diverse languages.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 3 November 2023

Qiuwen Ma, Sai On Cheung and Shan Li

Integrated project delivery (IPD) project that does not use multiparty agreement is identified as IPD-ish. The use of IPD-ish arrangement by incorporating integration practices in…

Abstract

Purpose

Integrated project delivery (IPD) project that does not use multiparty agreement is identified as IPD-ish. The use of IPD-ish arrangement by incorporating integration practices in conventional contract can be viewed as the part of the adoption process of IPD. Moreover, inappropriate integration practices invite new forms of risks and the absence of multiparty agreement adds to the challenges of risk management in IPD-ish projects. This study discusses such challenges and proposes the use of joint risk management to address the potential pitfalls in IPD-ish arrangement.

Design/methodology/approach

A mixed research method was applied. First, the criticality of IPD-ish general and integration-specific risks was examined through a survey. Second, a real IPD-ish project was used to exemplify the use of joint risk management (JRM) to manage IPD-ish risks.

Findings

Two types of risks, namely integration risks (IRs) and general risks (GRs), are identified in IPD-ish projects. Two major findings for the IRs: (1) the most critical IRs are related to unbalanced incentivization and inefficient multidisciplinary teams; and (2) only team formation related pre-contract JRM strategies affect IRs. As for the GRs, the most critical ones are associated with design issues and can be effectively mitigated by post-contract JRM.

Originality/value

Using IPD-ish arrangement is an inevitable part of implementation of full IPD. This happens as many change-averse owners would like to test the integration principles using a conventional contract that they are familiar with. In fact, success in IPD-ish would pave the path for further adoption of IPD. This study offers insight into categorization of risks in IPD-ish projects. Appropriate use of post-contract and organization related pre-contract JRM would improve the chance of teasing out the values of IPD through IPD-ish arrangements. Care should be taken to introduce some contracting integration initiatives, such as risk/reward sharing incentive.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 21 June 2022

Jamshid Ali Turi and Muddassar Sarfraz

Political risk devastates social and economic developmental projects. Countries with political stability attract foreign direct investment (FDI) and engage domestic investment…

Abstract

Purpose

Political risk devastates social and economic developmental projects. Countries with political stability attract foreign direct investment (FDI) and engage domestic investment corporations. This study aims to investigate the impact of perceived organizational politics and political risk on project success, considering the moderating and mediating roles of ethical leadership and the psychological contract.

Design/methodology/approach

A multimethod approach was adopted in this work that includes an exploratory content analysis to confirm the latent factors of the variables under study. A measurement scale was developed and tested for perceived organizational politics, political risk, the psychological contract and ethical leadership in the projectized environment. Lastly, cross-sectional data were collected from the senior-level professionals of the projectized organizations and analyzed using SPSS and SMARTPLS techniques.

Findings

The findings indicate that ethical leadership and the psychological contract mitigate political risk. The study recommends that developing countries emphasize well-defined policies and standard operating procedures to streamline the project design and execution processes.

Research limitations/implications

The study claims that ethical leaders can play a vital role in mitigating perceived organizational politics and political risk and maximizing project value through the psychological contract.

Originality/value

Although previous research predicts that ethical leadership has very little effect on project success, this study provides critical theoretical and practical contributions to research on project success regarding leadership expertise and the psychological contract.

Details

Kybernetes, vol. 52 no. 11
Type: Research Article
ISSN: 0368-492X

Keywords

Article
Publication date: 2 April 2024

Rick Forster, Andrew Lyons, Nigel Caldwell, Jennifer Davies and Hossein Sharifi

The study sets out to demonstrate how a lifecycle perspective on complex, public-sector procurement projects can be used for making qualitative assessments of procurement policy…

Abstract

Purpose

The study sets out to demonstrate how a lifecycle perspective on complex, public-sector procurement projects can be used for making qualitative assessments of procurement policy and practice and reveal those procurement capabilities that are most impactful for operating effectively.

Design/methodology/approach

Agency theory, institutional theory and the lifecycle analysis technique are combined to abductively develop a framework to identify, analyse and compare complex procurement policies and practices in public sector organisations. Defence is the focal case and is compared with cases in the Nuclear, Local Government and Health sectors.

Findings

The study provides a framework for undertaking a lifecycle analysis to understand the challenges and capabilities of complex, public-sector buyers. Eighteen hierarchically-arranged themes are identified and used in conjunction with agency theory and institutional theory to explain complex procurement policy and practice variation in some of the UK’s highest-profile public buyers. The study findings provide a classification of complex buyers and offer valuable guidance for practitioners and researchers navigating complex procurement contexts.

Originality/value

The lifecycle approach proposed is a new research tool providing a bespoke application of theory by considering each lifecycle phase as an individual but related element that is governed by unique institutional pressures and principal-agent relationships.

Details

International Journal of Operations & Production Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0144-3577

Keywords

Article
Publication date: 15 August 2023

Badar Latif, James Gaskin, Nuwan Gunarathne, Robert Sroufe, Arshian Sharif and Abdul Hanan

Debates regarding climate change risk perception (CCRP), particularly its scale and impact on social and environmental sustainability, have continued for decades. CCRP is…

Abstract

Purpose

Debates regarding climate change risk perception (CCRP), particularly its scale and impact on social and environmental sustainability, have continued for decades. CCRP is experiencing a renaissance with an increased focus on environmentally relevant behaviors to mitigate the effects of climate change. However, CCRP lacks investigation from the employee perspective. Supported by the social exchange and value–belief–norm theories, this study aims to address the impact of employees’ CCRP on their proenvironmental behavior (PEB) via the moderating roles of environmental values and psychological contract breach.

Design/methodology/approach

The nonprobability convenience sampling technique was used to collect survey data from a sample of 299 employees across 138 manufacturing firms in Pakistan.

Findings

The results show that employees’ CCRP positively impacts their PEB and that this relationship is moderated by their environmental values and psychological contract breach. Specifically, environmental values strengthen the CCRP–PEB relationship, while psychological contract breach weakens it.

Practical implications

The findings of the study emphasize useful guidance for managers and practitioners as a future avenue to restructure the climate change framework by emphasizing the conditions (i.e. environmental values and psychological contract breach). In doing so, the study is beneficial for managers and practitioners in helping to increase employees’ PEB through the development of climate change action plans.

Originality/value

To the best of the authors’ knowledge, this study is one of the first investigations into CCRP–employees’ PEB nexus in the developing country context. The study incorporates social exchange and value–belief–norm theory, which serve as the CCRP’s theoretical underpinnings. The findings advance the new knowledge about a firm’s social responsibility to achieve the sustainable development goals outlined in the UN’s 2030 Agenda.

Details

Social Responsibility Journal, vol. 20 no. 3
Type: Research Article
ISSN: 1747-1117

Keywords

Open Access
Article
Publication date: 23 December 2022

Rouzbeh Shabani, Tobias Onshuus Malvik, Agnar Johansen and Olav Torp

Uncertainty management (UM) in projects has been a point of attention for researchers for many years. Research on UM has mainly been aimed at uncertainty analyses in the front-end…

2039

Abstract

Purpose

Uncertainty management (UM) in projects has been a point of attention for researchers for many years. Research on UM has mainly been aimed at uncertainty analyses in the front-end and managing uncertainty in the construction phase. In contrast, UM components in the design phase have received less attention. This research aims to improve knowledge about the key components of UM in the design phase of large road projects.

Design/methodology/approach

This study adopted a literature review and case study. The literature review was used to identify relevant criteria for UM. These criteria helped to design the interview guide. Multiple case study research was conducted, and data were collected through document study and interviews with project stakeholders in two road projects. Each case's owners, contractors and consultants were interviewed individually.

Findings

The data analysis obtained helpful information on the involved parties, process and exploit tools and techniques during the design phase. Johansen's (2015) framework [(a) human and organisation, (b) process and (c) tools and techniques)] was completed and developed by identifying relevant criteria (such as risk averse or risk-taker, culture and documentation level) for each component. These criteria help to measure UM performance. The authors found that owners and contractors are major formal UM actors, not consultants. Empirical data showed the effectiveness of Web-based tools in UM.

Research limitations/implications

The studied cases were Norwegian, and this study focussed on uncertainties in the project's design phase. Relevant criteria did not cover all the criteria for evaluating the performance of UM. Qualitative evaluation of criteria allows further quantitative analysis in the future.

Practical implications

This paper gave project owners and managers a better understanding of relevant criteria for measuring UM in the owners and managers' projects. The paper provides policy-makers with a deeper understanding of creating rigorous project criteria for UM during the design phase. This paper also provides a guideline for UM in road projects.

Originality/value

This research gives a holistic evaluation of UM by noticing relevant criteria and criteria's interconnection in the design phase.

Details

International Journal of Managing Projects in Business, vol. 16 no. 8
Type: Research Article
ISSN: 1753-8378